Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
NPG of Texas, L.P. Doing Business As: NPG of Texas, L.P. |
825 Edmond Street Saint Joseph, MO 64501 United States |
+1 (816) 271-8505 | tim.hannan@npgco.com | Limited Partnership |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
The Preparer is same as the reimbursement contact. |
|
|
|
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Please see transaction plan exhibit. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Retune Existing |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | Linear Industries |
Model | AT725P | |
Year | 2014 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 0.25 kW |
Section | Question | Response |
---|---|---|
New Mask Filter | Does the transmitter require a new mask filter? | Yes |
Mask Filter Type | Stringent | |
Power | 100-200W | |
New Exciter | Is a new exciter needed? | No |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | No | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Other | |
Other Antenna Type | Para Panel | |
ERP: | 0.25 kW | |
Manufacturer | ||
Model | PR-TV-17 | |
Year | 2014 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Other | |
Other Antenna Type | Para Panel | |
ERP: | 0.25 kW | |
Manufacturer | ||
Model | PRM Tetra UHF | |
Year | 2018 | |
Justification for New Antenna | Please see Transition Plan Description Exhibit |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | No |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | No |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Name | Description |
---|---|
Additional Non-Catalog Displacement Legal Services |
Additional Non-Catalog Displacement Legal Services |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $12,762.50 | $3,237.50 | N/A | $1,475.00 | N/A |
Total for all systems | $29,689.75 | $25,315.75 | N/A | $14,324.95 | N/A |
Primary Transmitter AT725P | $12,762.50 | $3,237.50 | $1,475.00 | ||
Retune - UHF and VHF - minor re-channel issues | $11,000.00 | $1,475.00 | N/A | $1,475.00 | N/A |
100-200W w mask filter Stringent | $1,762.50 | $1,762.50 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Retune - UHF and VHF - minor re-channel issues | |
100-200W w mask filter Stringent | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $324.75 | $324.75 | N/A | $324.75 | N/A |
Total for all systems | $29,689.75 | $25,315.75 | N/A | $14,324.95 | N/A |
Primary Antenna PRM Tetra UHF | $324.75 | $324.75 | $324.75 | ||
UHF-Low Power, Side Mount, Other, 0.25kW input, Horizontal | $324.75 | $324.75 | N/A | $324.75 | N/A |
Actual Information Description | File Name |
---|---|
UHF-Low Power, Side Mount, Other, 0.25kW input, Horizontal |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $16,267.50 | $21,418.50 | N/A | $12,355.20 | N/A |
Total for all systems | $29,689.75 | $25,315.75 | N/A | $14,324.95 | N/A |
Outside Professional Services | $16,267.50 | $21,418.50 | $12,355.20 | ||
Additional Non-Catalog Displacement Legal Services | $5,000.00 | $5,000.00 | N/A | $1,694.20 | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $5,286.00 | Additional expenses were incurred as indicated in the attached invoices. | $5,286.00 | Additional expenses were incurred as indicated in the attached invoices. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | $642.60 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | N/A | N/A |
Perform engineering study for displacement application | $1,800.00 | $3,375.00 | Additional expenses were incurred as indicated in the attached invoices. | $3,375.00 | Additional expenses were incurred as indicated in the attached invoices. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | $1,100.00 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | $257.40 | N/A |
Actual Information Description | File Name |
---|---|
Additional Non-Catalog Displacement Legal Services | |
Prepare/ Review 399 reimbursement form | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Perform engineering study for displacement application | |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $335.00 | $335.00 | N/A | $170.00 | N/A |
Total for all systems | $29,689.75 | $25,315.75 | N/A | $14,324.95 | N/A |
Other Expenses | $335.00 | $335.00 | $170.00 | ||
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | $170.00 | N/A |
Actual Information Description | File Name |
---|---|
FCC Filing Fees - Form 2100 license to cover application |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $29,689.75 | $25,315.75 | $14,324.95 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | J. Timothy Hannan EVP & CFO of Parent, NPGCO 08/10/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | J. Timothy Hannan EVP & CFO of Parent, NPGCO 08/10/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | J. Timothy Hannan EVP & CFO of Parent, NPGCO 08/10/2022 |