Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
Gray Television Licensee, LLC |
4370 Peachtree Road, NE Atlanta, GA 30319 United States |
+1 (404) 266-3888 | allfcclms@gray.tv | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Sam Hariton Widelity |
4031 University Dr Suite 100 Fairfax, VA 22030 United States |
+1 (339) 222-8107 | sam.hariton@widelity.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | The Translator will only require a new Bandpass filter and transmitter alignment on new channel. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | No |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | No |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | No |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Prepare Form 601 | Yes | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Name | Description |
---|---|
Scala Bandpass Filter |
There is a need of a single filter to support the Channel change |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $15,537.50 | $15,537.50 | N/A | $0.00 | N/A |
Total for all systems | $17,120.50 | $17,120.50 | N/A | $0.00 | N/A |
Outside Professional Services | $15,537.50 | $15,537.50 | $0.00 | ||
Attorney Fees - Prepare and File request for Special Temporary Authorization | $2,235.00 | $2,235.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | N/A | N/A |
Prepare Form 601 | $755.00 | $755.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $1,280.00 | $1,280.00 | N/A | N/A | N/A |
Perform engineering study for displacement application | $1,800.00 | $1,800.00 | N/A | N/A | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,710.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,583.00 | $1,583.00 | N/A | $0.00 | N/A |
Total for all systems | $17,120.50 | $17,120.50 | N/A | $0.00 | N/A |
Other Expenses | $1,583.00 | $1,583.00 | $0.00 | ||
FCC Filing Fees - Special Temporary Authorization request | $305.00 | $305.00 | N/A | N/A | N/A |
Scala Bandpass Filter | $943.00 | $943.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $17,120.50 | $17,120.50 | $0.00 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |