Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
KIRO-TV, Inc. Doing Business As: KIRO-TV, Inc. |
Chief Engineer 2807 Third Avenue Seattle, WA 98121 United States |
+1 (206) 728-7777 | knealey@kiro7.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Keith Nealey Director of Engineering KIRO-TV, Inc. |
Chief Engineer 2807 THIRD AVENUE SEATTLE, WA 98121 United States |
+1 (206) 728-7777 | knealey@kiro7.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | We powered down the old transmitter, took down the old antenna and removed the old transmitter. We then installed the new transmitter and antenna in place of the old ones using existing wave guide. This occurred in a three hour period in Nov. of 2018. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | TTHDU-250 | |
Year | 2009 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 180 W |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | UAXTE-3P-C-600W | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 600 W | |
Justification for New Transmitter | Location within the predicted noiselimited contour of and predicted interference greater than 0.5 percent to Post-Incentive-Auction Spectrum Repack facilities of Full-Service station KWDK on Channel 34, which itself is being repacked from Channel 42. |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
Mask Filter |
Mask Filter 625W UHF Part FLUA-0062506AT |
Assembly Parts |
UAXT Kit 10FT Flex Assembly |
Translator Receiver |
Sencore MRD26 Receiver |
Tax |
Tax on all GatesAir transmitter parts |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Bottom | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels | 4 | |
Design power capacity in use | 33.0 % | |
Lower Limit | 692.00 MHz | |
Upper Limit | 698.00 MHz | |
ERP: | 0.95 kW | |
Manufacturer | ||
Model | ALP4L1-HSP-51 | |
Year | 2009 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Bottom | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 0.95 kW | |
Manufacturer | ||
Model | AL4P-18M | |
Year | 2018 | |
Justification for New Antenna | Antenna cannot be retuned to Channel 18 from 51 |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | No |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Ownership | Leased | |
Is this tower consider Complex? | Candelabra | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1056094 | |
Coordinates (NAD83) | Latitude (NAD83) | 47° 30' 16.3" N- |
Longitude (NAD83) | 121° 58' 10.0" W- | |
Overall Structure Height | 310.04 feet | |
Support Structure Height | 270.01 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 2838.88 feet | |
Structure Type | LTOWER - Lattice Tower | |
Tower Owner | American Towers LLC | |
Date Constructed | 12/01/1998 |
Facility ID | Call Sign | Service |
---|---|---|
20357 | KZOK-FM | FM |
4630 | KQMV | FM |
35419 | KWDK | DTV |
20356 | KSWD | FM |
1091 | KJAQ | FM |
57843 | KNUC | FM |
56852 | KWPX-TV | DTV |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | No study needed |
Tower Reinforcements | Please select whether tower reinforcements are needed: | No reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Candelabra |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Tower Climbers |
Rigged tower, removed old antenna, attached new antenna |
Tower Climbers |
Moved translator receive antenna to lower position on tower |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 100 | |
Explanation | KIRO-TV does not have sufficient resource capacity and expertise in house to handle all activities necessary for completion of the station's build by the construction deadline. KIRO-TV will hire an outside firm to facilitate a timely transition. | |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | No |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $37,830.94 | $26,837.19 | N/A | $26,837.19 | N/A |
Total for all systems | $155,415.25 | $70,819.09 | N/A | $67,410.59 | N/A |
Primary Transmitter UAXTE-3P-C-600W | $37,830.94 | $26,837.19 | $26,837.19 | ||
Mask Filter | $3,692.97 | $3,692.97 | N/A | $3,692.97 | N/A |
Assembly Parts | $867.26 | $867.26 | N/A | $867.26 | N/A |
Tax | $2,461.91 | $2,461.91 | N/A | $2,461.91 | N/A |
Translator Receiver | $2,708.80 | $2,708.80 | N/A | $2,708.80 | N/A |
UHF - Air Cooled Solid State Transmitter 320 - 700 Watts | $28,100.00 | $17,106.25 | N/A | $17,106.25 | See attached quote "IAASAQUAH Q-76154 KIRO DRT UAXTE-3P-C 600w.pdf" for type, cooling and power information. |
Actual Information Description | File Name |
---|---|
Mask Filter | |
Assembly Parts | |
Tax | |
Translator Receiver | |
UHF - Air Cooled Solid State Transmitter 320 - 700 Watts |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $13,242.50 | $13,242.50 | N/A | $13,242.50 | N/A |
Total for all systems | $155,415.25 | $70,819.09 | N/A | $67,410.59 | N/A |
Primary Antenna AL4P-18M | $13,242.50 | $13,242.50 | $13,242.50 | ||
UHF-Low Power, Side Mount, Slotted Coaxial, 0.95kW input, Horizontal | $13,242.50 | $13,242.50 | N/A | $13,242.50 | Please see "ERI Antenna Preliminary Specification 20180509-995 ISSAQUAH.pdf" and "ERI Antenna Quote 20180509-995 - Issaquah Translator.pdf" for antenna mounting and polarization details. |
Actual Information Description | File Name |
---|---|
UHF-Low Power, Side Mount, Slotted Coaxial, 0.95kW input, Horizontal |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $9,200.00 | $9,200.00 | N/A | $8,808.00 | N/A |
Total for all systems | $155,415.25 | $70,819.09 | N/A | $67,410.59 | N/A |
Primary Tower LTOWER | $9,200.00 | $9,200.00 | $8,808.00 | ||
Tower Climbers | $1,200.00 | $1,200.00 | N/A | $1,101.00 | N/A |
Complex Tower (includes, e.g., towers with candelabras and/or stacked antennas) | $8,000.00 | $8,000.00 | N/A | $7,707.00 | N/A |
Actual Information Description | File Name |
---|---|
Tower Climbers | |
Complex Tower (includes, e.g., towers with candelabras and/or stacked antennas) |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $94,250.00 | $20,647.59 | N/A | $17,631.09 | N/A |
Total for all systems | $155,415.25 | $70,819.09 | N/A | $67,410.59 | N/A |
Outside Professional Services | $94,250.00 | $20,647.59 | $17,631.09 | ||
RF Exposure Measurements | $12,100.00 | $500.00 | N/A | $150.00 | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $3,262.50 | $47.10 | Please see KIRO-TV1 Attorney Fees - Negotiation of Lease and Other Matters budget justification letter | $47.10 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,740.40 | FCC filing fees are included in the legal costs | $1,740.40 | x |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $1,881.34 | N/A | $1,881.34 | x |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $500.00 | N/A | $300.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $1,200.00 | N/A | $1,017.86 | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $284.50 | N/A | $284.50 | x |
Project management of the transition | $10,550.00 | $2,806.25 | Please see KIRO-TV1 Project Management Budget Revision Justification Letter | $2,806.25 | N/A |
Comprehensive coverage verification via field study, if needed | $52,600.00 | $5,000.00 | N/A | $4,312.15 | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $4,470.00 | $5,188.00 | Staggered RF power increases required multiple changes to the STA request during a period of 3 months. | $3,661.10 | N/A |
Perform engineering study for displacement application | $1,800.00 | $1,500.00 | N/A | $1,430.39 | N/A |
Actual Information Description | File Name |
---|---|
RF Exposure Measurements | |
Attorney Fees - Negotiation of lease and other matters for shared locations | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Prepare/ Review 399 reimbursement form | |
Project management of the transition | |
Comprehensive coverage verification via field study, if needed | |
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Perform engineering study for displacement application |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $891.81 | $891.81 | N/A | $891.81 | N/A |
Total for all systems | $155,415.25 | $70,819.09 | N/A | $67,410.59 | N/A |
Other Expenses | $891.81 | $891.81 | $891.81 | ||
Equipment Delivery and Handling Charges | $891.81 | $891.81 | N/A | $891.81 | N/A |
Actual Information Description | File Name |
---|---|
Equipment Delivery and Handling Charges |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $155,415.25 | $70,819.09 | $67,410.59 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Keith Nealey Director of Engineering 01/19/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Keith Nealey Director of Engineering 01/19/2021 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Keith Nealey Director of Engineering 01/19/2021 |