Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
SCRIPPS BROADCASTING HOLDINGS LLC Doing Business As: SCRIPPS BROADCASTING HOLDINGS LLC |
DAVE GILES 312 WALNUT STREET 28TH FLOOR CINCINNATI, OH 45202 United States |
+1 (513) 977-3000 | DAVE.GILES@SCRIPPS.COM | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Ray Thurber SCRIPPS BROADCASTING HOLDINGS LLC |
Ray Thurber 312 WALNUT STREET 28TH FLOOR CINCINNATI, OH 45202 United States |
+1 (248) 827-9202 | ray.thurber@scripps.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | WTKR antenna will be replaced by a leased broadband antenna. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | SigmaCD-P3 | |
Year | 2005 | |
Type | Inductive Output Tube | |
IOT Power Type | Three | |
Power Capacity | 75 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | ULXTE-80 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 50 kW | |
Justification for New Transmitter | Current Transmitter has been stated as not re-tunable by the manufacturer Current system has 36% excess capacity (overhead) |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | Yes | |
Description | Electrical install | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Disposal removal |
Removal of current transmitter to make room |
Primary Transmitter-Additional Pieces |
Additional pieces required for operation of transmitter |
Primary Transmitter - Remote Control System |
Primary Transmitter - Remote Control System |
Primary Transmitter-GPS Antennas |
GPS antennas necessary to keep the new transmitters locked to a common time |
Primary Transmitter - UPS |
Primary Transmitter - UPS |
Primary Transmitter-Cooling Re-pipe |
Primary Transmitter-Cooling Re-pipe |
Primary Transmitter - Transmitter Installation |
Primary Transmitter - Transmitter Installation |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Lease New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 800.0 kW | |
Manufacturer | ||
Model | TFU-28 GTH-R 06SP | |
Year | 2005 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Lease New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Leased | |
Owner | American Tower | |
Is antenna shared? | Yes | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Broadband Panel | |
Number of Stations Supported | 4 | |
Number of Panels/Bays | 14 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 700.00 MHz | |
Design power capacity in use | 58.0 % | |
Other Antenna Type | N/A | |
ERP: | 565.0 kW | |
Manufacturer | ||
Model | PEPL56D-04-14/56-2-T | |
Year | 2019 | |
Justification for New Antenna | Current antenna is single channel, it will be replaced by a broadband leased antenna. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 3 | |
Frequencies of channels supported | RF channel | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | No | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Broadband | |
Feed Line Size | 8 3/16 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
RF Channel Number |
---|
31 |
16 |
20 |
33 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Lease New | |
Ownership | Leased | |
Owner | American Tower | |
Is antenna shared? | Yes | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Broadband Slot | |
Number of Stations Supported | 4 | |
Number of Panels/Bays | 24 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 700.00 MHz | |
Design power capacity in use | 98.0 % | |
Other Antenna Type | N/A | |
ERP: | 1955.0 kW | |
Manufacturer | ||
Model | SBB-EPD-24C160 | |
Year | 2019 | |
Justification for New Antenna | All stations must have a temporary location while the top antennas are being replaced to maintain service to the viewers.. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 4 | |
Frequencies of channels supported | RF channel | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | No | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | B | |
Feed Line Size | 8 3/16 inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
RF Channel Number |
---|
46 |
16 |
33 |
40 |
Name | Description |
---|---|
Rental |
Rental of Antenna during tower work |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Lease New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | Broadband | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1300 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Lease New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 8 3/16 inches | |
Other Diameter | N/A | |
Segment Length | Broadband | |
Other Segment Length | N/A | |
Number of parallel runs | 2 | |
Length | 1300 feet per run | |
Justification for New Transmission Line | Moving to a Broadband antenna system, current line will not support the power required. |
Name | Description |
---|---|
Primary Transmission Line - Other Expenses |
Primary Transmission Line - Other Expenses |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Lease New | |
Type | Rigid | |
Diameter | 8 3/16 inches | |
Segment Length | Broadband | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 1100 feet per run | |
Justification for New Transmission Line | 4 stations need temporary facilities during construction |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | Candelabra | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1057874 | |
Coordinates (NAD83) | Latitude (NAD83) | 36° 48' 31.8" N- |
Longitude (NAD83) | 076° 30' 11.3" W- | |
Overall Structure Height | 1258.84 feet | |
Support Structure Height | 1254.91 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 22.97 feet | |
Structure Type | GTOWER - Guyed Structure Used for Communication Purposes | |
Tower Owner | American Towers, LLC | |
Date Constructed | 02/03/2006 |
Facility ID | Call Sign | Service |
---|---|---|
4627 | KBCS | FM |
47401 | WTKR | DTV |
25932 | WHRO-TV | DTV |
40759 | WTVZ-TV | DTV |
67077 | WPXV-TV | DTV |
40755 | WNVZ | FM |
82574 | WTPC-TV | DTV |
25933 | WHRV | FM |
25940 | WHRO-FM | FM |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Minor Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Candelabra |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 100 | |
Explanation | Landlord management of the tower project | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | Yes | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
Removal |
Rigging costs to remove current antenna |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,681,020.57 | $1,585,542.07 | N/A | $1,237,320.67 | N/A |
Total for all systems | $5,552,836.21 | $3,027,858.63 | N/A | $1,362,238.63 | N/A |
Primary Transmitter ULXTE-80 | $1,681,020.57 | $1,585,542.07 | $1,237,320.67 | ||
Primary Transmitter - Transmitter Installation | $47,415.50 | $47,415.50 | Please see Tri-star Electric proposal dated 10-8-2018 (split between WTKR and WGNT, less discount) | $30,779.32 | N/A |
Primary Transmitter-Cooling Re-pipe | $6,614.09 | $6,614.09 | Please see Professional Heating and Cooling, Inc. quote dated 9-27-19 | $6,614.09 | N/A |
Primary Transmitter - UPS | $6,513.00 | $6,513.00 | Please see WTKR Primary Transmitter - UPS Budget Revision Justification Letter | $6,513.00 | N/A |
Primary Transmitter-GPS Antennas | $848.00 | $848.00 | Please see GPS Networking estimate 42784, plus shipping and handling on invoice 33715 | $0.00 | N/A |
Primary Transmitter - Remote Control System | $3,238.68 | $3,238.68 | Please see Burk Technology quote 00005059, plus freight and actual expenses on invoice 00070862 | $3,238.68 | N/A |
Primary Transmitter-Additional Pieces | $191.30 | $191.30 | Please see Pasternack quote SQ862329, plus tax and freight on invoice PSIN01023442 | $191.30 | N/A |
Disposal removal | $25,000.00 | $25,000.00 | N/A | $10,640.00 | N/A |
Other Electrical Service: Electrical install | $80,000.00 | $80,000.00 | N/A | $30,054.31 | N/A |
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW | $1,473,000.00 | $1,400,000.00 | N/A | $1,133,568.47 | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $15,721.50 | See Estimated Cost Justification WTKR-110-1st Primary Transmitter - Industrial Switchgear V0 | $15,721.50 | N/A |
Actual Information Description | File Name |
---|---|
Primary Transmitter - Transmitter Installation | |
Primary Transmitter-Cooling Re-pipe | |
Primary Transmitter - UPS | |
Primary Transmitter-GPS Antennas | |
Primary Transmitter - Remote Control System | |
Primary Transmitter-Additional Pieces | |
Disposal removal | |
Other Electrical Service: Electrical install | |
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW | |
Switchgear - industrial 800 amp |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,470,510.00 | $502,550.00 | N/A | $0.00 | N/A |
Total for all systems | $5,552,836.21 | $3,027,858.63 | N/A | $1,362,238.63 | N/A |
Interim Antenna SBB-EPD-24C160 | $270,630.00 | $200,000.00 | $0.00 | ||
Rental | $57,600.00 | $57,600.00 | N/A | N/A | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $0.00 | N/A | N/A | N/A |
Elbow complex, broadband, at antenna input, per 8 3/16. feedline (if needed) | $18,950.00 | $12,000.00 | N/A | N/A | N/A |
UHF - High Power, Side Mount, basic slot antenna, 24 bay,, 1955 kW input, directional,, elliptically or circularly polarized | $80,000.00 | $80,000.00 | N/A | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
New combiner, cost per channel (without antenna) | $84,200.00 | $44,000.00 | N/A | N/A | N/A |
Primary Antenna PEPL56D-04-14/56-2-T | $1,199,880.00 | $302,550.00 | $0.00 | ||
Elbow complex, broadband, at antenna input, per 8 3/16. feedline (if needed) | $18,950.00 | $18,000.00 | N/A | N/A | N/A |
New combiner, cost per channel (without antenna) | $84,200.00 | $80,000.00 | Cost per channel Included installation | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
UHF - High Power Top Mount (200-1000 kW), Four Station broadband panel antenna, elliptically or circularly polarized | $1,090,000.00 | $198,150.00 | WTKR 25% share | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,492,005.00 | $356,376.00 | N/A | $51,079.38 | N/A |
Total for all systems | $5,552,836.21 | $3,027,858.63 | N/A | $1,362,238.63 | N/A |
Interim Transmission Line | $438,900.00 | $120,000.00 | $623.90 | ||
Rigid Transmission Line - copper, 8 3/16" broadband | $438,900.00 | $120,000.00 | N/A | $623.90 | N/A |
Primary Transmission Line | $1,053,105.00 | $236,376.00 | $50,455.48 | ||
Primary Transmission Line - Other Expenses | $15,705.00 | $15,705.00 | Please see Tri-Star Electric Proposal dated 11-7-2019 and Tri-Star Electric Change Order CO #1 - WO# 32829 | $15,210.00 | N/A |
Rigid Transmission Line - copper, 8 3/16" broadband | $1,037,400.00 | $220,671.00 | N/A | $35,245.48 | N/A |
Actual Information Description | File Name |
---|---|
Rigid Transmission Line - copper, 8 3/16" broadband | |
Primary Transmission Line - Other Expenses | |
Rigid Transmission Line - copper, 8 3/16" broadband |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $591,600.00 | $195,333.00 | N/A | $0.00 | N/A |
Total for all systems | $5,552,836.21 | $3,027,858.63 | N/A | $1,362,238.63 | N/A |
Primary Tower GTOWER | $591,600.00 | $195,333.00 | $0.00 | ||
Minor tower reinforcement/modifications | $158,000.00 | $50,000.00 | N/A | N/A | N/A |
Structural engineering tower load study for well documented tower | $12,600.00 | $12,000.00 | N/A | N/A | N/A |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $133,333.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $150,660.00 | $214,175.00 | N/A | $50,744.45 | N/A |
Total for all systems | $5,552,836.21 | $3,027,858.63 | N/A | $1,362,238.63 | N/A |
Outside Professional Services | $150,660.00 | $214,175.00 | $50,744.45 | ||
Removal | $80,000.00 | $80,000.00 | N/A | N/A | N/A |
RF Exposure Measurements | $21,050.00 | $11,000.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $7,360.00 | $3,000.00 | N/A | $600.00 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,000.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $2,000.00 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $4,100.00 | $3,000.00 | N/A | $525.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,000.00 | N/A | N/A | N/A |
Project management of the transition | $15,800.00 | $99,675.00 | Per Estimated Cost Justification WTKR-510-Project Management v0 | $49,619.45 | N/A |
Actual Information Description | File Name |
---|---|
Removal | Information not provided. |
RF Exposure Measurements | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare request for Special Temporary Authorization | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | Information not provided. |
Prepare and or review reimbursement form | Information not provided. |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $167,040.64 | $173,882.56 | N/A | $23,094.13 | N/A |
Total for all systems | $5,552,836.21 | $3,027,858.63 | N/A | $1,362,238.63 | N/A |
Other Expenses | $167,040.64 | $173,882.56 | $23,094.13 | ||
Develop and air announcement of upcoming channel change | $100,000.00 | $100,000.00 | N/A | N/A | N/A |
Equipment Storage | $5,000.00 | $5,000.00 | N/A | $179.39 | N/A |
Equipment Delivery and Handling Charges | $15,000.00 | $15,000.00 | N/A | $717.50 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $380.00 | Two STAs to file | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $18,216.92 | see Estimated Cost Justification WTKR-610-Medical Facility Notifications v0 | $14,236.60 | N/A |
MVPD Notification of Channel Change | $7,960.64 | $7,960.64 | Submitted Channel Change invoices | $7,960.64 | x |
Local Zoning | $2,000.00 | $2,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Storage | |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
FCC Filing Fees - Special Temporary Authorization request | Information not provided. |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
DTV Medical Facility Notification | |
MVPD Notification of Channel Change | |
Local Zoning | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $5,552,836.21 | $3,027,858.63 | $1,362,238.63 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Sravan V Reddy , Reddy . Senior Director, General Accounting 02/11/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Sravan V Reddy , Reddy . Senior Director, General Accounting 02/11/2021 |