Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
GREATER CINCINNATI TELEVISON EDUCATIONAL FOUNDATION |
1223 Central Parkway Cincinnati, OH 45214 United States |
+1 (513) 345-6538 | lweinel@cetconnect.org | Not-for-Profit |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
The Preparer is same as the reimbursement contact. |
|
|
|
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | Transition plan |
Question | Response |
---|---|
Sharee Station Facility ID | 65666 |
Call Sign | WCET |
Type | Noncommercial Educational |
Licensee Name | GREATER CINCINNATI TELEVISON EDUCATIONAL FOUNDATION |
Status | LICENSED |
DTS | No |
Community of License | CINCINNATI, OH |
Pre-auction RF Channel | 17 |
Post-auction RF Channel | 17 |
Neilsen DMA | CINCINNATI |
Network Affiliation |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | CD3140P2 | |
Year | 2002 | |
Type | Inductive Output Tube | |
IOT Power Type | Two | |
Power Capacity | 140 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | ULXTE-30 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 19.2 kW | |
Justification for New Transmitter | GatesAir technicians tell us our transmitter is obsolete and we will not be able to get parts for repair purposes. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 150 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 4 inches | |
Length | 500.0 feet | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Heating and Cooling | |
Size | 10 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 750.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 400.0 kW | |
Manufacturer | ||
Model | TFU-24DSB-H(C) | |
Year | 2002 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 408.0 kW | |
Manufacturer | ||
Model | VFU-24DSB-H | |
Year | 2019 | |
Justification for New Antenna | New antenna necessary to carry new broadcast signal |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 6 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 400.0 kW | |
Manufacturer | ||
Model | TFU-16WB | |
Year | 2019 | |
Justification for New Antenna | New interim antenna as specified in transition plan. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Segment Length | 19 ¾ ' | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 820 feet per run | |
Justification for New Transmission Line | See transition plan. Need line for interim antenna. Dielectric now quoting a larger diameter. |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Type | Flexible Air | |
Diameter | 4 inches | |
Segment Length | N/A | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 400 feet per run | |
Justification for New Transmission Line | Additional interim antenna necessary while tower crew has installed gin pole on top of tower. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
ASR Number | ||
Coordinates (NAD83) | Latitude (NAD83) | 39° 07' 19.0" N- |
Longitude (NAD83) | 084° 32' 52.0" W- | |
Overall Structure Height | 1020.98 feet | |
Support Structure Height | 951.76 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 728.01 feet | |
Structure Type | LTOWER - Lattice Tower | |
Tower Owner | WXIX, LLC | |
Date Constructed | 01/01/1985 |
Facility ID | Call Sign | Service |
---|---|---|
39738 | WXIX-TV | DTV |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | No study needed |
Tower Reinforcements | Please select whether tower reinforcements are needed: | No reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Interim Antenna |
Remove and install new Interim Antenna |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 100 | |
Explanation | We do not have staff personnel available for the tasks that Project Management would cover, nor is the staff trained to provide those services. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | Yes | |
Number of Days | 2 | |
Justification | Site survey |
Name | Description |
---|---|
Personnel costs |
100 hours x $100/hour |
Comprehensive Coverage Verification |
Comprehensive Coverage Verification - Antenna Pattern Verification via unmanned aerial vehicle (UAV).ff |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $981,809.00 | $944,059.00 | N/A | $626,808.37 | N/A |
Total for all systems | $2,234,382.49 | $1,874,639.59 | N/A | $1,121,773.48 | N/A |
Primary Transmitter ULXTE-30 | $981,809.00 | $944,059.00 | $626,808.37 | ||
UHF - Liquid Cooled Solid State Transmitter 14.2 - 20 kW | $684,000.00 | $650,000.00 | N/A | $582,722.37 | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $36,300.00 | N/A | N/A | N/A |
Transformer 3 phase/480v - 150 KVA | $25,550.00 | $29,200.00 | Adjusted to agree with actual proposal from Kraft Electrical Contracting Inc. | $29,200.00 | N/A |
4" Rigid Conduit and Wiring (Cost per foot) | $50,500.00 | $48,000.00 | N/A | N/A | N/A |
10 Ton system | $60,500.00 | $57,500.00 | N/A | N/A | N/A |
Other -- Building Addition Size: 750.0 | $123,059.00 | $123,059.00 | Transmission line bridge included in this cost as only necessary because of move to new building. Building cost estimate attached. | $14,886.00 | N/A |
Actual Information Description | File Name |
---|---|
UHF - Liquid Cooled Solid State Transmitter 14.2 - 20 kW | |
Switchgear - industrial 800 amp | Information not provided. |
Transformer 3 phase/480v - 150 KVA | |
4" Rigid Conduit and Wiring (Cost per foot) | Information not provided. |
10 Ton system | Information not provided. |
Other -- Building Addition Size: 750.0 |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $427,910.00 | $258,745.00 | N/A | $102,894.30 | N/A |
Total for all systems | $2,234,382.49 | $1,874,639.59 | N/A | $1,121,773.48 | N/A |
Interim Antenna TFU-16WB | $196,230.00 | $121,520.00 | $75,122.10 | ||
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized | $189,500.00 | $115,120.00 | quote attached | $75,122.10 | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | Per signed quote | $0.00 | N/A |
Primary Antenna VFU-24DSB-H | $231,680.00 | $137,225.00 | $27,772.20 | ||
Sweep test of existing antenna | $6,730.00 | $12,800.00 | To agree with amounts contained in quote 700186CMZ-3 | $5,760.00 | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $14,160.00 | This was omitted from original estimated cost and not included in antenna base cost per invoice. | $12,744.00 | N/A |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | $12,300.00 | $10,298.00 | This was not included in the original estimated cost plan. | $9,268.20 | N/A |
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized | $189,500.00 | $99,967.00 | Cost per Dielectric quotation attached | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized | |
Sweep test of existing antenna | |
Sweep test of existing antenna | |
Side mount brackets for high power antennas (if not included in antenna base cost) | |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | |
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $195,240.00 | $161,655.60 | N/A | $146,826.85 | N/A |
Total for all systems | $2,234,382.49 | $1,874,639.59 | N/A | $1,121,773.48 | N/A |
Interim Transmission Line | $165,640.00 | $126,987.60 | $120,098.85 | ||
Rigid Transmission Line - copper, 6 1/8" | $165,640.00 | $126,987.60 | Actual cost as provided by Dielectric on quote 700186CMZ-3 for line and flanges and expected changes | $120,098.85 | The amount claimed is equal to amount invoiced |
Interim Transmission Line | $29,600.00 | $34,668.00 | $26,728.00 | ||
Flexible Air Transmission Line - dielectric, 4" | $29,600.00 | $34,668.00 | Per quote as provided by Dielectric before adjustments. | $26,728.00 | N/A |
Actual Information Description | File Name |
---|---|
Rigid Transmission Line - copper, 6 1/8" | |
Flexible Air Transmission Line - dielectric, 4" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $359,150.00 | $247,240.00 | N/A | $157,013.00 | N/A |
Total for all systems | $2,234,382.49 | $1,874,639.59 | N/A | $1,121,773.48 | N/A |
Primary Tower LTOWER | $359,150.00 | $247,240.00 | $157,013.00 | ||
Tall Tower (greater than 500') | $210,500.00 | $98,590.00 | Antenna installation as per Dielectric quotation. | $82,688.00 | N/A |
Interim Antenna | $148,650.00 | $148,650.00 | Tower rigging as per bid received from Dielectric and temporary antenna removal as per bid from Tower Consultants Inc | $74,325.00 | N/A |
Actual Information Description | File Name |
---|---|
Tall Tower (greater than 500') | |
Interim Antenna |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $224,604.45 | $217,820.95 | N/A | $72,066.45 | N/A |
Total for all systems | $2,234,382.49 | $1,874,639.59 | N/A | $1,121,773.48 | N/A |
Outside Professional Services | $224,604.45 | $217,820.95 | $72,066.45 | ||
Comprehensive Coverage Verification | $40,232.00 | $40,232.00 | Coverage verification per QComm quote 839C attached to invoices | $40,232.00 | N/A |
Personnel costs | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Additional Field Engineering Service, 2 Days | $18,402.45 | $18,402.45 | Actual invoice received in excess of estimate | $18,402.45 | The cost of the sweep came in at a cost in excess of estimated cost. |
RF Exposure Measurements | $21,050.00 | $20,000.00 | N/A | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $80,000.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $3,680.00 | $3,500.00 | N/A | $2,578.00 | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $4,210.00 | $4,000.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | $514.00 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | $2,337.00 | N/A |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,500.00 | N/A | $600.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | $750.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,001.00 | N/A | $1,725.00 | N/A |
Prepare and or review reimbursement form | $2,630.00 | $3,935.50 | Actual invoices received has exceeded original estimate. | $3,728.00 | The amount of actual invoices received has exceeded original estimate. |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | $702.50 | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | $497.50 | N/A |
Project management of the transition | $15,800.00 | $15,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Comprehensive Coverage Verification | |
Personnel costs | Information not provided. |
Additional Field Engineering Service, 2 Days | |
RF Exposure Measurements | Information not provided. |
Comprehensive coverage verification via field study, if needed | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Attorney Fees - Negotiation of lease and other matters for shared locations | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
Prepare request for Special Temporary Authorization | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Prepare and or review reimbursement form | |
Perform engineering study for new channel assignment and antenna development | |
Address transition timing and coordination issues w/ other stations and wireless | |
Project management of the transition | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $45,669.04 | $45,119.04 | N/A | $16,164.51 | N/A |
Total for all systems | $2,234,382.49 | $1,874,639.59 | N/A | $1,121,773.48 | N/A |
Other Expenses | $45,669.04 | $45,119.04 | $16,164.51 | ||
MVPD Notification of Channel Change | $500.00 | $500.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $1,000.00 | $1,000.00 | N/A | N/A | N/A |
Equipment Storage | $4,145.00 | $4,145.00 | Actual charge as per Dielectric invoice 778009 | $4,145.00 | N/A |
Equipment Delivery and Handling Charges | $22,474.04 | $22,474.04 | Additional freight and shipping billed by Dielectric | $8,744.51 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | $3,275.00 | N/A |
Local Zoning | $1,000.00 | $1,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
MVPD Notification of Channel Change | Information not provided. |
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Storage | |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
DTV Medical Facility Notification | |
Local Zoning | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $2,234,382.49 | $1,874,639.59 | $1,121,773.48 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | Yes |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lee R Weinel CFO 03/21/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lee R Weinel CFO 03/21/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|