Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
RADIANT LIFE MINISTRIES, INC. Doing Business As: RADIANT LIFE MINISTRIES, INC. |
PO BOX 1010 MARION, IL 62959 United States |
+1 (618) 997-4700 | jchautin@hardycarey.com | Not-for-Profit |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Stephen C Simpson Attorney at Law |
1250 Connecticut Avenue, NW Suite 700 Washington, DC 20036 United States |
+1 (202) 408-7035 | simpson@scsimpsonlaw.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Change from channel 48 to 29. Installation of replacement transmitter and new main antenna. Interim antenna, transmitter, and transmission line to maintain operational continuity. Replacement of tower necessary based on structural analysis. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | DCX-2P | |
Year | 2005 | |
Type | Inductive Output Tube | |
IOT Power Type | Two | |
Power Capacity | 60 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | THU9evo | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 37.0 kW | |
Justification for New Transmitter | New transmitter required because retuning of existing IOT transmitter is no longer an option. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | Yes | |
Power | 150 kVA | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 1000.0 kW | |
Manufacturer | ||
Model | TFU-28DSC-S200 | |
Year | 2005 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 691.0 kW | |
Manufacturer | ||
Model | TFU-24DSC-R S200 | |
Year | 2017 | |
Justification for New Antenna | Current antenna is coaxial slot design. Channel change not possible. Proposed antenna replicates existing antenna, except in number of bays, which is reduced to maintain approximate physical size. New antenna to be installed on replacement tower. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 6 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1200 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 19 1/2 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1350 feet per run | |
Justification for New Transmission Line | Replacement tower required due to structural analysis. New transmission line to be installed on new tower with new antenna. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Construct New |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1242292 | |
Coordinates (NAD83) | Latitude (NAD83) | 30° 59' 52.0" N- |
Longitude (NAD83) | 086° 43' 13.0" W- | |
Overall Structure Height | 1103.99 feet | |
Support Structure Height | 1099.07 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 145.01 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Flinn Broadcasting Corp | |
Date Constructed | 03/01/2004 |
Section | Question | Response |
---|---|---|
Construct New Tower | Use | Primary (Main) |
Description of Use | N/A | |
Is this a request for upgraded equipment? | No | |
Height | 1104.00 feet | |
Justification for New Tower | Current tower fails TIA-222-G based on completed structural analysis. |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Dismantle and Disposal of Old Tower |
Dismantle and disposal of tower to be replaced. |
Existing Primary Tower - Structural Analysis |
Structural analysis required before equipment could be installed on tower |
New Tower - Tower Lights |
New Tower - Tower Lights |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 675 | |
Explanation | External project management for 80 hours provided by Land Communications to assist owner who has insufficient staff resources. An additional estimate for 595 hours from Widelity for project management of the transition | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
NEPA Section 106 environmental review | Yes | |
Environmental Assessment | Yes | |
ASR Modification | Yes | |
FAA Consultation (including preparation of FAA Form 7460) | Yes | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
Building modifications, concrete pad, road repairs |
Required building modifications including concrete pad for interim xmtr heat exchange. Road repairs for material deliveries. |
Tower Removal |
Tower Removal |
Equipment Rental |
Equipment Rental |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,498,550.00 | $1,246,927.30 | N/A | $1,246,927.30 | N/A |
Total for all systems | $6,049,947.69 | $5,730,829.87 | N/A | $5,381,346.95 | N/A |
Primary Transmitter THU9evo | $1,498,550.00 | $1,246,927.30 | $1,246,927.30 | ||
Transformer 3 phase/480v - 150 KVA | $25,550.00 | $8,550.00 | Please see attached Land Communications Budgetary Quote. This estimated cost is for two 90 kVA transformers. LMS will not allow a selection below 150 kVA. | $8,550.00 | N/A |
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW | $1,473,000.00 | $1,238,377.30 | Please see attached Land Communications Budgetary Quote. | $1,238,377.30 | N/A |
Actual Information Description | File Name |
---|---|
Transformer 3 phase/480v - 150 KVA | |
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $202,338.00 | $199,292.00 | N/A | $199,292.00 | N/A |
Total for all systems | $6,049,947.69 | $5,730,829.87 | N/A | $5,381,346.95 | N/A |
Primary Antenna TFU-24DSC-R S200 | $202,338.00 | $199,292.00 | $199,292.00 | ||
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | $6,400.00 | N/A |
UHF - High Power, Side Mount, basic slot antenna, 691 kW input, directional,, horizontally polarized | $160,158.00 | $160,158.00 | see Estimated Cost Justification WFBD-210-Primary Antenna - UHF High Power Side Mount, Directional, H-POL v0 | $160,158.00 | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $21,750.00 | N/A | $21,750.00 | N/A |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | $12,300.00 | $10,984.00 | N/A | $10,984.00 | N/A |
Actual Information Description | File Name |
---|---|
Sweep test of existing antenna | |
UHF - High Power, Side Mount, basic slot antenna, 691 kW input, directional,, horizontally polarized | |
Side mount brackets for high power antennas (if not included in antenna base cost) | |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $272,700.00 | $167,465.25 | N/A | $164,866.09 | N/A |
Total for all systems | $6,049,947.69 | $5,730,829.87 | N/A | $5,381,346.95 | N/A |
Primary Transmission Line | $272,700.00 | $167,465.25 | $164,866.09 | ||
Rigid Transmission Line - copper, 6 1/8" | $272,700.00 | $167,465.25 | N/A | $164,866.09 | N/A |
Actual Information Description | File Name |
---|---|
Rigid Transmission Line - copper, 6 1/8" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $3,548,307.00 | $3,584,832.73 | N/A | $3,584,832.73 | N/A |
Total for all systems | $6,049,947.69 | $5,730,829.87 | N/A | $5,381,346.95 | N/A |
Primary Tower TOWER | $0.00 | $0.00 | $0.00 | ||
Primary Tower | $3,548,307.00 | $3,584,832.73 | $3,584,832.73 | ||
New Tower - Tower Lights | $2,100.00 | $2,100.00 | Please see WFBD New Tower - Tower Lights Budget Revision Justification Letter | $2,100.00 | N/A |
Existing Primary Tower - Structural Analysis | $6,000.00 | $6,000.00 | Please see George Flinn WFBD Existing Primary Tower-Structural Analysis Revision Justification Cover Letter | $6,000.00 | N/A |
Tall Tower (greater than 500') | $210,500.00 | $0.00 | Please see attached ERI proposal 20190626-971. This proposal includes a combined expense for both tower construction and tower rigging. This expense has been moved to the New Tower Construction Category | $0.00 | N/A |
Dismantle and Disposal of Old Tower | $426,187.00 | $426,187.00 | per ERI quote 20190820-502 Rev A | $426,187.00 | N/A |
New tower between 1000' and 1500' without elevator, presumptive soil conditions | $2,903,520.00 | $3,150,545.73 | Please see Estimated Cost Justification WFBD-480-New Tower-Construct New Tower v2 | $3,150,545.73 | N/A |
Actual Information Description | File Name |
---|---|
New Tower - Tower Lights | |
Existing Primary Tower - Structural Analysis | |
Tall Tower (greater than 500') | Information not provided. |
Dismantle and Disposal of Old Tower | |
New tower between 1000' and 1500' without elevator, presumptive soil conditions |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $158,400.00 | $166,264.90 | N/A | $149,387.40 | N/A |
Total for all systems | $6,049,947.69 | $5,730,829.87 | N/A | $5,381,346.95 | N/A |
Outside Professional Services | $158,400.00 | $166,264.90 | $149,387.40 | ||
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | $2,105.00 | $1,500.00 | N/A | $625.00 | N/A |
ASR modification (prepare FCC Form 854) | $2,105.00 | $1,500.00 | N/A | $250.00 | N/A |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | $10,520.00 | $3,500.00 | see Estimated Cost Justification WFBD NEPA Review and EA Report v0 | $3,425.00 | N/A |
NEPA Section 106 environmental review, if needed | $6,310.00 | $11,500.00 | see Estimated Cost Justification WFBD NEPA Review and EA Report v0 | $10,350.00 | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $3,680.00 | $3,500.00 | N/A | $2,722.50 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | $0.00 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | $0.00 | N/A |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,500.00 | N/A | $0.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | $0.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $5,000.00 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $5,000.00 | Please see the submitted invoices. |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $10,250.00 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $10,250.00 | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | $0.00 | N/A |
Project management of the transition | $106,650.00 | $111,634.90 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $111,634.90 | x |
Prepare and or review reimbursement form | $2,630.00 | $5,130.00 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $5,130.00 | N/A |
Actual Information Description | File Name |
---|---|
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | |
ASR modification (prepare FCC Form 854) | |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | |
NEPA Section 106 environmental review, if needed | |
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Perform engineering study for new channel assignment and antenna development | |
Address transition timing and coordination issues w/ other stations and wireless | Information not provided. |
Project management of the transition | |
Prepare and or review reimbursement form |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $369,652.69 | $366,047.69 | N/A | $36,041.43 | N/A |
Total for all systems | $6,049,947.69 | $5,730,829.87 | N/A | $5,381,346.95 | N/A |
Other Expenses | $369,652.69 | $366,047.69 | $36,041.43 | ||
Equipment Rental | $446.00 | $446.00 | Please see WFBD Equipment Rental Budget Revision Justification Letter | $446.00 | N/A |
Tower Removal | $186,500.00 | $186,500.00 | At the request of the FCC staff, a line item entitled “tower removal” has been added into the “Other Expenses Not Listed” section reflecting the attached $186,500.00 quote. Please note that this line item is duplicative of the $400,000 line item “Dismantle and Disposal of Old Tower” in the “Tower Equipment and Rigging Cost Information” section. | $0.00 | N/A |
Building modifications, concrete pad, road repairs | $0.00 | $0.00 | N/A | $0.00 | N/A |
Develop and air announcement of upcoming channel change | $1,000.00 | $1,000.00 | N/A | $0.00 | N/A |
Equipment Storage | $16,016.69 | $16,016.69 | See Estimated Cost Justification WFBD-610-Equipment Storage v1 | $16,016.69 | N/A |
Non-zoning permits | $1,000.00 | $1,000.00 | N/A | $0.00 | N/A |
MVPD Notification of Channel Change | $1,000.00 | $1,000.00 | N/A | $0.00 | N/A |
Equipment Delivery and Handling Charges | $50,000.00 | $50,000.00 | N/A | $18,003.74 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $100,000.00 | $100,000.00 | N/A | $1,575.00 | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $190.00 | N/A | $0.00 | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | $0.00 | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,070.00 | N/A | $0.00 | N/A |
DTV Medical Facility Notification | $11,550.00 | $8,000.00 | N/A | $0.00 | N/A |
Local Zoning | $500.00 | $500.00 | N/A | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
Equipment Rental | |
Tower Removal | Information not provided. |
Building modifications, concrete pad, road repairs | Information not provided. |
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Storage | |
Non-zoning permits | Information not provided. |
MVPD Notification of Channel Change | Information not provided. |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | |
FCC Filing Fees - Special Temporary Authorization request | Information not provided. |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
FCC Filing Fees - Form 2100 minor change CP application | Information not provided. |
DTV Medical Facility Notification | Information not provided. |
Local Zoning | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $6,049,947.69 | $5,730,829.87 | $5,381,346.95 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | Yes |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Shane Chaney CFO 03/16/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Shane Chaney CFO 03/16/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Shane Chaney CFO 03/16/2022 |