Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
VENTANA TELEVISION, INC. Doing Business As: HSN/Ventana Television Inc. |
Eric Yonkin 1 HSN Drive St. Petersburg, FL 33729 United States |
+1 (727) 872-7443 | EASnotice@hsn.net | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Ari Q. Fitzgerald Hogan Lovells US LLP |
555 Thirteenth Street, NW Washington, DC 20004 United States |
+1 (202) 637-2257 | ari.fitzgerald@hoganlovells.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | To operate on the post-repack channel, the station requires a new transmitter, antenna, and transmission line, all of which must be received and installed. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | TXUP2500 LD | |
Year | 2008 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 0.8 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | EC702HP-BB2 D18 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 1.5 kW | |
Justification for New Transmitter | The existing transmitter is incapable of generating the necessary power level. |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | Yes | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
Invoice No. S10566-1 Hitachi - W18ET-D, SYS EC702HP BB2 D18 |
Transmitter |
Invoice No. 20200423 NFB Consulting - Software:Statmon:STC-PLUGIN PO No.HN813170009 |
SNMP plugin to adapt existing remote control to operate new transmitters. Previous transmitter control system was serial; new one requires SNMP. |
Invoice No. S10566-2 Hitachi - W18ET-D, SYS EC702HP BB2 D18 |
Transmitter |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 10.0 kW | |
Manufacturer | ||
Model | PSILP16AN-20 | |
Year | 2012 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | CS-2030-G-16 (E/P) | |
Year | 2020 | |
Justification for New Antenna | Previous Channel 20 antenna would not work on channel 18. Very different directional plan. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | No |
Name | Description |
---|---|
Invoice No. C2245-B Micronetixx - 16 bay CS-2030-G-16 EP |
CS-2030-G-16 (E/P) - antenna installation |
Invoice No. C225-C, CS-2030-G-16 EP |
CS-2030-G-16 (E/P) - Freight Costs |
Invoice No. C2245-A Micronetixx - 16 bay CS-2030-G-16 EP |
CS-2030-G-16 (E/P) - antenna installation |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Foam | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 450 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Flexible Air | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 450 feet per run | |
Justification for New Transmission Line | The existing transmission line is foam-filled. The new antenna requires pressurization, so a gas-filled line is required to pressurize the antenna power divider. | |
Interior RF Systems | Does the Installation of the Transmission Line require an additional or replacement Inside RF system including switching, patch panels, and dehydrators? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Ownership | Leased | |
Is this tower consider Complex? | Candelabra | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1035176 | |
Coordinates (NAD83) | Latitude (NAD83) | 33° 27' 37.0" N- |
Longitude (NAD83) | 086° 51' 07.0" W- | |
Overall Structure Height | 708.98 feet | |
Support Structure Height | 664.03 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 939.95 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | WTTO, INC | |
Date Constructed | 12/01/1995 |
Facility ID | Call Sign | Service |
---|---|---|
730 | WBHJ | FM |
150836 | W222BK | FX |
Users |
---|
Two-Way Service |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Tower mapping and report for structural engineer |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Serious Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Candelabra |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Invoice No. SIN007596 FDH Infrastucture - Broadcast Structural Services |
Structural engineering study for a guyed or free standing tower, 50% down payment Second study required to include necessary mounting structure for antenna. |
Invoice No. SIN007600 FDH Infrastucture - Construction services |
Tower crew to remove old antenna, then install structural reinforcement steel on tower, antenna mounting, coaxial jumper, and new antenna. Includes structural steel reinforcement materials. 50% down payment. |
Invoice No. SIN008082 FDH Infrastucture - Construction services |
Tower crew to remove old antenna, then install structural reinforcement steel on tower, antenna mounting, coaxial jumper, and new antenna. Includes structural steel reinforcement materials. 50% final payment. |
Invoice No. SIN008466 FDH Infrastucture - Construction services |
Additional tower crew time and RF hazard suit rental due to high RF fields found on tower. |
Invoice No. SIN005558 FDH Infrastucture - Broadcast Structural Services |
Structural engineering study for a guyed or free standing tower, 50% final payment |
Invoice No. SIN006612 FDH Infrastucture - Broadcast Structural Services |
Design and generate installation drawings for necessary tower modifications. |
Invoice No. SIN003795 FDH Infrastucture - Broadcast Structural Services |
Structural engineering study for a guyed or free standing tower, 50% down payment |
Invoice No. SIN007692 FDH Infrastucture - Broadcast Structural Services |
Structural engineering study for a guyed or free standing tower, 50% final payment Second study required to include necessary mounting structure for antenna. |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | No |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | No |
Prepare engineering section of Form FCC Construction Permit Application | No | |
Prepare engineering section of Form FCC License to Cover Application | No | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | No |
Prepare and file Form FCC License to Cover Application | No | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | No | |
Additional Field Engineering Service | Yes | |
Number of Days | 5 | |
Justification | The station requires a comprehensive coverage verification via field study to confirm that the station's post repack coverage is accurate. The station will be contracting a third party that performs field studies with the use of unmanned aerial vehicles. |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | Yes | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Name | Description |
---|---|
SHIP-HANDLE W18ET-D TO BE INVOICED, POHN813163381 |
SHIP-HANDLE W18ET-D TO BE INVOICED, POHN813163381 |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $184,974.00 | $184,974.00 | N/A | $49,788.20 | N/A |
Total for all systems | $527,306.20 | $499,831.20 | N/A | $135,087.20 | N/A |
Primary Transmitter EC702HP-BB2 D18 | $184,974.00 | $184,974.00 | $49,788.20 | ||
Transmitter Building Site Survey/Installation | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | $84,000.00 | $84,000.00 | N/A | $49,788.20 | N/A |
Invoice No. 20200423 NFB Consulting - Software:Statmon:STC-PLUGIN PO No.HN813170009 | $450.00 | $450.00 | N/A | $0.00 | N/A |
Invoice No. S10566-2 Hitachi - W18ET-D, SYS EC702HP BB2 D18 | $45,262.00 | $45,262.00 | N/A | $0.00 | N/A |
Invoice No. S10566-1 Hitachi - W18ET-D, SYS EC702HP BB2 D18 | $45,262.00 | $45,262.00 | N/A | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
Transmitter Building Site Survey/Installation | Information not provided. |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | |
Invoice No. 20200423 NFB Consulting - Software:Statmon:STC-PLUGIN PO No.HN813170009 | |
Invoice No. S10566-2 Hitachi - W18ET-D, SYS EC702HP BB2 D18 | |
Invoice No. S10566-1 Hitachi - W18ET-D, SYS EC702HP BB2 D18 |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $68,993.29 | $68,993.29 | N/A | $0.00 | N/A |
Total for all systems | $527,306.20 | $499,831.20 | N/A | $135,087.20 | N/A |
Primary Antenna CS-2030-G-16 (E/P) | $68,993.29 | $68,993.29 | $0.00 | ||
Invoice No. C2245-A Micronetixx - 16 bay CS-2030-G-16 EP | $22,700.00 | $22,700.00 | N/A | $0.00 | N/A |
Invoice No. C225-C, CS-2030-G-16 EP | $893.29 | $893.29 | N/A | $0.00 | N/A |
UHF-Low Power, Side Mount, Slotted Coaxial, 15.0kW input, Elliptical | $22,700.00 | $22,700.00 | N/A | $0.00 | N/A |
Invoice No. C2245-B Micronetixx - 16 bay CS-2030-G-16 EP | $22,700.00 | $22,700.00 | N/A | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
Invoice No. C2245-A Micronetixx - 16 bay CS-2030-G-16 EP | |
Invoice No. C225-C, CS-2030-G-16 EP | |
UHF-Low Power, Side Mount, Slotted Coaxial, 15.0kW input, Elliptical | |
Invoice No. C2245-B Micronetixx - 16 bay CS-2030-G-16 EP |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $14,850.00 | $14,850.00 | N/A | $0.00 | N/A |
Total for all systems | $527,306.20 | $499,831.20 | N/A | $135,087.20 | N/A |
Primary Transmission Line | $14,850.00 | $14,850.00 | $0.00 | ||
Flexible Air Transmission Line - dielectric, 1 5/8" | $14,850.00 | $14,850.00 | N/A | $0.00 | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $190,223.00 | $190,223.00 | N/A | $85,299.00 | N/A |
Total for all systems | $527,306.20 | $499,831.20 | N/A | $135,087.20 | N/A |
Primary Tower TOWER | $190,223.00 | $190,223.00 | $85,299.00 | ||
Invoice No. SIN008082 FDH Infrastucture - Construction services | $34,462.00 | $34,462.00 | N/A | $0.00 | N/A |
Invoice No. SIN006612 FDH Infrastucture - Broadcast Structural Services | $2,200.00 | $2,200.00 | N/A | $0.00 | N/A |
Invoice No. SIN003795 FDH Infrastucture - Broadcast Structural Services | $2,875.00 | $2,875.00 | N/A | $0.00 | N/A |
Invoice No. SIN008466 FDH Infrastucture - Construction services | $6,425.00 | $6,425.00 | N/A | $0.00 | N/A |
Invoice No. SIN005558 FDH Infrastucture - Broadcast Structural Services | $2,875.00 | $2,875.00 | N/A | $0.00 | N/A |
Invoice No. SIN007600 FDH Infrastucture - Construction services | $34,462.00 | $34,462.00 | N/A | $0.00 | N/A |
Invoice No. SIN007596 FDH Infrastucture - Broadcast Structural Services | $1,000.00 | $1,000.00 | N/A | $0.00 | N/A |
Serious tower reinforcement/modifications | $15,000.00 | $15,000.00 | N/A | $6,425.00 | N/A |
Tower mapping and report for structural engineer | $21,000.00 | $21,000.00 | N/A | $9,950.00 | N/A |
Complex Tower (includes, e.g., towers with candelabras and/or stacked antennas) | $68,924.00 | $68,924.00 | N/A | $68,924.00 | N/A |
Invoice No. SIN007692 FDH Infrastucture - Broadcast Structural Services | $1,000.00 | $1,000.00 | N/A | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
Invoice No. SIN008082 FDH Infrastucture - Construction services | |
Invoice No. SIN006612 FDH Infrastucture - Broadcast Structural Services | |
Invoice No. SIN003795 FDH Infrastucture - Broadcast Structural Services | |
Invoice No. SIN008466 FDH Infrastucture - Construction services | |
Invoice No. SIN005558 FDH Infrastucture - Broadcast Structural Services | |
Invoice No. SIN007600 FDH Infrastucture - Construction services | |
Invoice No. SIN007596 FDH Infrastucture - Broadcast Structural Services | |
Serious tower reinforcement/modifications | |
Tower mapping and report for structural engineer | |
Complex Tower (includes, e.g., towers with candelabras and/or stacked antennas) | |
Invoice No. SIN007692 FDH Infrastucture - Broadcast Structural Services |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $65,810.00 | $38,335.00 | N/A | $0.00 | N/A |
Total for all systems | $527,306.20 | $499,831.20 | N/A | $135,087.20 | N/A |
Outside Professional Services | $65,810.00 | $38,335.00 | $0.00 | ||
Additional Field Engineering Service, 5 Days | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $52,600.00 | $25,125.00 | N/A | $0.00 | N/A |
Form 399 assistance or other Program Management costs | $1,500.00 | $1,500.00 | N/A | N/A | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,710.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Additional Field Engineering Service, 5 Days | Information not provided. |
Comprehensive coverage verification via field study, if needed | |
Form 399 assistance or other Program Management costs | Information not provided. |
Prepare/ Review 399 reimbursement form | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $2,455.91 | $2,455.91 | N/A | $0.00 | N/A |
Total for all systems | $527,306.20 | $499,831.20 | N/A | $135,087.20 | N/A |
Other Expenses | $2,455.91 | $2,455.91 | $0.00 | ||
SHIP-HANDLE W18ET-D TO BE INVOICED, POHN813163381 | $920.91 | $920.91 | N/A | $0.00 | N/A |
Equipment Storage | $1,200.00 | $1,200.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $527,306.20 | $499,831.20 | $135,087.20 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | Yes |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Eric Yonkin Associate General Counsel, Legal 12/06/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Eric Yonkin Associate General Counsel, Legal 12/06/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Eric Yonkin Associate General Counsel, Legal 12/06/2022 |