Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
EDGE SPECTRUM, INC. Doing Business As: EDGE SPECTRUM, INC. |
Randy Weiss PO Box 54025 Hurst, TX 76054 United States |
+1 (214) 770-7770 | randy@crosstalk.org | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
The Preparer is same as the reimbursement contact. |
|
|
|
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | K48GC-D displaced into the core. Applicant will build the CP as part of a coordinated system build out plan. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | Innovator 150 | |
Year | 2012 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | .15 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | EC704MP BB3 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | .35 kW | |
Justification for New Transmitter | Old transmitter cannot be retuned to Ch 34. See attached Comark Transmitter Selection Exhibit. |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | Yes | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | Yes | |
Description | To be determined based on site survey. | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 5 tons | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 3.27 kW | |
Manufacturer | ||
Model | JA/LS-AG-12 | |
Year | 2012 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
ERP: | 3.0 kW | |
Manufacturer | ||
Model | DLP-8B/VP | |
Year | 2020 | |
Justification for New Antenna | Old antenna cut to Ch 48 cannot be used for Ch 34. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Foam | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 110 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Flexible Foam | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 250 feet per run | |
Justification for New Transmission Line | Transmitter is being moved to a new tower site, new line will be required. | |
Interior RF Systems | Does the Installation of the Transmission Line require an additional or replacement Inside RF system including switching, patch panels, and dehydrators? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Ownership | Leased | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1061293 | |
Coordinates (NAD83) | Latitude (NAD83) | 43° 57' 19.0" N- |
Longitude (NAD83) | 124° 04' 30.0" W- | |
Overall Structure Height | 109.91 feet | |
Support Structure Height | 99.74 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 719.81 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | SILKE COMMUNICATIONS INC. | |
Date Constructed | 10/03/1990 |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
New Tower Location |
Transmitter being moved to a new location. |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 80 | |
Explanation | No on site engineering staff. Complete turnkey project management. | |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | No |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | No |
Prepare and file Form FCC License to Cover Application | No | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | Yes | |
Number of Days | 5 | |
Justification | Turnkey installation and integration of new and existing equipment, includes, EAS, satellite hookup, etc. |
Name | Description |
---|---|
Mobilization Charge and travel expenses for installation |
$1500/day, 4 days |
Mobilization Charge and travel expenses for site survey |
$1500/day, 1.5 days |
Site Survey |
8 hours @ $100/hour |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $60,383.00 | $71,968.00 | N/A | $49,935.00 | N/A |
Total for all systems | $191,991.00 | $201,944.06 | N/A | $82,791.06 | N/A |
Primary Transmitter EC704MP BB3 | $60,383.00 | $71,968.00 | $49,935.00 | ||
Transmitter Building Site Survey/Installation | $10,000.00 | $11,050.00 | See Comark Transmitter Quote Installation Line Item | $11,050.00 | N/A |
5 Ton system | $20,250.00 | $20,000.00 | N/A | N/A | N/A |
Other Electrical Service: To be determined based on site survey. | $2,033.00 | $2,033.00 | Electrical Mr. Sparky Quote | N/A | N/A |
UHF - Air Cooled Solid State Transmitter 320 - 700 Watts | $28,100.00 | $38,885.00 | transmitter cost. | $38,885.00 | N/A |
Actual Information Description | File Name |
---|---|
Transmitter Building Site Survey/Installation | |
5 Ton system | Information not provided. |
Other Electrical Service: To be determined based on site survey. | Information not provided. |
UHF - Air Cooled Solid State Transmitter 320 - 700 Watts |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $13,948.00 | $13,948.00 | N/A | $8,218.00 | N/A |
Total for all systems | $191,991.00 | $201,944.06 | N/A | $82,791.06 | N/A |
Primary Antenna DLP-8B/VP | $13,948.00 | $13,948.00 | $8,218.00 | ||
Sweep test of transmission line and antenna | $5,730.00 | $5,730.00 | N/A | N/A | N/A |
UHF-Low Power, Side Mount, Slotted Coaxial, 3.0kW input, Elliptical | $8,218.00 | $8,218.00 | ***System Notice: Estimate adjusted and locked because line has been superseded.***Antenna | $8,218.00 | N/A |
Actual Information Description | File Name |
---|---|
Sweep test of transmission line and antenna | Information not provided. |
UHF-Low Power, Side Mount, Slotted Coaxial, 3.0kW input, Elliptical |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $6,000.00 | $7,938.06 | N/A | $7,938.06 | N/A |
Total for all systems | $191,991.00 | $201,944.06 | N/A | $82,791.06 | N/A |
Primary Transmission Line | $6,000.00 | $7,938.06 | $7,938.06 | ||
Flexible Foam Transmission Line - dielectric, 1 5/8" | $6,000.00 | $7,938.06 | Actual Cost | $7,938.06 | N/A |
Actual Information Description | File Name |
---|---|
Flexible Foam Transmission Line - dielectric, 1 5/8" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $65,690.00 | $65,690.00 | N/A | $0.00 | N/A |
Total for all systems | $191,991.00 | $201,944.06 | N/A | $82,791.06 | N/A |
Primary Tower TOWER | $65,690.00 | $65,690.00 | $0.00 | ||
Tower Rigging Short Tower (less than 500') | $56,190.00 | $56,190.00 | N/A | N/A | N/A |
New Tower Location | $9,500.00 | $9,500.00 | See ARCJ Additional Tower Site relocation Quote and SOW | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $30,635.00 | $27,065.00 | N/A | $11,700.00 | N/A |
Total for all systems | $191,991.00 | $201,944.06 | N/A | $82,791.06 | N/A |
Outside Professional Services | $30,635.00 | $27,065.00 | $11,700.00 | ||
Form 399 assistance or other Program Management costs | $2,000.00 | $2,000.00 | See BWS Estimate Eligibility 1876 Filings | $2,000.00 | N/A |
Site Survey | $800.00 | $800.00 | Site Survey Charge See ARCJ Site Survey Quote & SOW. | $800.00 | N/A |
Mobilization Charge and travel expenses for site survey | $2,250.00 | $2,250.00 | 1 1/2 day @ $1500/day See ARCJ Site Survey Quote & SOW.pdf | $2,250.00 | N/A |
Mobilization Charge and travel expenses for installation | $6,000.00 | $6,000.00 | Mobilization Charge and Travel Expenses for Installation of EAS, CAP. Satellite Interconnect, Final Transmitter/Antenna connection, station turn on. Trip $1500/day 4 days. See ARCJ Turnkey Quote & SOW | $0.00 | N/A |
Additional Field Engineering Service, 5 Days | $5,000.00 | $5,000.00 | Turnkey Installation and integration of new and existing equipment. Installation of EAS,CAP, Satellite Interconnect, Final Transmitter/Antenna connection, station turn on. See ARCJ Turnkey Integration Quote & SOW | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $1,280.00 | $150.00 | CP EXT | $150.00 | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,710.00 | See BWS 399 Reimbursement Estimate | $1,000.00 | N/A |
Project management of the transition | $8,440.00 | $6,000.00 | See ARCJ Project Management Quote & SOW.pdf | $5,500.00 | N/A |
Actual Information Description | File Name |
---|---|
Form 399 assistance or other Program Management costs | |
Site Survey | |
Mobilization Charge and travel expenses for site survey | |
Mobilization Charge and travel expenses for installation | |
Additional Field Engineering Service, 5 Days | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare request for Special Temporary Authorization | |
Prepare/ Review 399 reimbursement form | |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $15,335.00 | $15,335.00 | N/A | $5,000.00 | N/A |
Total for all systems | $191,991.00 | $201,944.06 | N/A | $82,791.06 | N/A |
Other Expenses | $15,335.00 | $15,335.00 | $5,000.00 | ||
Equipment Delivery and Handling Charges | $5,000.00 | $5,000.00 | Removal and disposal of equipment from job site, transmitter, coax, antenna and all debris. SEE K27JP ARCJ Equipment Storage Removal Disposal Quote & SOW.pdf | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $5,000.00 | $5,000.00 | Removal and disposal of equipment from job site, transmitter, coax, antenna and all debris. SEE K27JP ARCJ Equipment Storage Removal Disposal Quote & SOW.pdf | N/A | N/A |
Equipment Storage | $5,000.00 | $5,000.00 | Included SEE ARCJ Equipment Storage Removal Disposal Quote & Sow | $5,000.00 | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Equipment Delivery and Handling Charges | Information not provided. |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
Equipment Storage | |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $191,991.00 | $201,944.06 | $82,791.06 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | SUSAN HANSEN CONSULTANT 10/25/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | RANDY WEISS CEO 10/25/2021 |