Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
TV-49, INC. Doing Business As: TV-49, INC. |
Norman H. Shapiro 26 NORTH HALSTED STREET CHICAGO, IL 60661 United States |
+1 (312) 705-2600 | nshapiro@WCIU.COM | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
The Preparer is same as the reimbursement contact. |
|
|
|
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | WJFB will transition from its pre-auction channel 44 to its post-auction channel 25 at its existing transmission location and in accordance with its transition phase 6 deadline. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | CXE-60 | |
Year | 2003 | |
Type | Inductive Output Tube | |
IOT Power Type | Two | |
Power Capacity | 60 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | THU9evo-40 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 61 kW | |
Justification for New Transmitter | WJFB's existing txmtr. is not returnable & WJFB has been unable to obtain any quotes for a replacement IOT txmtr. Above txmtr is correctly sized to new antenna TPO (30.3kw) as the next size down (50 series) isn't sufficient (29.9kw) to make allocated ERP. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | Yes |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 150 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 3 inches | |
Length | 40.0 feet | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 440.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Txmtr deconstruction and disposal |
Existing IOT transmitter must be deconstructed and disposed of (no parts are salvageable for future use) |
Additional Field Engineering Time |
Additional Field Engineering Time |
Mask Filter |
Mask Filter |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase | |
Manufacturer | ||
Model | UAXTE | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 5 kW | |
Justification for New Transmitter | WJFB's txmtr. bldg. does not have sufficient space to allow installation of new txmtr. without deconstruction of existing IOT transmitter. As such a smaller interim transmitter must be utilized in order to remain on air during this 2-3 wk. period |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A | |
Inside RF System | Is an additional interior RF system required to support this interim transmitter? | No |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 1000.0 kW | |
Manufacturer | ||
Model | TFU29JTH-R04 | |
Year | 2003 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 51.0 kW | |
Manufacturer | ||
Model | ATW22H3-ETO12-25H | |
Year | 2018 | |
Justification for New Antenna | Existing antenna is unable to be utilized for post-auction UHF channel 25 operations. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | Yes | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Circular | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 12.0 kW | |
Manufacturer | ||
Model | 2 x 750 | |
Year | 2017 | |
Justification for New Antenna | WJFB txmtr building does not have sufficient space to allow installation of its repack tx system and existing tx and requires utilization of a smaller interim system in order to avoid going dark during the 2-3wk repack txmtr replacement period |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 3 | |
Frequencies of channels supported | Upper and lower frequency | |
Frequency | 470.0 MHz - 698.0 MHz | |
Do you need a combiner output splitter/switcher for dual feed lines? | No | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | No |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 310 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 19 1/2 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 310 feet per run | |
Justification for New Transmission Line | Existing transmission line has been professionally tested (RF swept) and determined to be unusable for post-auction channel 25 operations |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Type | Flexible Air | |
Diameter | 3 inches | |
Segment Length | N/A | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 270 feet per run | |
Justification for New Transmission Line | Required for installation of interim transmitter/antenna system. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Yes | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1044881 | |
Coordinates (NAD83) | Latitude (NAD83) | 36° 09' 13.0" N- |
Longitude (NAD83) | 086° 22' 46.0" W- | |
Overall Structure Height | 278.87 feet | |
Support Structure Height | 275.59 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 889.10 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | BRYANT BROADCASTING INC | |
Date Constructed | 01/01/1986 |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 350 | |
Explanation | WJFB employs one engineering staff member and, unfortunately, does not have sufficient technical resources to safely and effectively manage a project of this scope without additional outside project management assistance. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | Yes | |
FAA Consultation (including preparation of FAA Form 7460) | Yes | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | No | |
Address transition timing and coordination issues w/ other stations and wireless providers | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | No | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
Internal Employee Time Costs |
Internal Employee Time Costs |
Repacking Related Tax Services |
Repacking Related Tax Services |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $2,129,930.00 | $1,554,413.04 | N/A | $1,329,313.02 | N/A |
Total for all systems | $2,919,946.49 | $2,189,722.52 | N/A | $1,868,514.63 | N/A |
Interim Transmitter UAXTE | $236,500.00 | $163,752.50 | $0.00 | ||
UHF - Air Cooled Solid State Transmitter 4 - 6 kW | $236,500.00 | $163,752.50 | N/A | N/A | N/A |
Primary Transmitter THU9evo-40 | $1,893,430.00 | $1,390,660.54 | $1,329,313.02 | ||
Mask Filter | $0.00 | $0.00 | N/A | $0.00 | N/A |
Additional Field Engineering Time | $2,700.00 | $2,700.00 | N/A | $2,700.00 | N/A |
Other -- Building Addition Size: 440.0 | $3,500.00 | $3,500.00 | N/A | N/A | N/A |
3" Rigid Conduit and Wiring (Cost per foot) | $2,080.00 | $1,800.00 | N/A | N/A | N/A |
Transformer 3 phase/480v - 150 KVA | $25,550.00 | $13,500.00 | N/A | $1,152.48 | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $31,100.00 | N/A | N/A | N/A |
Service entrance 3 phase/800 amp/208 volt | $14,400.00 | $12,600.00 | N/A | N/A | N/A |
UHF - Liquid Cooled Solid State Transmitter 52 - 61 kW | $1,788,000.00 | $1,306,460.54 | Total of transmitter cost, additional parts plus tax. See attached quote from Rohde. | $1,306,460.54 | N/A |
Txmtr deconstruction and disposal | $19,000.00 | $19,000.00 | See attached quote from Marsand. | $19,000.00 | N/A |
Actual Information Description | File Name |
---|---|
UHF - Air Cooled Solid State Transmitter 4 - 6 kW | Information not provided. |
Mask Filter | |
Additional Field Engineering Time | |
Other -- Building Addition Size: 440.0 | Information not provided. |
3" Rigid Conduit and Wiring (Cost per foot) | Information not provided. |
Transformer 3 phase/480v - 150 KVA | |
Switchgear - industrial 800 amp | Information not provided. |
Service entrance 3 phase/800 amp/208 volt | Information not provided. |
UHF - Liquid Cooled Solid State Transmitter 52 - 61 kW | |
Txmtr deconstruction and disposal |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $430,249.32 | $207,679.35 | N/A | $201,834.85 | N/A |
Total for all systems | $2,919,946.49 | $2,189,722.52 | N/A | $1,868,514.63 | N/A |
Interim Antenna 2 x 750 | $134,019.32 | $37,422.32 | $34,077.82 | ||
New combiner, cost per channel (without antenna) | $84,200.00 | $7,189.00 | Combiner cost plus $500 installation. See attached quote from Kathrein | $3,844.50 | N/A |
UHF - High Power, Side Mount, basic slot antenna, 12 kW input, elliptically or circularly polarized | $26,669.32 | $26,669.32 | ***System Notice: Estimate adjusted and locked because line has been superseded.***See attached quote from Kathrein | $26,669.32 | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $3,564.00 | See attached quote from Kathrein | $3,564.00 | N/A |
Primary Antenna ATW22H3-ETO12-25H | $296,230.00 | $170,257.03 | $167,757.03 | ||
Sweep test of existing antenna | $6,730.00 | $6,250.00 | N/A | $3,750.00 | N/A |
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized | $289,500.00 | $164,007.03 | See attached quote from ERI | $164,007.03 | N/A |
Actual Information Description | File Name |
---|---|
New combiner, cost per channel (without antenna) | |
UHF - High Power, Side Mount, basic slot antenna, 12 kW input, elliptically or circularly polarized | |
Side mount brackets for high power antennas (if not included in antenna base cost) | |
Sweep test of existing antenna | |
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $78,550.00 | $120,403.10 | N/A | $107,373.61 | N/A |
Total for all systems | $2,919,946.49 | $2,189,722.52 | N/A | $1,868,514.63 | N/A |
Interim Transmission Line | $15,930.00 | $13,029.49 | $0.00 | ||
Flexible Air Transmission Line - dielectric, 3" | $15,930.00 | $13,029.49 | N/A | N/A | N/A |
Primary Transmission Line | $62,620.00 | $107,373.61 | $107,373.61 | ||
Rigid Transmission Line - copper, 6 1/8" | $62,620.00 | $107,373.61 | See attached quote from ERI and Enertech. Due to the A frame construction of the WJFB self supporting tower, this transmission line package requires additional custom fabricated line hangers, line elbows and fine matching tuner section. | $107,373.61 | N/A |
Actual Information Description | File Name |
---|---|
Flexible Air Transmission Line - dielectric, 3" | Information not provided. |
Rigid Transmission Line - copper, 6 1/8" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $87,200.00 | $185,669.86 | N/A | $185,669.86 | N/A |
Total for all systems | $2,919,946.49 | $2,189,722.52 | N/A | $1,868,514.63 | N/A |
Primary Tower TOWER | $87,200.00 | $185,669.86 | $185,669.86 | ||
Tower Analysis | $3,000.00 | $3,000.00 | N/A | $3,000.00 | N/A |
Short Tower (less than 500') | $84,200.00 | $182,669.86 | This quotation includes the additional cost of installation and removal of the interim antenna and tx line system on WJFB's tower. | $182,669.86 | N/A |
Actual Information Description | File Name |
---|---|
Tower Analysis | |
Short Tower (less than 500') |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $170,268.20 | $104,368.20 | N/A | $37,709.32 | N/A |
Total for all systems | $2,919,946.49 | $2,189,722.52 | N/A | $1,868,514.63 | N/A |
Outside Professional Services | $170,268.20 | $104,368.20 | $37,709.32 | ||
Repacking Related Tax Services | $120.74 | $120.74 | N/A | $120.74 | N/A |
Internal Employee Time Costs | $987.46 | $987.46 | N/A | $987.46 | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $45,000.00 | N/A | N/A | N/A |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $3,680.00 | $3,000.00 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,200.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $8,310.00 | Updating estimated cost per FCC requirement. | $8,310.00 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Project management of the transition | $55,300.00 | $30,000.00 | N/A | $28,291.12 | N/A |
ASR modification (prepare FCC Form 854) | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Repacking Related Tax Services | |
Internal Employee Time Costs | |
Comprehensive coverage verification via field study, if needed | Information not provided. |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | Information not provided. |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Project management of the transition | |
ASR modification (prepare FCC Form 854) | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $23,748.97 | $17,188.97 | N/A | $6,613.97 | N/A |
Total for all systems | $2,919,946.49 | $2,189,722.52 | N/A | $1,868,514.63 | N/A |
Other Expenses | $23,748.97 | $17,188.97 | $6,613.97 | ||
MVPD Notification of Channel Change | $1,500.00 | $1,500.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $1,500.00 | $1,500.00 | N/A | N/A | N/A |
Equipment Storage | $1,000.00 | $1,000.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $4,613.97 | $4,613.97 | N/A | $4,613.97 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $2,500.00 | $2,500.00 | N/A | $0.00 | N/A |
Non-zoning permits | $500.00 | $500.00 | N/A | N/A | N/A |
Local Zoning | $250.00 | $250.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $5,000.00 | N/A | $2,000.00 | N/A |
Actual Information Description | File Name |
---|---|
MVPD Notification of Channel Change | Information not provided. |
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Storage | Information not provided. |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
Non-zoning permits | Information not provided. |
Local Zoning | Information not provided. |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
DTV Medical Facility Notification |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $2,919,946.49 | $2,189,722.52 | $1,868,514.63 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Norman H Shapiro Director, President, Secretary and Treasurer 03/09/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Norman H Shapiro Director, President, Secretary and Treasurer 03/09/2021 |