Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
NW COMMUNICATIONS OF PHOENIX, INC. |
Ann West Bobeck PO Box 20011 Suite 200 West WASHINGTON, DC 20001 United States |
+1 (202) 824-6503 | ann.bobeck@fox.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Joseph L. Snelson , Jr. . Technical Consultant Meintel, Sgrignoli and Wallace |
1282 Smallwood Drive Suite 372 Waldorf, MD 20603 United States |
+1 (281) 466-2080 | joe.snelson@mswdtv.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Station has already transitioned to its post-repack channel. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Retune Existing |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | Larcan |
Model | MXIG25 | |
Year | 2014 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 100 W |
Section | Question | Response |
---|---|---|
New Mask Filter | Does the transmitter require a new mask filter? | No |
New Exciter | Is a new exciter needed? | No |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 0.61 kW | |
Manufacturer | ||
Model | ALP4L1-HSW | |
Year | 2005 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | Yes | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels/Bays | 12 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 862.00 MHz | |
Design power capacity in use | 100.0 % | |
ERP: | 0.61 kW | |
Manufacturer | ||
Model | 4x3 75010210 | |
Year | 2018 | |
Justification for New Antenna | Former antenna cannot be retuned to post-repack channel |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 2 | |
Frequencies of channels supported | RF channel | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | No |
Power Dividers | Does the panel antenna require power dividers? | No |
Cable Harness | Does the panel antenna require cable harness? | No |
RF Channel Number |
---|
28 |
26 |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Foam | |
Diameter | 7/8 inches | |
Number of parallel runs | 1 | |
Length | 40 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Flexible Foam | |
Diameter | 7/8 inches | |
Number of parallel runs | 1 | |
Length | 40 feet per run | |
Justification for New Transmission Line | Needed to minimize downtime. New antenna and line placed on tower at same time before cut over. | |
Interior RF Systems | Does the Installation of the Transmission Line require an additional or replacement Inside RF system including switching, patch panels, and dehydrators? | Yes |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Ownership | Leased | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
Coordinates (NAD83) | Latitude (NAD83) | 35° 15' 25.0" N- |
Longitude (NAD83) | 111° 35' 51.8" W- | |
Overall Structure Height | 30.48 feet | |
Support Structure Height | 30.48 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 2815.25 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | El Paso Natural Gas | |
Date Constructed | 01/01/2005 |
Facility ID | Call Sign | Service |
---|---|---|
68896 | K28CW-D | LPT |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | No |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | Yes | |
Number of Days | 5 | |
Justification | Field tuning of filters. Final proof of performance |
Name | Description |
---|---|
Project Management |
Project Management and Technical Engineering |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | Yes |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Name | Description |
---|---|
Project Management |
Technical and Project Management |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $11,000.00 | $5,000.00 | N/A | $0.00 | N/A |
Total for all systems | $126,185.00 | $41,528.34 | N/A | $830.00 | N/A |
Primary Transmitter MXIG25 | $11,000.00 | $5,000.00 | $0.00 | ||
Retune - UHF and VHF - minor re-channel issues | $11,000.00 | $5,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $30,400.00 | $4,363.34 | N/A | $0.00 | N/A |
Total for all systems | $126,185.00 | $41,528.34 | N/A | $830.00 | N/A |
Primary Antenna 4x3 75010210 | $30,400.00 | $4,363.34 | $0.00 | ||
1 kW UHF Combiner (per channel) | $9,400.00 | $3,000.00 | N/A | N/A | N/A |
UHF Broadband panel antenna (per panel), horizontally-polarized | $21,000.00 | $1,363.34 | N/A | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
1 kW UHF Combiner (per channel) | Information not provided. |
UHF Broadband panel antenna (per panel), horizontally-polarized |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $2,940.00 | $3,500.00 | N/A | $0.00 | N/A |
Total for all systems | $126,185.00 | $41,528.34 | N/A | $830.00 | N/A |
Primary Transmission Line | $2,940.00 | $3,500.00 | $0.00 | ||
Interior RF Systems: Inside RF system including switching, patch panels and dehydrators | $2,500.00 | $2,500.00 | Installation of filters | N/A | N/A |
Flexible Foam Transmission Line - dielectric, 7/8" | $440.00 | $1,000.00 | New line required to feed new antenna and avoid off air time prior to switching over to repack facility. | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $56,190.00 | $5,000.00 | N/A | $0.00 | N/A |
Total for all systems | $126,185.00 | $41,528.34 | N/A | $830.00 | N/A |
Primary Tower TOWER | $56,190.00 | $5,000.00 | $0.00 | ||
Tower Rigging Short Tower (less than 500') | $56,190.00 | $5,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $19,360.00 | $17,830.00 | N/A | $830.00 | N/A |
Total for all systems | $126,185.00 | $41,528.34 | N/A | $830.00 | N/A |
Outside Professional Services | $19,360.00 | $17,830.00 | $830.00 | ||
Project Management | $830.00 | $830.00 | N/A | $830.00 | N/A |
Additional Field Engineering Service, 5 Days | $4,000.00 | $4,000.00 | Inside building tuning bandpass and mask filter. | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for displacement application | $1,800.00 | $1,800.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,000.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,000.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,500.00 | N/A | N/A | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $3,262.50 | $2,000.00 | N/A | N/A | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,700.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Project Management | |
Additional Field Engineering Service, 5 Days | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for displacement application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Negotiation of lease and other matters for shared locations | Information not provided. |
Prepare/ Review 399 reimbursement form | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $6,295.00 | $5,835.00 | N/A | $0.00 | N/A |
Total for all systems | $126,185.00 | $41,528.34 | N/A | $830.00 | N/A |
Other Expenses | $6,295.00 | $5,835.00 | $0.00 | ||
Project Management | $0.00 | $0.00 | N/A | $0.00 | N/A |
FCC Filing Fees - Form 2100 Major change CP application | $4,960.00 | $4,500.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $1,000.00 | $1,000.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $126,185.00 | $41,528.34 | $830.00 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Angelo Servedio SVP Controller 09/16/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Angelo Servedio SVP Controller 09/16/2022 |