Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
KITV, INC. Doing Business As: KITV, INC. |
Wade O'Hagan 999 MONTEREY STREET SUITE 350 SAN LUIS OBISPO, CA 93401 United States |
+1 (805) 548-0602 | sjlwade@aol.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
The Preparer is same as the reimbursement contact. |
|
|
|
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | To relocate from channel 40 to channel 20, KITV will retune its existing primary antenna and install a new transmitter and transmission line at the station's existing tower location. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | DHD30P1 Diamond CD | |
Year | 2004 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 7.5 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | THU9-6 EVO | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 9.8 kW | |
Justification for New Transmitter | The existing transmitter cannot be retuned to operate on channel 20. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | Yes |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 15 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Installation |
Move new transmitter to transmitter room on 40th floor |
Transmitter Room Ventilation |
Transmitter room ventilation services for new transmitter |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Retune Existing |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels | 6 | |
Design power capacity in use | 100.0 % | |
Lower Limit | 470.00 MHz | |
Upper Limit | 600.00 MHz | |
Other Antenna Type | N/A | |
ERP: | 85.0 kW | |
Manufacturer | RFS | |
Model | PHP6U313 | |
Year | 2004 |
Section | Question | Response |
---|---|---|
Sweep Test of Existing Antenna | Do you need a sweep test of existing antenna? | Yes |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Air | |
Diameter | 3 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 250 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Flexible Air | |
Diameter | 3 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 250 feet per run | |
Justification for New Transmission Line | A new transmission line is recommended by antenna manufacturer due to age. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | Located on Building | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1019034 | |
Coordinates (NAD83) | Latitude (NAD83) | 21° 17' 25.0" N- |
Longitude (NAD83) | 157° 50' 24.0" W- | |
Overall Structure Height | 495.07 feet | |
Support Structure Height | 399.93 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 4.92 feet | |
Structure Type | BANT - Building with an Antenna | |
Tower Owner | KITV, Inc. | |
Date Constructed | 01/01/1976 |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Located on Building |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Other Tower Expenses |
Demolition and disposal services |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 200 | |
Explanation | The station's attorney will manage the reimbursement filings, review engineering applications, and engage in any additional coordination that is needed for KITV to accomplish its repack transition over the three year period. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
Other Expenses |
Engineer Travel Expenses |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
Other Expenses |
Engineer Travel Expenses |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $393,338.69 | $389,838.69 | N/A | $327,262.12 | N/A |
Total for all systems | $971,578.69 | $556,879.69 | N/A | $374,468.43 | N/A |
Primary Transmitter THU9-6 EVO | $393,338.69 | $389,838.69 | $327,262.12 | ||
UHF - Air Cooled Solid State Transmitter 9.8 kW | $313,555.00 | $313,555.00 | N/A | $313,555.00 | N/A |
Service entrance 3 phase/800 amp/208 volt | $14,400.00 | $13,700.00 | N/A | $4,123.43 | N/A |
15 Ton system | $55,800.00 | $53,000.00 | N/A | N/A | N/A |
Installation | $5,500.00 | $5,500.00 | N/A | $5,500.00 | N/A |
Transmitter Room Ventilation | $4,083.69 | $4,083.69 | N/A | $4,083.69 | N/A |
Actual Information Description | File Name |
---|---|
UHF - Air Cooled Solid State Transmitter 9.8 kW | |
Service entrance 3 phase/800 amp/208 volt | |
15 Ton system | Information not provided. |
Installation | |
Transmitter Room Ventilation |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $6,730.00 | $8,266.00 | N/A | $8,266.00 | N/A |
Total for all systems | $971,578.69 | $556,879.69 | N/A | $374,468.43 | N/A |
Primary Antenna PHP6U313 | $6,730.00 | $8,266.00 | $8,266.00 | ||
Sweep test of existing antenna | $6,730.00 | $8,266.00 | The invoice from the vendor for the antenna sweep is $8266.00. | $8,266.00 | N/A |
Actual Information Description | File Name |
---|---|
Sweep test of existing antenna |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $14,750.00 | $14,000.00 | N/A | $0.00 | N/A |
Total for all systems | $971,578.69 | $556,879.69 | N/A | $374,468.43 | N/A |
Primary Transmission Line | $14,750.00 | $14,000.00 | $0.00 | ||
Flexible Air Transmission Line - dielectric, 3" | $14,750.00 | $14,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $425,000.00 | $14,000.00 | N/A | $3,665.20 | N/A |
Total for all systems | $971,578.69 | $556,879.69 | N/A | $374,468.43 | N/A |
Primary Tower BANT | $425,000.00 | $14,000.00 | $3,665.20 | ||
Other Tower Expenses | $4,000.00 | $4,000.00 | No predetermined cost associated with this item. | $3,665.20 | N/A |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $10,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Other Tower Expenses | |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $59,680.00 | $59,250.00 | N/A | $22,035.15 | N/A |
Total for all systems | $971,578.69 | $556,879.69 | N/A | $374,468.43 | N/A |
Outside Professional Services | $59,680.00 | $59,250.00 | $22,035.15 | ||
Prepare and or review reimbursement form | $2,630.00 | $5,500.00 | The actual costs were greater than the estimated costs. Estimated costs increased to reflect. | $5,351.25 | N/A |
Project management of the transition | $31,600.00 | $30,000.00 | N/A | $15,528.90 | N/A |
Other Expenses | $0.00 | $0.00 | N/A | $0.00 | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $3,680.00 | $3,500.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | $75.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | $1,080.00 | N/A |
Actual Information Description | File Name |
---|---|
Prepare and or review reimbursement form | |
Project management of the transition | |
Other Expenses | |
Attorney Fees - Prepare and File request for Special Temporary Authorization | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | Information not provided. |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $72,080.00 | $71,525.00 | N/A | $13,239.96 | N/A |
Total for all systems | $971,578.69 | $556,879.69 | N/A | $374,468.43 | N/A |
Other Expenses | $72,080.00 | $71,525.00 | $13,239.96 | ||
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | $335.00 | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | $3,245.00 | N/A |
Other Expenses | $10,000.00 | $10,000.00 | No predetermined cost associated with this item. | $8,024.96 | N/A |
MVPD Notification of Channel Change | $5,000.00 | $5,000.00 | Estimate based on prior experience and site's remote location. | $1,635.00 | N/A |
Develop and air announcement of upcoming channel change | $10,000.00 | $10,000.00 | Estimate based on prior experience. | N/A | N/A |
Equipment Delivery and Handling Charges | $25,000.00 | $25,000.00 | Estimate based on prior experience. | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $10,000.00 | $10,000.00 | Estimate based on prior experience. | N/A | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $190.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
FCC Filing Fees - Form 2100 license to cover application | |
DTV Medical Facility Notification | |
Other Expenses | |
MVPD Notification of Channel Change | |
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Delivery and Handling Charges | Information not provided. |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
FCC Filing Fees - Special Temporary Authorization request | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $971,578.69 | $556,879.69 | $374,468.43 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Wade O'Hagan Vice President 01/07/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Wade O'Hagan Vice President 01/07/2021 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Wade O'Hagan Vice President 01/07/2021 |