Facility ID:
17037
Service:
DTV
Call Sign:
KDFI
Channel:
27 (UHF)
File Number:
0000027215
FRN:
0013522339
Date Submitted:
09/15/2022

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

NW COMMUNICATIONS OF TEXAS, INC.

Joseph M. Di Scipio

400 N. CAPITOL STREET, NW

SUITE 890

WASHINGTON, DC 20001

United States

+1 (202) 824-6522 Joe.Discipio@fox.com Corporation

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

Dennis Wallace

Managing Partner

Meintel, Sgrignoli & Wallace, LLC

Dennis Wallace

1282 Smallwood Drive

Suite 372

Waldorf, MD 20603

United States

+1 (202) 251-7589 Dennis.Wallace@mswdtv.com

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan Station KDFI is still working on its transition plan. However, the initial plan would be to install an interim facility to broadcast on the post-auction channel. Then replace the existing antenna and transmission line with new antenna and tx line.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model DCXP-2
Year 2004
Type Inductive Output Tube
IOT Power Type Two
Power Capacity 30 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model THU9-48
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 73.5 kW
Justification for New Transmitter IOT Tube type transmitters no longer available by the time purchase was to be made. See 1118_servicebulletin180402 and 1118_Quote Rohde and Schwarz.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service Yes
Description Comprehensive services entrance, panels, conduit and wiring.
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? Yes
Size 800.0 square feet
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Terminal Equipment

Various broadcast related equipment

Filter

New Rohde and Schwarz filter to replace faulty ERI filter

UPS

UPS, Commissioning, Shipping

Additional Installation Costs

Unanticipated additional installation costs

HVAC Modifications

Rework of current HVAC system

Interim Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Interim
Description of Use N/A
Change Type Purchase
Manufacturer
Model TBD
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 30 kW
Justification for New Transmitter Interim Transmitter for operation at interim facility site while existing site is modified. ATC will decommission existing antenna waveguide run in early 2018.

Interim Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service No
Description N/A
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? Yes
Size 800.0 square feet
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A
Inside RF System Is an additional interior RF system required to support this interim transmitter? No

Interim Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Leased
Owner ATC
Site N/A
Is the existing antenna shared with another station or stations? Yes
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? Yes
Existing Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Bottom
Polarization Horizontal
Type Broadband Panel
Number of Stations Supported 2
Number of Panels 48
Design power capacity in use 35.0 %
Lower Limit 602.00 MHz
Upper Limit 644.00 MHz
Other Antenna Type N/A
ERP: 1000.0 kW
Manufacturer
Model A/CUK40671/1
Year 2008

Facility ID's and Call Signs of all stations with whom the antenna is shared.

Facility ID Call Sign
68834 KPXD-TV

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Types Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Elliptical
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 1000.0 kW
Manufacturer
Model ATW28H3-ETC1-27H
Year 2019
Justification for New Antenna Relocation was necessary to meet repack timeline. See attached 1118_Revised Narrative and Composite quote 1118_Quote ERI

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna?
Type
Number of channels supported N/A
Frequencies of channels supported N/A
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? N/A
Elbow Complex Do you require the separate purchase of the Elbow Complex? No
Broadband or Single Channel? N/A
Feed Line Size N/A
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna?
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Elbows

Elbows, reducer, freight

Spinner System Install

Installation of spinner AMS system

Antenna Installation

Installation of antenna

Structural Services Custom 55ft Spine

Custom build of spine for antenna to rest on

Interim Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Interim
Description of Use N/A
Change Type Purchase New
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Bottom
Polarization Horizontal
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 829.0 kW
Manufacturer
Model TBD
Year 2017
Justification for New Antenna Interim Antenna for operation while main antenna transmission line is removed and replaced by ATC. Antenna manufacturer and model number is yet to be finalized.

Interim Antenna

Back to Top

Other Antenna Costs

Section Question Response
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? B
Feed Line Size 6 1/8 inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for an antenna?
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? Yes
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Interim Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Peter Eckman Services

Peter Eckman services and parts for preliminary work on antenna system.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Leased
Owner ATC
Site N/A
Is the existing transmission line shared with another station or stations? Yes
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer
Type Waveguide
Diameter N/A
Other Diameter N/A
Segment Length N/A
Other Segment Length N/A
Number of parallel runs 1
Length 1600 feet per run

Facility ID's and Call Signs of all stations with whom the transmission line is shared.

Facility ID Call Sign
68834 KPXD-TV

Primary Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? No
Type Rigid
Diameter 7 3/16 inches
Other Diameter N/A
Segment Length 20 inches
Other Segment Length N/A
Number of parallel runs 1
Length 1600 feet per run
Justification for New Transmission Line New transmission line to feed to main antenna. See attached 1118_Revised Narrative and Composite quote 1118_Quote ERI

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Interior Line

Interior line inside building

Dehydrator

SARAG2A Dehydrator for transmission line

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Auxiliary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Auxiliary (Backup)
Description of Use
Ownership Leased
Is this tower consider Complex? Candelabra
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users No
Is tower documented for structural analysis? Unknown
Is tower compliant with Rev G? Unknown
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1059733
Coordinates (NAD83) Latitude (NAD83) 32° 32' 36.0" N-
Longitude (NAD83) 096° 57' 33.0" W-
Overall Structure Height 1635.15 feet
Support Structure Height 1523.60 feet
Ground Elevation Above Mean Sea Level (AMSL) 813.97 feet
Structure Type GTOWER - Guyed Structure Used for Communication Purposes
Tower Owner American Towers, LLC
Date Constructed 06/18/2000

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
68834 KPXD-TV DTV

Auxiliary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for undocumented/poorly documented tower
Tower Reinforcements Please select whether tower reinforcements are needed: Minor Reinforcements needed

Auxiliary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Candelabra
Helicopter Services Required Are helicopter services required? No

Auxiliary Tower

Back to Top

Other Tower Expenses Not Listed

Information not provided.

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Description of Use N/A
Ownership Leased
Is this tower consider Complex? Candelabra
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users No
Is tower documented for structural analysis? Unknown
Is tower compliant with Rev G? Unknown
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1059733
Coordinates (NAD83) Latitude (NAD83) 32° 32' 36.0" N-
Longitude (NAD83) 096° 57' 33.0" W-
Overall Structure Height 1635.15 feet
Support Structure Height 1523.60 feet
Ground Elevation Above Mean Sea Level (AMSL) 813.97 feet
Structure Type GTOWER - Guyed Structure Used for Communication Purposes
Tower Owner American Towers, LLC
Date Constructed 06/18/2000

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
68834 KPXD-TV DTV

Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: No study needed
Tower Reinforcements Please select whether tower reinforcements are needed: No reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Candelabra
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Name Description

Weather Days

Weather days prevented tower work. Tower crew unable to mobilize to another job.

Pre-Construction Site Visit

Pre Construction Site Visit

Gin Pole Support Frames

Gin Pole support frames

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 350
Explanation Project management of transitioning facilities.
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 2
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 2
NEPA Section 106 environmental review No
Environmental Assessment No
ASR Modification No
FAA Consultation (including preparation of FAA Form 7460) No
Negotiation of Lease and other Matter for Shared Locations No
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements No
Additional Field Engineering Service Yes
Number of Days 20
Justification On Site RF Engineering Services to supervise installation of equipment and verify performance of new equipment.

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Name Description

Land Survey Primary Tower

Easement/Land Survey for primary tower

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning No
Non-zoning permits Yes
BLM or NFS Coordination No
FCC Construction Permit Minor Change No
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? Yes
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? Yes
Does this relocation require MVPD Notification of a Channel Change? Yes

Other Expenses

Back to Top

Other Expenses Not Listed

Name Description

Prepare FCC Qtrly Reports

Prepare & file quarterly FCC Progress Reports

Lease Modifications

Lease modification for new facilities

Prepare FCC Qtrly Reports

Prepare & file quarterly FCC Progress Reports

Lease Modifications

Lease modification for new facilities

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $3,525,695.73 $2,019,163.80 N/A $1,374,011.14 N/A
Total for all systems $6,571,167.71 $4,199,337.68 N/A $2,838,541.60 N/A
Interim Transmitter TBD $980,303.00 $33,303.00 $33,303.00
Other -- Building Addition Size: 800.0 $30,048.00 $30,048.00 ***System Notice: Estimate adjusted and locked because line has been superseded.***Concrete Pad addition for Heat Exchangers. $30,048.00 N/A
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW $947,000.00 $0.00 estimated costs from catalog $0.00 N/A
Other Electrical Service: Electrical installation costs for Interim Transmitter at interim transmitter site. $3,255.00 $3,255.00 ***System Notice: Estimate adjusted and locked because line has been superseded.***Estimated electrical contractor costs for installation of new interim transmitter at interim site. See attached quote as proxy for costs. $3,255.00 N/A
Primary Transmitter THU9-48 $2,545,392.73 $1,985,860.80 $1,340,708.14
HVAC Modifications $19,590.01 $19,590.01 N/A $19,590.01 N/A
Additional Installation Costs $10,000.00 $10,000.00 Unanticipated additional installation costs. $1,500.00 N/A
UPS $0.00 $0.00 N/A $0.00 N/A
Filter $246,296.00 $246,296.00 Requesting the difference between the new filter and the funds already received for the previous (faulty) ERI filter. $246,296.00 N/A
Terminal Equipment $19,198.53 $19,198.53 Monitoring equipment, supression filter, commissioning $19,198.53 N/A
Other -- Building Addition Size: 800.0 $65,053.92 $65,053.92 See quote: Marsand new transmitter building quote-1 $35,005.92 N/A
Other Electrical Service: Comprehensive services entrance, panels, conduit and wiring. $186,254.27 $186,254.27 N/A $178,324.68 N/A
UHF - Liquid Cooled Solid State Transmitter 68.5 - 75 kW $1,999,000.00 $1,439,468.07 N/A $840,793.00 N/A

Components

Actual Information Description File Name
Other -- Building Addition Size: 800.0

Component Description:
Building modifications for transmitter equipment- 50% deposit
Amount:
$30,048.00
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW

Component Description:
Invoice reflects 50% downpayment.
Amount:
$719,734.00
Other Electrical Service: Electrical installation costs for Interim Transmitter at interim transmitter site.

Component Description:
Eaton Powerware UPS- 20% deposit on Equipment
Amount:
$3,255.00
HVAC Modifications

Component Description:
Duct removal associated with HVAC. Please also see KDFI_letter re KDFW.pdf.
Amount:
$1,169.10

Component Description:
HVAC duct install. Please also see attachment KDFI_letter re KDFW.pdf.
Amount:
$1,829.43

Component Description:
HVAC duct work modifications. Please also see KDFI_letter re KDFW.pdf.
Amount:
$16,591.48
Additional Installation Costs

Component Description:
Transfer switch install. Revised attachment with cover letter
Amount:
$1,500.00
UPS Information not provided.
Filter

Component Description:
Filter. 2nd, 3rd and 4th milestone payment
Amount:
$123,148.00

Component Description:
Filter, 50% minus credit
Amount:
$123,148.00

Component Description:
filter, 50% down minus credit
Amount:
$123,148.00

Component Description:
Filter. First 50% down.
Amount:
$123,148.00

Component Description:
Final 50%, minus credit for previous filter
Amount:
$123,148.00

Component Description:
50% down, minus credit for previous filter
Amount:
$123,148.00
Terminal Equipment

Component Description:
Interconnect with 20 ft length cable
Amount:
$851.12

Component Description:
Video patchbay
Amount:
$966.64

Component Description:
UPS field engineering, startup labor
Amount:
$1,506.84

Component Description:
Monitoring, supression filter. Please see note from vendor on invoice re: name change.
Amount:
$15,586.37

Component Description:
UPS Commissioning. See note from vendor on quote about name change.
Amount:
$1,506.84

Component Description:
Smart TV's for monitoring
Amount:
$287.56
Other -- Building Addition Size: 800.0

Component Description:
New Transmitter building. See Marsand new transmitter building quote-1.pdf.
Amount:
$28,200.00

Component Description:
new transmitter building. See Marsand new transmitter building quote-1.pdf. Updated attachment with cover letter.
Amount:
$6,805.92
Other Electrical Service: Comprehensive services entrance, panels, conduit and wiring.

Component Description:
Transmitter parts - cables. See quote 'anixter.pdf'
Amount:
$218.84

Component Description:
Redundant Power Supply, Video Bypass Router. Revised attachment with quote and cover letter.
Amount:
$12,508.75

Component Description:
3 Cycle bypass switch. Revised attachment with cover letter and quote.
Amount:
$25,058.00

Component Description:
Transmitter parts - cables. See quote 'anixter.pdf'
Amount:
$306.04

Component Description:
Transmitter parts - crimper. See quote 'anixter.pdf'
Amount:
$138.86

Component Description:
Transmitter Electrical work. Please see 'innovative electrical services.pdf' for quote.
Amount:
$37,645.77

Component Description:
Transmitter parts - crimp braid. See quote: 'anixter.pdf'
Amount:
$285.34

Component Description:
Transmitter Electrical Work. See quote 'innovative electrical services.pdf'
Amount:
$31,371.48

Component Description:
Transmitter Electrical Work. Please see quote 'innovative electrical services.pdf'
Amount:
$56,468.69

Component Description:
Transmitter parts - cable ties
Amount:
$44.93

Component Description:
UPS (Uninterrupted Power Supply plus freight). Updated attachment with cover letter.
Amount:
$15,271.99
UHF - Liquid Cooled Solid State Transmitter 68.5 - 75 kW

Component Description:
Primary transmitter. Additional time and scaffolding rental for installation. Quote included.
Amount:
$8,590.00

Component Description:
Transmitter 30% downpayment. Includes upgrades. Quotes and variance included.
Amount:
$249,660.90

Component Description:
Transmitter 10% down at proof. Includes upgrades. Quotes and variance attached.
Amount:
$83,220.30

Component Description:
Transmitter 10% down at completion. Includes upgrade. Quotes and variance sheet attached.
Amount:
$83,220.30

Component Description:
50% transmitter downpayment. Includes upgrade. Quotes and variance sheet included
Amount:
$416,101.50

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,133,507.09 $798,837.09 N/A $783,837.09 N/A
Total for all systems $6,571,167.71 $4,199,337.68 N/A $2,838,541.60 N/A
Interim Antenna TBD $283,964.90 $11,274.90 $11,274.90
Peter Eckman Services $11,274.90 $11,274.90 N/A $11,274.90 N/A
Elbow complex, broadband, at antenna input, per 6 1/8. feedline (if needed) $13,700.00 $0.00 N/A N/A N/A
Sweep test of existing antenna $6,730.00 $0.00 N/A N/A N/A
UHF - High Power Top Mount (200-1000 kW), One station antenna, horizontally polarized $247,000.00 $0.00 N/A N/A N/A
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) $5,260.00 $0.00 N/A N/A N/A
Primary Antenna ATW28H3-ETC1-27H $849,542.19 $787,562.19 $772,562.19
Structural Services Custom 55ft Spine $100,000.00 $100,000.00 See ERI quote 20171218-575 Rev G attached to invoices $100,000.00 N/A
Antenna Installation $445,158.00 $445,158.00 See ERI quote 20171218-575 Rev G attached to antenna installation invoices $445,158.00 N/A
Spinner System Install $3,272.34 $3,272.34 Install of spinner AMS system $3,272.34 N/A
Elbows $4,881.85 $4,881.85 Elbows, reducer, freight $4,881.85 N/A
Sweep test of existing antenna $6,730.00 $6,250.00 N/A $6,250.00 N/A
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized $289,500.00 $228,000.00 See ERI quote 20171218-575 Rev G attached to antenna invoices $213,000.00 N/A

Components

Actual Information Description File Name
Peter Eckman Services

Component Description:
Downpayment for interim tower materials.
Amount:
$11,274.90
Elbow complex, broadband, at antenna input, per 6 1/8. feedline (if needed) Information not provided.
Sweep test of existing antenna Information not provided.
UHF - High Power Top Mount (200-1000 kW), One station antenna, horizontally polarized Information not provided.
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) Information not provided.
Structural Services Custom 55ft Spine

Component Description:
Total cost of custom 55ft spine 100,000. Requesting 30% of total cost prior to shipment on this invoice.
Amount:
$30,000.00

Component Description:
Total cost for custom 55ft spine 100,000. Requesting 30% of cost at time of order on this invoice.
Amount:
$30,000.00

Component Description:
Total cost of custom 55ft spine 100,000. Requesting final 10% of total on this invoice.
Amount:
$10,000.00

Component Description:
Total cost of custom 55ft spine 100,000. Requesting 30% of total cost 30 days ARO on this invoice.
Amount:
$30,000.00
Antenna Installation

Component Description:
Total installation cost $445,158.00. Requesting final 10% of cost on this invoice.
Amount:
$44,515.80

Component Description:
Total installation cost $445,158.00. Requesting 30% of total at time or order.
Amount:
$133,547.40

Component Description:
Total cost of installation $445,158.00. Requesting 30% of total 30 day ARO on this invoice.
Amount:
$133,547.40

Component Description:
Total installation cost $445,158.00. Requesting 30% of total prior to shipment on this invoice.
Amount:
$133,547.40
Spinner System Install

Component Description:
Spinner AMS system install
Amount:
$3,272.34
Elbows

Component Description:
Elbows, reducers, freight.
Amount:
$4,881.85
Sweep test of existing antenna

Component Description:
Total cost of TV System Sweep $6250. Requesting final 10% of total on this invoice.
Amount:
$625.00

Component Description:
Total cost of TV System Sweep $6250. Requesting 30% of total cost at time of shipment, on this invoice.
Amount:
$1,875.00

Component Description:
Total cost of TV System Sweep $6250. Requesting 30% of total cost at time of order on this invoice.
Amount:
$1,875.00

Component Description:
Total cost of TV System Sweep $6250. Requesting 30% of total cost 30 day ARO, on this invoice.
Amount:
$1,875.00
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized

Component Description:
Total antenna cost $228,000.00. Requesting final 10% of like for like antenna cost on this invoice.
Amount:
$21,300.00

Component Description:
Total antenna cost $228,000.00. Requesting 30% of like for like antenna cost prior to shipment on this invoice.
Amount:
$63,900.00

Component Description:
Requesting 30% of like for like antenna cost at time of order.
Amount:
$63,900.00

Component Description:
Total antenna cost $228,000.00. Requesting 30% of like for like antenna cost ARO on this invoice.
Amount:
$63,900.00

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $496,763.50 $457,513.70 N/A $443,942.68 N/A
Total for all systems $6,571,167.71 $4,199,337.68 N/A $2,838,541.60 N/A
Primary Transmission Line $496,763.50 $457,513.70 $443,942.68
Dehydrator $7,557.25 $7,557.25 SARAH2A Dehydrator $7,557.25 N/A
Interior Line $25,206.25 $25,206.25 Interior RF line inside building. $20,324.40 N/A
Rigid Transmission Line - copper, 7 3/16" $464,000.00 $424,750.20 N/A $416,061.03 N/A

Components

Actual Information Description File Name
Dehydrator

Component Description:
Total cost of dehydrator is $7557.25. Requesting 30% of total 30 days ARO on this invoice.
Amount:
$2,267.18

Component Description:
Total cost for Dehydrator is $7557.25. Requesting 30% of total due at time of order.
Amount:
$2,267.18

Component Description:
Total cost of dehydrator is $7557.25. Requesting final 10% of total on this invoice.
Amount:
$755.71

Component Description:
Total cost of dehydrator is $7557.25. Requesting 30% of total prior to shipping on this invoice.
Amount:
$2,267.18
Interior Line

Component Description:
30% prior to shipment. Interior Run install and transmission line system.
Amount:
$3,355.56

Component Description:
30% payment 30 days ARO. Interior Run install and Transmission Line System.
Amount:
$7,272.36

Component Description:
10% net invoice. Interior Run install and Transmission line system.
Amount:
$2,424.12

Component Description:
30% deposit with order. Interior run install and transmission line system.
Amount:
$7,272.36
Rigid Transmission Line - copper, 7 3/16"

Component Description:
Total cost of transmission line system $416,061.05. Requesting 30% of total 30 days ARO on this invoice.
Amount:
$124,818.31

Component Description:
Total cost of main transmission line $416,061.05. Requesting 30% of total prior to shipment on this invoice.
Amount:
$124,818.31

Component Description:
Total cost of main transmission line is $416,061.05. Requesting final 10% of total on this invoice.
Amount:
$41,606.10

Component Description:
Total cost of transmission line system $416,06.05. Requesting 30% at time of order on this invoice.
Amount:
$124,818.31

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,074,650.00 $573,775.60 N/A $92,617.60 N/A
Total for all systems $6,571,167.71 $4,199,337.68 N/A $2,838,541.60 N/A
Auxiliary Tower GTOWER $605,300.00 $44,267.60 $44,267.60
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $0.00 Catalog Price - tower rigging and new Aux Antenna Installation at Aux Site. Project abandoned. N/A N/A
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study $26,300.00 $44,267.60 See attached quote from ERI for tower mapping and tower studies for potential Interim/Aux site. Includes sales tax of $1,887.60. Plus additional fee of $7,500 for supplemental study of the original analysis. $44,267.60 N/A
Minor tower reinforcement/modifications $158,000.00 $0.00 N/A N/A N/A
Primary Tower GTOWER $469,350.00 $529,508.00 $48,350.00
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $481,158.00 Actual cost exceeded catalog. N/A N/A
Gin Pole Support Frames $27,000.00 $27,000.00 Gin Pole support frames. See ERI quote 20171218-575 REV.G $27,000.00 N/A
Pre-Construction Site Visit $9,000.00 $9,000.00 Pre Construction Site Visit see ERI quote 20171218-575 REV.G $9,000.00 N/A
Weather Days $12,350.00 $12,350.00 Bad weather prohibited work on tower. Station to pay weather days based on contract. $12,350.00 N/A

Components

Actual Information Description File Name
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) Information not provided.
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study

Component Description:
Structural analysis and report PO 17-0230.
Amount:
$36,767.60

Component Description:
Supplemental study required for original analysis.
Amount:
$7,500.00
Minor tower reinforcement/modifications Information not provided.
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) Information not provided.
Gin Pole Support Frames

Component Description:
Total cost of Gin Pole support frames is $27,000. Requesting final 10% of total on this invoice.
Amount:
$2,700.00

Component Description:
Total cost of Gin Pole support frames is 27,000. Requesting 30% of total prior to shipping on this invoice.
Amount:
$8,100.00

Component Description:
Total cost of Gin Pole support frames is $27,000. Requesting 30% of the total due at time of order on this invoice.
Amount:
$8,100.00

Component Description:
Total cost of Gin Pole support frames is $27,000. Requesting 30% of total 30 days ARO on this invoice.
Amount:
$8,100.00
Pre-Construction Site Visit

Component Description:
Total cost of pre-construction site visit $9000. Requesting 30% of total 30 days ARO on this invoice.
Amount:
$2,700.00

Component Description:
Total cost of pre-construction visit is $9000. Requesting 30% of total due at time of order on this invoice.
Amount:
$2,700.00

Component Description:
Total cost of pre-construction site visit $9000. Requesting 30% of total prior to shipping on this invoice.
Amount:
$2,700.00

Component Description:
Total cost of pre-construction site visit $9000. Requesting final 10% on this invoice.
Amount:
$900.00
Weather Days

Component Description:
Bad weather days for tower work
Amount:
$7,800.00

Component Description:
Bad weather days for tower work
Amount:
$4,550.00

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $231,214.50 $244,410.60 N/A $117,303.10 N/A
Total for all systems $6,571,167.71 $4,199,337.68 N/A $2,838,541.60 N/A
Outside Professional Services $231,214.50 $244,410.60 $117,303.10
Land Survey Primary Tower $4,979.50 $4,979.50 Easement/Land Survey for primary tower $4,979.50 N/A
Additional Field Engineering Service, 20 Days $42,400.00 $42,400.00 20 Days on site RF Engineering Supervision of equipment installation and performance verification. $0.00 N/A
Comprehensive coverage verification via field study, if needed $84,200.00 $80,000.00 N/A $27,025.00 N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $7,360.00 $7,000.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $2,250.00 N/A N/A N/A
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application $4,210.00 $4,000.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $5,000.00 N/A N/A N/A
Prepare request for Special Temporary Authorization $4,100.00 $3,000.00 N/A N/A N/A
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application $1,580.00 $1,500.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A N/A N/A
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application $2,105.00 $2,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $3,000.00 N/A $2,996.25 N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $7,000.00 N/A $6,521.25 N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A N/A N/A
Prepare and or review reimbursement form $2,630.00 $2,500.00 N/A N/A N/A
Project management of the transition $55,300.00 $75,781.10 RF Consulting and Project Mgmt $75,781.10 RF consulting

Components

Actual Information Description File Name
Land Survey Primary Tower

Component Description:
Easement/Land Survey for primary tower.
Amount:
$4,979.50
Additional Field Engineering Service, 20 Days Information not provided.
Comprehensive coverage verification via field study, if needed

Component Description:
Full Site Survey of KDFI with Drawing Package- 50% down payment
Amount:
$13,512.50

Component Description:
Full Site Survey of KDFI with Drawing Package- remaining 50%
Amount:
$13,512.50
Attorney Fees - Prepare and File request for Special Temporary Authorization Information not provided.
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application Information not provided.
Prepare request for Special Temporary Authorization Information not provided.
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application

Component Description:
Prepare and file FCC CP Application, technical exhibits
Amount:
$2,996.25
Perform engineering study for new channel assignment and antenna development

Component Description:
Channel search, interference assessment, pop counts, coverage mapping.
Amount:
$6,521.25
Address transition timing and coordination issues w/ other stations and wireless Information not provided.
Prepare and or review reimbursement form Information not provided.
Project management of the transition

Component Description:
RF Consulting 9/1/21 - 9/30/21
Amount:
$635.00

Component Description:
RF Consulting/Project Management 1/4/18 - 12/31/18
Amount:
$594.03

Component Description:
RF Engineering/Project Mgmt 10/1/21-10/7/21
Amount:
$717.50

Component Description:
RF Consulting/Project Management 1/1/18 - 12/31/18
Amount:
$19,035.00

Component Description:
Repack Project Management 1/1/19 - 12/31/19
Amount:
$1,077.08

Component Description:
Prepare, amend, revise 399 budgets, respond to FCC tech review, develop narratives.
Amount:
$7,931.25

Component Description:
Repack Project Management 1/4/18 - 12/31/18
Amount:
$594.03

Component Description:
RF Consulting 1/1/20 - 12/31/20
Amount:
$16,702.50

Component Description:
RF Consulting and Project Management 1/1/19 - 12/31/19
Amount:
$14,785.00

Component Description:
RF Consulting/Project Management 1/4/18 - 12/31/18
Amount:
$594.02

Component Description:
RF Consulting July 2021
Amount:
$453.75

Component Description:
Repack Project Management 1/5/17 - 12/31/17
Amount:
$3,583.75

Component Description:
Repack project management 1/1/19 - 12/31/19
Amount:
$14,785.00

Component Description:
zeroing this line item out
Amount:
N/A

Component Description:
Equipment inventory, determine channel specific components, rechannel vs replacement determination
Amount:
$3,172.50

Component Description:
Repack project management 1/1/18 - 12/31/18
Amount:
$20,092.50

Component Description:
RF Consulting 1/1/21 - 1/28/21
Amount:
$6,770.00

Component Description:
RF Consulting 8/1/21 - 8/31/21
Amount:
$323.75

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $109,336.89 $105,636.89 N/A $26,829.99 N/A
Total for all systems $6,571,167.71 $4,199,337.68 N/A $2,838,541.60 N/A
Other Expenses $109,336.89 $105,636.89 $26,829.99
Lease Modifications $15,000.00 $15,000.00 N/A N/A N/A
Prepare FCC Qtrly Reports $23,850.00 $23,850.00 See attached vendor quote for FCC Progress Reporting. N/A N/A
MVPD Notification of Channel Change $5,000.00 $5,000.00 N/A $0.00 N/A
Develop and air announcement of upcoming channel change $1,500.00 $1,500.00 N/A N/A N/A
Equipment Storage $10,000.00 $10,000.00 N/A N/A N/A
Equipment Delivery and Handling Charges $16,906.89 $16,906.89 Based on actual costs $16,906.89 N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $15,000.00 $15,000.00 Disposal Costs $2,058.10 N/A
Non-zoning permits $10,000.00 $10,000.00 N/A N/A N/A
FCC Filing Fees - Special Temporary Authorization request $195.00 $190.00 N/A N/A N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $325.00 N/A N/A N/A
DTV Medical Facility Notification $11,550.00 $7,865.00 N/A $7,865.00 N/A

Components

Actual Information Description File Name
Lease Modifications Information not provided.
Prepare FCC Qtrly Reports Information not provided.
MVPD Notification of Channel Change Information not provided.
Develop and air announcement of upcoming channel change Information not provided.
Equipment Storage Information not provided.
Equipment Delivery and Handling Charges

Component Description:
Freight for antenna, dehydrator, main transmission line (invoices KDFI-001, KDFI-002, KDFI-003A, KDFI-53434)
Amount:
$16,906.89
Disposal Costs (for equipment and other waste, net of any salvage value)

Component Description:
Dumpster/Equipment Disposal 5/16/19-5/31/19. Revised attachment with cover letter and variance.
Amount:
$461.97

Component Description:
Dumpster/Equipment Disposal 6/16/19-6/30/19. Revised attachment with cover letter and variance sheet.
Amount:
$426.70

Component Description:
Dumpster/Equipment disposal 4/1/19 - 4/15/19. This includes a revised attachment with cover letter.
Amount:
$537.00

Component Description:
Disposal container use 6/1/19-6/15/19. Updated with cover letter.
Amount:
$88.17

Component Description:
Dumpster/Equipment Disposal 4/16/19-4/30/19. Revised attachment with cover letter.
Amount:
$88.17

Component Description:
Dumpster/Equipment Disposal 5/1/19-5/15/19. Updated with cover letter
Amount:
$456.09
Non-zoning permits Information not provided.
FCC Filing Fees - Special Temporary Authorization request Information not provided.
FCC Filing Fees - Form 2100 license to cover application Information not provided.
DTV Medical Facility Notification

Component Description:
DTV notification for medical facilities. Please see 'DTV Notifications-1.pdf' for quote.
Amount:
$7,865.00

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $6,571,167.71 $4,199,337.68 $2,838,541.60

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. Yes
Construction of final facilities or all necessary modifications are complete. Yes
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Angelo Servedio

SVP Controller


09/15/2022

Certification

Back to Top
Section Question Response
Submission of Final Allocation or Accounting Information Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  2. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  3. The above-named entity certifies that all costs identified as "actual costs" herein accurately represent the costs actually paid by the above-named entity, including any discounts, refunds, or rebates.

  4. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  5. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  6. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Angelo Servedio

SVP Controller


09/15/2022

Attachments

Back to Top