Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

CBS BROADCASTING INC.

Doing Business As: CBS BROADCASTING INC.

Daniel G. Ryson

1725 DeSales St. NW

Suite 501

Washington, DC 20036

United States

+1 (202) 457-4505 dryson@cbs.com Corporation

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

Daniel G. Ryson

Associate Director of Spectrum Management

CBS

Daniel G. Ryson

1725 DeSales St. NW

Suite 501

Washington, DC 20036

United States

+1 (202) 457-4074 dryson@cbs.com

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. Yes
Briefly describe transition plan Interim post-transition transmitter will be commissioned at the interim site. Following the transition, the interim site will become the new main and the prior main site will be equipped with new transmitter and become the aux.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Auxiliary Transmitter

Back to Top

Add Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Retune Existing
Use Auxiliary (Backup)
Ownership Owned
Owner N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer Harris
Model Maxiva UAX
Year 2012
Type Solid State
Solid State Cooling Air Cooled
Solid State Power capacity 2 kW

Auxiliary Transmitter

Back to Top

Retuning Transmitter Costs

Section Question Response
New IOT Tubes Number of Tubes (including accessories) needed N/A
New Mask Filter
Power 3 kW
Other Power N/A
New Exciter Is a new exciter needed? No

Auxiliary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service No
Description N/A
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Auxiliary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Auxiliary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Auxiliary (Backup)
Description of Use Auxiliary
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model Diamond
Year 2003
Type Solid State
Solid State Cooling Air Cooled
Solid State Power Capacity 21 kW

Auxiliary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Auxiliary (Backup)
Change Type Purchase New
Is this a request for upgraded equipment? No
Manufacturer
Model UAXTE-32R44
Transmitter Type Solid State
Solid State Cooling Air Cooled
Solid State Power capacity 19.2 kW
Justification for New Transmitter Vendor will not retune existing aux transmitter. We will use this transmitter as the interim until the main can be built. Solid State transmitters once considered an upgrade are no longer considered an upgrade.

Auxiliary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service Yes
Description Surge Suppressor and 112.5 Kva Transformer.
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Auxiliary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Additional Electrical Work

Additional Electrical Work for Deer Park site.

Disconnect Old Transmitter

Disconnect old transmitter to create sufficient room for interim transmitter.

State Sales Tax

Auxiliary Transmitter Sales Tax.

Grounding Bonding Etc

Install Ground System for Deer Park site.

RF Accessories

Coaxial Switch and Test Load

Ground Rods Fixtures, etc.

Light fixtures, ground rods, etc.

Emergency Generator

Emergency Generator for Deer Park site.

Test Load

Water Cooled test load for interim transmitter.

New Power Distribution

Replacement Power Distribution Panel

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model Sigma
Year 2009
Type Inductive Output Tube
IOT Power Type Two
Power Capacity 42 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model ULXTE-90
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 56.4 kW
Justification for New Transmitter Vendor will not re-tune the existing backup (see Exhibit 1). New IOT transmitter (see Exhibit 2) is more expensive than proposed transmitter (see Exhibit 3).

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) Yes
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring Yes
Size 4 inches
Length 100.0 feet
Other Electrical Service Yes
Description Transformer 208. Step-down transformer to 208 from 480 required for new transmitter. Larger conductors required.
HVAC Service Does the replacement transmitter require HVAC Service? Yes
Type Cooling Only
Size 30 tons
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? Yes
Size 0.0 square feet
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

RF Accessories

Required for transmitter. See Exhibit 3, item C.

Transmitter Site Survey

GatesAir Basic Site Survey. Determines site conditions and recommend materials and components for installation of GatesAir equipment. See Exhibit 25.

Electrical Sub Panel

New Sub-Panels for locations that are currently not supporting transmitter equipment. See Exhibit 5A.

Additional HVAC Unit

Small (5-Ton) Split System for cooling in the CBS equipment room.

Ducting and Plenum

Modifications to existing HVAC ducting and plenum are necessary for proper cooling of transmitter.

Sales Tax

Primary Transmitter Sales Tax

Fine Matcher

Fine Matcher. See Exhibit 49.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Retune Existing
Antenna Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? Yes
Existing Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Bottom
Polarization Horizontal
Type Broadband Panel
Number of Stations Supported 1
Number of Panels 64
Design power capacity in use 75.0 %
Lower Limit 470.00 MHz
Upper Limit 750.00 MHz
Other Antenna Type N/A
ERP: 540.0 kW
Manufacturer Harris
Model TAD-16UDA 8/64
Year 1995

Primary Antenna

Back to Top

Adjustment to Existing Antenna

Section Question Response
Sweep Test of Existing Antenna Do you need a sweep test of existing antenna? Yes

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? No
Type
Number of channels supported N/A
Frequencies of channels supported N/A
Frequency

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Auxiliary Antenna

Back to Top

Add Antenna Information

Section Question Response
Existing Antenna Description Type of change Retune Existing
Antenna Use Auxiliary (Backup)
Description of Use Doomsday Auxiliary
Ownership Owned
Owner N/A
Site N/A
Is this antenna currently shared with any other stations? Yes
Is this antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? No
Existing Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Panel
Number of Stations Supported 3
Number of Panels 16
Design power capacity in use 35.0 %
Lower Limit 470.00 MHz
Upper Limit 650.00 MHz
Other Antenna Type N/A
ERP: 50.0 kW
Manufacturer Dielectric
Model TUA-C2-8/16M-1
Year 2014

Facility ID's and Call Signs of all stations with whom the antenna is shared.

Facility ID Call Sign
35670 KTLA
47906 KNBC

Auxiliary Antenna

Back to Top

Adjustment to Existing Antenna

Section Question Response
Sweep Test of Existing Antenna Do you need a sweep test of existing antenna? No

Auxiliary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? Yes
Type Additional Module
Number of channels supported 1
Frequencies of channels supported RF channel
Frequency N/A

Enter a list of RF channel numbers.

RF Channel Number
31

Auxiliary Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Interim Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Interim
Description of Use N/A
Change Type Purchase New
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? No
Will antenna be located on or in close proximity to an antenna farm? No
New Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Bottom
Polarization Elliptical
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 590.0 kW
Manufacturer
Model TFU-22JBH/VP-R O8
Year 2019
Justification for New Antenna See March 2018 Invoices Statement and Exhibit 13.

Interim Antenna

Back to Top

Other Antenna Costs

Section Question Response
Elbow Complex Do you require the separate purchase of the Elbow Complex? No
Broadband or Single Channel? N/A
Feed Line Size N/A
Side Mount Brackets Do you require the separate purchase of side mount brackets for an antenna?
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Interim Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Antenna Sales Tax

9.5% State and Local Sales Tax.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Utilize Existing
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing transmission line shared with another station or stations? No
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer Myat and Dielectric
Type Rigid
Diameter 6 1/8 inches
Other Diameter N/A
Segment Length 20 inches
Other Segment Length N/A
Number of parallel runs 1
Length 410 feet per run

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Additional Rigid Line

50 feet of 6 1/8-inch for within building.

Interim Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Interim
Description of Use N/A
Change Type Lease New
Type Rigid
Diameter 6 1/8 inches
Segment Length 20'
Other Segment Length
Number of parallel runs 1
Length 1100 feet per run
Justification for New Transmission Line Transmission line is required for interim facility to function. Includes 10 elbows, gas stop, freight, and accessories, See Exhibit 12.

Interim Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Ceiling Hangers

Ceiling Hangers, Horizontal Anchors, and Shipping.

Coring Entry Plate

Install Entry Plate for Interim Line.

Grounding Bracing Line Routing

Grounding, earthquake bracing and interim transmission line routing.

Sales Tax

9.5% State and Local Taxes

Reinstall Switch

Emergency replacement of coaxial switch and fine matcher during off-air emergency.

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Auxiliary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Auxiliary (Backup)
Description of Use Interim
Ownership Leased
Is this tower consider Complex? Located on Building
Is this tower currently shared with any other stations? No
One or more FM, AM or TV radio broadcaster(s) N/A
Others Types of Users N/A
Is tower documented for structural analysis? Yes
Is tower compliant with Rev G? Yes
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1012836
Coordinates (NAD83) Latitude (NAD83) 34° 13' 55.0" N-
Longitude (NAD83) 118° 04' 21.0" W-
Overall Structure Height 972.43 feet
Support Structure Height 899.60 feet
Ground Elevation Above Mean Sea Level (AMSL) 5658.40 feet
Structure Type GTOWER - Guyed Structure Used for Communication Purposes
Tower Owner American Towers, LLC.
Date Constructed 01/01/1986


Auxiliary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for undocumented/poorly documented tower
Tower Reinforcements Please select whether tower reinforcements are needed: Major Reinforcements needed

Auxiliary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Located on Building
Helicopter Services Required Are helicopter services required? No

Auxiliary Tower

Back to Top

Other Tower Expenses Not Listed

Name Description

Structural Analysis

Cost to conduct structural analysis for tower reinforcements. See Exhibit 5B.

Tower Permit Packages

Permit drawings of tower, ground, and building.

Tower Project Management

Onsite project management for tower modification and RF installation.

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 355
Explanation Company lacks sufficient resources.
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application No
For Auxiliary Facility N/A
For Main Facility N/A
Prepare and file Form FCC License to Cover Application No
For Auxiliary Facility N/A
For Main Facility N/A
Prepare request for Special Temporary Authority No
Quantity N/A
NEPA Section 106 environmental review No
Environmental Assessment No
ASR Modification No
FAA Consultation (including preparation of FAA Form 7460) No
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement No
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study No
RF exposure measurements No
Additional Field Engineering Service No
Number of Days N/A
Justification N/A

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Name Description

Site Coordination Meeting

Site coordination meetings with all broadcasters, contractors and vendors involved with the site project. See Exhibit 5.

Fire Suppression Engineering Permitting

Fire Suppression Engineering and Permitting. Please see Exhibit 112.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning No
Non-zoning permits Yes
BLM or NFS Coordination Yes
FCC Construction Permit Minor Change No
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? Yes
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? Yes
Does this relocation require MVPD Notification of a Channel Change? Yes

Other Expenses

Back to Top

Other Expenses Not Listed

Name Description

Cable Tray Hardware

Interim Site Cable Tray Hardware. See Exhibit 55.

Fire Suppression Engineering Parts and Labor

Fire Suppression Engineering Parts and Labor

GPS Antenna Kits

4 Each GPS Antenna Kits. 2 each required for primary and auxiliary transmitter exciters.

In-House Labor

Time Spent by Internal Employee on Channel Change Tasks.

Self-Assessed Sales Tax

California Sales Tax - Various Items

TX Removal and Installation

Remove Aux TX and assist with new TX system installation.

TX Removal and Installation Cont'd

Remove Aux TX and assist with new TX system installation. Added because prior cost category was locked.

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $4,770,857.45 $2,984,123.64 N/A $2,479,823.60 N/A
Total for all systems $6,911,945.19 $4,684,115.23 N/A $3,990,264.57 N/A
Primary Transmitter ULXTE-90 $3,694,451.77 $2,002,487.45 $1,509,439.35
Sales Tax $100,994.25 $100,994.25 State Sales Tax. Please See Exhibit 3, Page 1. $99,771.13 N/A
Ducting and Plenum $2,500.00 $2,500.00 After remove and replacing transmitters, heat distribution in the transmitter room will change. No additional HVAC is needed but the location of things that need to be cooled will change. N/A N/A
Electrical Sub Panel $4,750.00 $4,750.00 New Sub-Panels for locations that are currently not supporting transmitter equipment. See Exhibit 5B. Final costs exceeded original estimate. Please see Exhibits 111 & 112. $4,750.00 Per American Towers LLC: "Cost Came in slightly higher than estimated." Please see Exhibit 112.
Transmitter Site Survey $7,541.10 $7,541.10 GatesAir Basic Site Survey. Determines site conditions and recommend materials and components for installation of GatesAir equipment. See Exhibit 25. $7,541.10 N/A
RF Accessories $54,194.37 $54,194.37 Coaxial Switch, Coaxial Switch Controller. Required for transmitter. See Exhibit 3, Item C. $54,194.37 N/A
Other -- HVAC Service Type: C Size:30 (Other) $60,000.00 $60,000.00 HVAC required in previously unused space to accommodate new repack transmitter and equipment. See Exhibit 5B. $0.00 N/A
Other Electrical Service: Transformer 208. Step-down transformer to 208 from 480 required for new transmitter. Larger conductors required. $9,983.62 $9,983.62 See Exhibit 3, Item D $9,983.62 N/A
4" Rigid Conduit and Wiring (Cost per foot) $10,100.00 $9,600.00 N/A N/A N/A
Switchgear - industrial 800 amp $38,200.00 $109,992.00 Various electrical wiring changes and additions required at main transmitter site. See Exhibit 7A. $109,992.00 N/A
UHF - Liquid Cooled Solid State Transmitter 52 - 61 kW $1,788,000.00 $1,089,018.70 See Exhibit 57, items A, B, E, Change Orders, and Freight. $669,293.72 N/A
Additional HVAC Unit $22,640.00 $22,640.00 Small (5-Ton) split HVAC unit and ductwork for cooling in CBS equipment room. Required in addition to large (30-Ton) unit being installed by American Tower. See quote provided as Exhibit 85. $22,640.00 N/A
Other -- Building Addition Size: 0.0 $119,090.00 $119,090.00 Prepare previously unused space to accommodate repack transmitter. See Exhibit 5B for initial quotation. Final costs exceeded original estimate. Please see Exhibits 111 & 112. $119,090.00 Per American Towers LLC Exhibit 112: "Preperation on previously unused space to accomidate repack equipment." (sic). Please Exhibit 112 Item 3-C-3.
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW $1,473,000.00 $408,724.98 ***System Notice: Estimate adjusted and locked because line has been superseded.***See Exhibit 3, items A, B, and E. $408,724.98 N/A
Fine Matcher $3,458.43 $3,458.43 Fine Matcher. Includes Tax and Freight. See exhibits 48 and 49. $3,458.43 N/A
Auxiliary Transmitter Maxiva UAX $109,355.00 $14,585.51 $14,585.51
UHF and VHF - minor banding issues $105,200.00 $11,001.95 Retune Mask Filter - See Exhibit 6A. (This is a newer quotation than that Exhibit 6 but there was no change in estimated cost.) $11,001.95 N/A
3 kW mask filter $4,155.00 $3,583.56 See $3,150 quote provided as Exhibit 76 plus 299.25 sales tax and $122.66 shipping and $11.65 for sales tax on shipping. $3,583.56 N/A
Auxiliary Transmitter UAXTE-32R44 $967,050.68 $967,050.68 $955,798.74
New Power Distribution $26,372.73 $26,372.73 The new transmitter required circuit breaker sizes that are no longer available to the old, no longer manufactured or supported, power distribution panel. Please see Exhibit 121 for quote. $26,372.64 N/A
Test Load $2,933.88 $2,933.88 Water cooled test load. Required to test interim transmitter. See Exhibit 66 for quote. $2,933.88 N/A
Emergency Generator $150,000.00 $150,000.00 Emergency Generator. Duplicates capability at main primary. See Exhibits 68 and 69. $150,000.00 N/A
Ground Rods Fixtures, etc. $9,126.27 $9,126.27 See quotes provided as Exhibit 72, 73, and 74. $8,573.01 asfd
RF Accessories $84,232.34 $84,232.34 Coaxial Switch and Dummy Load for Interim Transmitter. See Exhibit 61 for quotation ($58,079.90), Exhibit 84 for sales tax ($4,472.44), and Exhibit 87 ($21,680.00) for installation labor . $84,232.33 N/A
Grounding Bonding Etc $4,053.42 $4,053.42 Install and provide ground bus bars and ground transmitter at Deer Park site. See Exhibit 44 for quote and details. $4,053.42 N/A
State Sales Tax $53,298.00 $53,298.00 State Sales Tax. Please see Exhibit 4, Page 1. $42,599.42 N/A
Disconnect Old Transmitter $1,950.00 $1,950.00 Disconnect an old transmitter. This work was necessary to create room for the new interim transmitter. Please see quote in Exhibit 98. $1,950.00 N/A
Additional Electrical Work $71,257.00 $71,257.00 Various electrical work required at Deer Park site. Please see quote provided as Exhibit 42 ($65,055) plus Exhibit 103 ($6,202). $71,257.00 N/A
Other Electrical Service: Surge Suppressor and 112.5 Kva Transformer. $4,309.03 $4,309.03 Surge suppressor and transformer required for proper operation of transmitter. See Exhibit 4. $4,309.03 N/A
UHF - Air Cooled Solid State Transmitter 19.2 kW $23,512.89 $23,512.89 Transmitter, mask filter, and installation/proof. Estimated Cost is based on $559,518.01 (see Exhibit 4 items A, B, D plus Change Orders Q-74735 and Q-79831 in Exhibit 110A) minus already reimbursed $536,005.12 shown in another now locked cost category. $23,512.89 asdf
UHF - Air Cooled Solid State Transmitter 19 kW $536,005.12 $536,005.12 ***System Notice: Estimate adjusted and locked because line has been superseded.***Transmitter, mask filter, and installation/proof. required for operation of interim site. Comparable to Widelity Cost Catalog pricing for 20 kW transmitter. See Exhibit 4, Items A, B, and D plus Change Orders Q-74735 and Q-79831 in Exhibit 110. $536,005.12 N/A

Components

Actual Information Description File Name
Sales Tax

Component Description:
Sales Tax on Items shipped to Corona at 7.75% and to Mount Wilson at 9.5%. See Exhibit 57.
Amount:
$287.61

Component Description:
Invoice is for Progress Payment on comparable ULXTE-60 Primary Transmitter. This cost represents Sales Tax on items shipped. See October 2018 GatesAir Statement.
Amount:
$99,483.52
Ducting and Plenum Information not provided.
Electrical Sub Panel

Component Description:
Invoice is Final "True-Up" Payment for American Tower at Deer Park Site. This cost is Electrical Sub Panel cost. See Exhibit 112 Item 3-C-6.
Amount:
$250.00

Component Description:
Invoice is 25% Milestone 3 Payment for American Tower at Deer Park Site. This cost is 25% of Estimated Electrical Sub Panel cost. See Quote Exhibit 5B Item 3-C-6.
Amount:
$1,125.00

Component Description:
Invoice is 50% Progress Payment for American Tower at Deer Park Site. This cost is 50% of Estimated Electrical Sub Panel cost. See Quote Exhibit 5B Item 3-C-6.
Amount:
$2,250.00

Component Description:
Invoice is 25% Down Payment for American Tower at Deer Park Site. This cost is 25% of Estimated Electrical Sub Panel cost. See Quote Exhibit 5B Item 3-C-6.
Amount:
$1,125.00
Transmitter Site Survey

Component Description:
GatesAir Basic Site Survey. Determines site conditions and recommend materials and components for installation of GatesAir equipment.
Amount:
$7,541.10
RF Accessories

Component Description:
Invoice is for Progress Payment on comparable ULXTE-60 Transmitter. This cost represents 2/3 of Exhibit 21A line item C. See October 2018 GatesAir Statement.
Amount:
$36,129.58

Component Description:
Invoice is for 1/3 Progress Payment on comparable ULXTE-60 Transmitter. This cost represents 1/3 of Exhibit 18B line item C. See October 2018 GatesAir Statement.
Amount:
$18,064.79
Other -- HVAC Service Type: C Size:30 (Other)

Component Description:
Invoice is 50% Progress Payment for American Tower at Deer Park Site. This cost is 50% of Estimated 30 Ton HVAC. See Quote Exhibit 5B Item 3-C-3.
Amount:
$30,000.00

Component Description:
HVAC System Was Never Installed by American Towers LLC per this "True-Up" invoice.
Amount:
($60,000.00)

Component Description:
Invoice is 25% Milestone 3 Payment for American Tower at Deer Park Site. This cost is 25% of Estimated 30 Ton HVAC. See Quote Exhibit 5B Item 3-C-2.
Amount:
$15,000.00

Component Description:
Invoice is 25% Down Payment for American Tower at Deer Park Site. This cost is 25% of Estimated 30 Ton HVAC. See Quote Exhibit 5B Item 3-C-2.
Amount:
$15,000.00
Other Electrical Service: Transformer 208. Step-down transformer to 208 from 480 required for new transmitter. Larger conductors required.

Component Description:
Invoice is for Progress Payment on comparable ULXTE-60 Transmitter. This cost represents 2/3 of Exhibit 21A line item D. See October 2018 GatesAir Statement.
Amount:
$6,655.75

Component Description:
Invoice is for 1/3 Progress Payment on comparable ULXTE-60 Transmitter. This cost represents 1/3 of Exhibit 18B line item D. See October 2018 GatesAir Statement.
Amount:
$3,327.87
4" Rigid Conduit and Wiring (Cost per foot) Information not provided.
Switchgear - industrial 800 amp

Component Description:
Final payment for electrical work at Weathervane site. See Exhibit 7A for quote.
Amount:
$3,799.00

Component Description:
Progress Payment on Electrical at Weathervane Site. See Exhibit 7A for quote and details.
Amount:
$26,000.00

Component Description:
Progress Payment on Electrical at Weathervane Site. See Exhibit 7A for quote and details.
Amount:
$28,696.00

Component Description:
Weathervane site electric work. Progress payment for September 2018. See Exhibit 43.
Amount:
$20,000.00

Component Description:
Progress payment for electrical work at Weathervane site. See Exhibit 7A for quote.
Amount:
$31,497.00
UHF - Liquid Cooled Solid State Transmitter 52 - 61 kW

Component Description:
Invoice is for Final Payment on comparable ULXTE-60 Transmitter. This cost represents Installation, Freight for non-upgraded transmitter, and Change Order Q79220.
Amount:
$81,389.31

Component Description:
Invoice is for 1/3 Progress Payment on comparable ULXTE-60 Transmitter. This cost represents 1/3 of Exhibit 18B line items A, B, and E Minus the two Change Orders. See October 2018 GatesAir Statement.
Amount:
$352,130.35

Component Description:
Invoice is for Progress Payment on comparable ULXTE-60 Transmitter. This cost represents remaining balance on Exhibit 21A line items A and B. See October 2018 GatesAir Statement.
Amount:
$235,774.06
Additional HVAC Unit

Component Description:
Small (5-Ton) HVAC unit for cooling CBS equipment room.
Amount:
$22,640.00
Other -- Building Addition Size: 0.0

Component Description:
Invoice is Final "True-Up" Payment for American Tower at Deer Park Site. This cost is for Building addition. See Exhibit 112 Item 3-C-3.
Amount:
$89,090.00

Component Description:
Invoice is 25% Milestone 3 Payment for American Tower at Deer Park Site. This cost is 25% of Building addition. See Quote Exhibit 5B Item 3-C-3.
Amount:
$7,500.00

Component Description:
Invoice is 50% Progress Payment for American Tower at Deer Park Site. This cost is 50% of Building addition. See Quote Exhibit 5B Item 3-C-3.
Amount:
$15,000.00

Component Description:
Invoice is 25% Down Payment for American Tower at Deer Park Site. This cost is 25% of Building addition. See Quote Exhibit 5B Item 3-C-3.
Amount:
$7,500.00
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW

Component Description:
Approximately 1/3 Down Payment.
Amount:
$408,724.98

Component Description:
Please delete this cost component, which has been moved to the corrected transmitter model. Intentionally seeking $0.00 here.
Amount:
N/A

Component Description:
Please delete this cost component, which has been moved to the corrected transmitter model. Intentionally seeking $0.00 here.
Amount:
N/A
Fine Matcher

Component Description:
Fine Matcher. Includes Tax and Freight.
Amount:
$3,458.43
UHF and VHF - minor banding issues

Component Description:
Retune Verdugo Peak Transmitter and Mask Filter. See Exhibit 6A for quotation.
Amount:
$11,001.95
3 kW mask filter

Component Description:
Sales Tax on Aux TX Mask Filter Shipping.
Amount:
$11.65

Component Description:
Sales tax for Verdugo Peak Mask Filter.
Amount:
$299.25

Component Description:
Mask Filter shipping
Amount:
$122.66

Component Description:
New 3 kW Mask Filter. See quote provided as Exhibit 76.
Amount:
$3,150.00
New Power Distribution

Component Description:
Electrical Distribution Panel Progress Payment. Please see Exhibit 121 for quote.
Amount:
$15,823.58

Component Description:
Electrical Distribution Panel Final Payment. Please see Exhibit 121 for quotation.
Amount:
$10,549.06
Test Load

Component Description:
Test load for interim transmitter.
Amount:
$2,933.88
Emergency Generator

Component Description:
Emergency generator at interim site. See Exhibits 68-70, Duplicates existing capability at primary site.
Amount:
$150,000.00

Component Description:
Emergency generator at interim site. See Exhibits 68-70, Duplicates existing capability at primary site.
Amount:
$150,000.00
Ground Rods Fixtures, etc.

Component Description:
Provide and install lighting fixtures, ground rods, and a 30 amp circuit. Please see statement and quotes provided in Exhibit 75A. Excludes $553.26 for corridor fixtures per RFI.
Amount:
$8,573.01
RF Accessories

Component Description:
Coax switch, switch controller, pump module, etc. Tax listed separately.
Amount:
$51,418.50

Component Description:
Sales tax on RF System. See Exhibit 84B.
Amount:
$4,472.43

Component Description:
Installation services for Interim Transmitter Switch and Load. Freight listed separately. Please see quote in Exhibit 87.
Amount:
$6,661.40

Component Description:
Install KCBS RF System and Test Load. See quotation provided as Exhibit 87.
Amount:
$21,680.00
Grounding Bonding Etc

Component Description:
Install ground system - Labor Only. See Exhibits 44 and 45.
Amount:
$1,520.00

Component Description:
Install ground system - Materials Only. See Exhibits 44 and 46.
Amount:
$2,533.42
State Sales Tax

Component Description:
Sales Tax on Aux Transmitter Change Order.
Amount:
$78.91

Component Description:
Invoice is for 1/3 Progress Payment on UAXTE-32R44 Transmitter. This cost represents 100% of Sales Tax See October 2018 GatesAir Statement.
Amount:
$42,520.51
Disconnect Old Transmitter

Component Description:
Invoice includes multiple items split into four cost categories. Please see Exhibits 98 and 99.
Amount:
$1,950.00
Additional Electrical Work

Component Description:
Please see quote provided as Exhibit 42.
Amount:
$65,055.00

Component Description:
Work to provide emergency power to KCBS-TV STL Room at interim site. See Exhibit 103 for proposal.
Amount:
$6,202.00
Other Electrical Service: Surge Suppressor and 112.5 Kva Transformer.

Component Description:
Invoice is for 1/3 Progress Payment on comparable UAXTE-32R44 Transmitter. This cost represents 2/3 of Exhibit 18 line item C. Items A, B, and D are listed separately. See October 2018 GatesAir Statement.
Amount:
$2,872.69

Component Description:
Invoice is for 1/3 Progress Payment on comparable UAXTE-32R44 Transmitter. This cost represents 1/3 of Exhibit 4 line item C. See October 2018 GatesAir Statement.
Amount:
$1,436.34
UHF - Air Cooled Solid State Transmitter 19.2 kW

Component Description:
Transmitter installation plus various components (See change orders Q-74735 and Q-79831 in Exhibit 110A).
Amount:
$23,512.89
UHF - Air Cooled Solid State Transmitter 19 kW

Component Description:
Approximately 1/3 Down Payment
Amount:
$204,709.34

Component Description:
Invoice is for 1/3 Progress Payment on comparable UAXTE-32R44 Transmitter. This cost represents 2/3 of Exhibit 18 line items B and D and remainder of balance for item A. Item C is listed separately. See October 2018 GatesAir Statement.
Amount:
$204,469.99

Component Description:
This invoice is now shown in a different cost category.
Amount:
N/A

Component Description:
Invoice is for 1/3 Progress Payment on comparable UAXTE-32R44 Transmitter. This cost represents a portion of Exhibit 4 line items A, B, and D plus one Change Order. See October 2018 GatesAir Statement.
Amount:
$126,825.79

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $420,513.46 $437,242.46 N/A $387,385.24 N/A
Total for all systems $6,911,945.19 $4,684,115.23 N/A $3,990,264.57 N/A
Interim Antenna TFU-22JBH/VP-R O8 $329,583.46 $390,842.46 $350,896.50
Antenna Sales Tax $33,353.46 $33,353.46 9.5% Sales Tax on Antenna (see Exhibit 13) minus V-Pol cost. N/A N/A
Sweep test of existing antenna $6,730.00 $6,400.00 Please see quote provided as Exhibit 12. $6,400.00 N/A
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized $289,500.00 $351,089.00 This bottom-mount stacked antenna must provide structural support for big, top-mount VHF antenna. Includes elbow complex, repack sweep, and one fixed length of 6-inch line. Additional V-Pol cost was subtracted. See Exhibit 13. $344,496.50 N/A
Primary Antenna TAD-16UDA 8/64 $0.00 $0.00 $0.00
Auxiliary Antenna TUA-C2-8/16M-1 $90,930.00 $46,400.00 $36,488.74
Adding a module to existing combiner (without antenna) $84,200.00 $40,000.00 See Exhibit 80 for combiner cost which will be shared with two other stations. KCBS-TV's share is $19,940.74 including shipping and tax. Revised installation cost is shown in Exhibit 105. $36,488.74 N/A
Sweep test of existing antenna $6,730.00 $6,400.00 N/A N/A N/A

Components

Actual Information Description File Name
Antenna Sales Tax Information not provided.
Sweep test of existing antenna

Component Description:
Please see Exhibits 93 and 94.
Amount:
$6,400.00
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized

Component Description:
This invoice is the 45% down payment for the main antenna Including elbow complex, repack sweep, and one fixed length of 6-inch line. Additional V-Pol cost was subtracted.
Amount:
$155,110.05

Component Description:
Antenna and Elbow Complex 10% Final Payment. Excludes V-Pol upgrade. Please see Exhibits 49 and 50.
Amount:
$34,276.40

Component Description:
This invoice is the 45% progress payment for the main antenna Including elbow complex, repack sweep, and one fixed length of 6-inch line. Additional V-Pol cost was subtracted.
Amount:
$155,110.05
Adding a module to existing combiner (without antenna)

Component Description:
Progress payment invoice divided among five cost categories. Please see Exhibit 106A for details.
Amount:
$12,565.81

Component Description:
Invoice is for 1/2 Down Payment as specified in quote (Exhibit 8A). This cost represents 1/6 (1/2 of 1/3) of the Verdugo Peak auxiliary antenna combiner installation which will be shared with two other stations.
Amount:
$2,500.00

Component Description:
Verdugo Peak Combiner Sales Tax. Shared with two other stations so only seeking 1/3 of costs. Combiner and shipping listed separately.
Amount:
$1,674.41

Component Description:
Invoice is for 30% Progress Payment as specified in quote (Exhibit 8A). This cost represents a portion of the Verdugo Peak auxiliary antenna combiner installation which will be shared with two other stations.
Amount:
$1,500.00

Component Description:
12.4638% progress payment on KCBS-TV pro rata share of aux combiner installation. Please see Exhibit 89C.
Amount:
$623.19

Component Description:
Verdugo Peak Combiner. Shared with two other stations so only seeking 1/3 of costs. Tax and shipping listed separately. See Exhibit 76 for quotation.
Amount:
$17,625.33
Sweep test of existing antenna Information not provided.

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $277,378.65 $261,762.25 N/A $227,176.86 N/A
Total for all systems $6,911,945.19 $4,684,115.23 N/A $3,990,264.57 N/A
Interim Transmission Line $267,778.65 $252,162.25 $227,176.86
Sales Tax $18,585.39 $18,585.39 9.5% State and Local Tax on Interim Transmission Line. N/A N/A
Ceiling Hangers $7,421.26 $7,421.26 Ceiling hangers, horizontal anchor, and freight. See quote in Exhibit 52 and shipping in Exhibit 54. $7,421.26 N/A
Rigid Transmission Line - copper, 6 1/8" $222,200.00 $206,583.60 Please see March 2018 Invoices Statement and Exhibit 12 ($195,635.60) plus Change Orders Exhibits 90 ($924.00), 96 ($7,175.00), and 113 ($2,849.00). Shipping listed separately. $200,183.60 N/A
Reinstall Switch $4,200.00 $4,200.00 Emergency replacement of transmission line switch and fine-matcher during off-air emergency due to failure of prior components. Please see Exhibit 100. $4,200.00 N/A
Grounding Bracing Line Routing $11,212.00 $11,212.00 Grounding, bracing, and interim transmission line routing. Please see Exhibits 98 and 99. $11,212.00 N/A
Coring Entry Plate $4,160.00 $4,160.00 Core drill transmission line entry plate. Please see quote provided as Exhibit 98. $4,160.00 N/A
Primary Transmission Line $9,600.00 $9,600.00 $0.00
Additional Rigid Line $9,600.00 $9,600.00 Required for installation of new post-transition transmitter. (Widelity Cost Catalog pricing shown.) N/A N/A

Components

Actual Information Description File Name
Sales Tax Information not provided.
Ceiling Hangers

Component Description:
Freight for Ceiling Hangers. See Exhibits 52 and 54A.
Amount:
$4,803.96

Component Description:
Ceiling Hangers and Horizontal Anchors. Please see Exhibits 52 and 53A.
Amount:
$2,617.30
Rigid Transmission Line - copper, 6 1/8"

Component Description:
Additional short custom cut transmission line. See Exhibit 90 for quotation.
Amount:
$924.00

Component Description:
Final payment for interim transmission line. Please see Exhibit 92.
Amount:
$11,238.56

Component Description:
Cut line sections. Please see quotation provided as Exhibit 113. Freight listed separately.
Amount:
$2,849.00

Component Description:
Invoice is 45% Down Payment for Transmission Line at Deer Park Site. This cost is 45% of the line, estimated shipping and field engineer. See Quote Exhibit 12.
Amount:
$88,036.02

Component Description:
Invoice is 45% Progress Payment for Transmission Line at Deer Park Site. This cost is 45% of the line, estimated shipping and field engineer. See Quote Exhibit 12.
Amount:
$88,036.02

Component Description:
Additional short pieces of transmission line. See quote provided as Exhibit 96. Shipping listed separately.
Amount:
$9,100.00
Reinstall Switch

Component Description:
Emergency replacement of coaxial switch and fine matcher during off-air emergency. Please see Exhibit 100.
Amount:
$4,200.00
Grounding Bracing Line Routing

Component Description:
Grounding, earthquake bracing, and routing interim transmission line. Please see Exhibits 98 and 99.
Amount:
$11,212.00
Coring Entry Plate

Component Description:
Core drill and install entry plate for interim transmission line. Please see Exhibits 98 and 99.
Amount:
$4,160.00
Additional Rigid Line Information not provided.

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $903,688.00 $451,964.25 N/A $447,264.25 N/A
Total for all systems $6,911,945.19 $4,684,115.23 N/A $3,990,264.57 N/A
Auxiliary Tower GTOWER $903,688.00 $451,964.25 $447,264.25
Major tower reinforcement/modifications $421,000.00 $150,000.00 It is expected that the additional loads imposed on the tower by the new appurtenances required for the repack project will cause the tower to fail. The structural failure is expected to be in the major category. See Exhibit 5B. $150,000.00 N/A
Structural Analysis $5,238.00 $5,238.00 Cost to conduct structural analysis for tower reinforcements. See Exhibit 5B. $5,238.00 N/A
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study $26,300.00 $10,300.00 Structural tower mapping to provide data to the structural engineer in order to generate the correct structural output. See Exhibit 5B. $10,300.00 N/A
Tower Project Management $20,000.00 $20,000.00 Due to the complexity of the site and its access, it was estimated that onsite project management would be a duration of 40 hours. See Exhibit 5B. Final costs exceeded original estimate. Please see Exhibits 111 and 112. $20,000.00 Per American Towers LLC Exhibit 112: "Increased civil scope and weather delays on project extended construction management cost."
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $256,276.25 Includes mobilization and tower rigging per the failing structural, removal of existing top antenna and tower top section, etc. See Exhibit 5B. Final costs exceeded original estimate. Please see Exhibits 111 & 112. $256,276.25 Per American Towers LLC Exhibit 112, Top Tower plate was welded on. Not caught in original SOW required fire watch and permit, extra time to modify tower grating for installation of transmission lines, Antenna delivery delays, post tower inspection.
Tower Permit Packages $10,150.00 $10,150.00 Generation of tower, building, and ground construction drawings required for local permits. See Exhibit 5B. ($4,700 plus $4,700, plus $750) $5,450.00 N/A

Components

Actual Information Description File Name
Major tower reinforcement/modifications

Component Description:
Invoice is 25% Milestone 3 Payment for American Tower at Deer Park Site. This cost is 25% of Estimated Major Tower Reinforcement. See Quote Exhibit 5B Item 3-A-2.
Amount:
$37,500.00

Component Description:
Invoice is 50% Down Payment for American Tower at Deer Park Site. This cost is 50% of Estimated Major Tower Reinforcement. See Quote Exhibit 5B Item 3-A-2.
Amount:
$75,000.00

Component Description:
Invoice is 25% Down Payment for American Tower at Deer Park Site. This cost is 25% of Estimated Major Tower Reinforcement. See Quote Exhibit 5B Item 3-A-2.
Amount:
$37,500.00
Structural Analysis

Component Description:
Structural Analysis, Main Tower. For Quote, see Exhibit 5A 3-A-1.
Amount:
$5,238.00
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study

Component Description:
Tower Mapping, Main Tower. For Quote, see Exhibit 5A 3-A-1.
Amount:
$10,300.00
Tower Project Management

Component Description:
Invoice is Final "True-Up" Payment for American Tower at Deer Park Site. This cost is for Tower Construction Management. See Exhibit 112 Item 3-D-1.
Amount:
$10,000.00

Component Description:
Invoice is 25% Milestone 3 Payment for American Tower at Deer Park Site. This cost is 25% of estimated tower construction project Management. See Quote Exhibit 5B Item 3-D-1.
Amount:
$2,500.00

Component Description:
Invoice is 50% Progress Payment for American Tower at Deer Park Site. This cost is 50% of estimated tower construction project Management. See Quote Exhibit 5B Item 3-D-1.
Amount:
$5,000.00

Component Description:
Invoice is 25% Down Payment for American Tower at Deer Park Site. This cost is 25% of estimated tower construction project Management. See Quote Exhibit 5B Item 3-D-1.
Amount:
$2,500.00
Complex Tower (includes, for example, those with candelabras and/or stacked antennas)

Component Description:
Invoice is Final "True-Up" Payment for American Tower at Deer Park Site. This cost is for Tower Rigging. See Exhibit 112 Item 3-C-1.
Amount:
$14,636.25

Component Description:
Invoice is 25% Milestone 3 Payment for American Tower at Deer Park Site. This cost is 25% of Tower Rigging for a Tall Tower. See Quote Exhibit 5B Item 3-C-1.
Amount:
$60,410.00

Component Description:
Invoice is 25% Down Payment for American Tower at Deer Park Site. This cost is 25% of Tower Rigging for a Tall Tower. See Quote Exhibit 5B Item 3-C-1.
Amount:
$60,410.00

Component Description:
Invoice is 50% Down Payment for American Tower at Deer Park Site. This cost is 50% of Tower Rigging for a Tall Tower. See Quote Exhibit 5B Item 3-C-1.
Amount:
$120,820.00
Tower Permit Packages

Component Description:
Invoice is 100% payment for American Tower costs at Deer Park Site. This cost is 100% of Estimated Building Permits. See Quote Exhibit 5B Item 1-A-3 ($750) plus Item 3-D-1 ($4,700).
Amount:
$5,450.00

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $99,760.00 $115,580.00 N/A $38,742.50 N/A
Total for all systems $6,911,945.19 $4,684,115.23 N/A $3,990,264.57 N/A
Outside Professional Services $99,760.00 $115,580.00 $38,742.50
Fire Suppression Engineering Permitting $14,000.00 $14,000.00 Engineering and Permitting for relocation of Halon nozzles and required upgrade to FM-200 system. Please see Exhibit 112 Item 1-B-1. $14,000.00 N/A
Site Coordination Meeting $5,000.00 $5,000.00 Site coordination meetings with all broadcasters, contractors and vendors involved with the site project. All involved parties will jointly define a site action plan and cutover approach. See Exhibit 5B. $5,000.00 N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $4,210.00 $4,000.00 N/A N/A N/A
Prepare request for Special Temporary Authorization $2,050.00 $1,500.00 N/A N/A N/A
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application $1,580.00 $1,500.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A $1,662.50 The actual cost was slightly complicated by the necessary use of a complex tower and stacked antennas.
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application $2,105.00 $2,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $3,000.00 N/A N/A N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $6,100.00 N/A $6,100.00 N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A $2,500.00 N/A
Project management of the transition $56,090.00 $74,480.00 Company lacks sufficient resources. See Exhibits 5B and 7. $9,480.00 N/A

Components

Actual Information Description File Name
Fire Suppression Engineering Permitting

Component Description:
Engineering and Permitting for relocation of Halon nozzles and required upgrade to FM-200 system. Please see Exhibit 112 Item 1-B-1.
Amount:
$14,000.00
Site Coordination Meeting

Component Description:
Invoice is 25% Milestone 3 Payment for American Tower at Deer Park Site. This cost is 25% of Site Coordination Meeting. See Quote Exhibit 5B Item 1-B-1.
Amount:
$1,250.00

Component Description:
Invoice is 50% Down Payment for American Tower at Deer Park Site. This cost is 50% of Site Coordination Meeting. See Quote Exhibit 5B Item 1-B-1.
Amount:
$2,500.00

Component Description:
Invoice is 25% Down Payment for American Tower at Deer Park Site. This cost is 25% of Site Coordination Meeting. See Quote Exhibit 5B Item 1-B-1.
Amount:
$1,250.00
Attorney Fees - Negotiation of lease and other matters for shared locations Information not provided.
Prepare request for Special Temporary Authorization Information not provided.
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application

Component Description:
Invoice shows actual cost to prepare Engineering Section of the FCC Construction Permit Application for main antenna.
Amount:
$1,662.50
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application Information not provided.
Perform engineering study for new channel assignment and antenna development

Component Description:
Study antenna mounting options and coordinate with other stations on tower.
Amount:
$3,712.50

Component Description:
Preliminary Engineering Study of Channel Assignment.
Amount:
$1,825.00

Component Description:
Further antenna studies and meetings with other stations to discuss antenna mounting alternatives.
Amount:
$562.50
Address transition timing and coordination issues w/ other stations and wireless

Component Description:
Invoice is 25% Milestone 3 Payment for American Tower at Deer Park Site. This cost is 25% of Coordination planning costs. See Quote Exhibit 5B Item 1-A-1.
Amount:
$625.00

Component Description:
Invoice is 25% Down Payment for American Tower at Deer Park Site. This cost is 25% of Coordination planning costs. See Quote Exhibit 5B Item 1-A-1.
Amount:
$625.00

Component Description:
Invoice is 50% Down Payment for American Tower at Deer Park Site. This cost is 50% of Coordination planning costs. See Quote Exhibit 5B Item 1-A-1.
Amount:
$1,250.00
Project management of the transition

Component Description:
Invoice is 100% payment for American Tower costs at Deer Park Site. This cost is 100% of Tower Project Management. See Quote Exhibit 5B Item 1-A-1.
Amount:
$9,480.00

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $439,747.63 $433,442.63 N/A $409,872.12 N/A
Total for all systems $6,911,945.19 $4,684,115.23 N/A $3,990,264.57 N/A
Other Expenses $439,747.63 $433,442.63 $409,872.12
TX Removal and Installation Cont'd $10,362.32 $10,362.32 Cost category added because original TX Removal and Installation category was locked for some reason. Amount shown is difference between $137,500 proposal and $127,137.68 already specified in the other category. $3,795.16 N/A
TX Removal and Installation $127,137.68 $127,137.68 ***System Notice: Estimate adjusted and locked because line has been superseded.***Estimate includes items in Exhibit 8A except Equipment Storage, Equipment Delivery, and Disposal, and 2/3 of the Verdugo Peak combiner installation costs, which will be shared between three stations. Also includes costs in Exhibit 62. $127,137.68 N/A
Self-Assessed Sales Tax $63,131.39 $63,131.39 Self-assessed Sales and Use Taxes paid to California Department of Tax and Fee Administration for invoices related to FCC Spectrum Repacking. Please see Exhibit 118. $63,131.39 N/A
In-House Labor $2,861.63 $2,861.63 A small portion of internal labor costs for this project. Please see Exhibit 117A. $2,861.63 N/A
GPS Antenna Kits $1,364.86 $1,364.86 ***System Notice: Estimate adjusted and locked because line has been superseded.***Four GPS Antenna Kits. Two each for primary and auxiliary transmitter exciters. Cost includes Sales Tax and Freight. See Exhibits 58 and 59. $1,364.86 N/A
Fire Suppression Engineering Parts and Labor $108,069.00 $108,069.00 Please see American Towers LLC Exhibit 112 Item 1-B-1. Halon nozzles had to be relocated to accommodate new transmitters. Code required halon system to be upgraded to FM-200 with any modification. $108,069.00 N/A
Cable Tray Hardware $1,374.40 $1,374.40 ***System Notice: Estimate adjusted and locked because line has been superseded.***Cable Tray Hardware - Required at Interim Site. See Exhibit 55. $1,374.40 N/A
MVPD Notification of Channel Change $1,000.00 $1,000.00 N/A N/A N/A
Develop and air announcement of upcoming channel change $1,000.00 $1,000.00 N/A N/A N/A
Equipment Storage $5,000.00 $5,000.00 See Exhibit 8A. $4,761.20 N/A
Equipment Delivery and Handling Charges $74,848.22 $74,848.22 See Exhibits 8A ($15,000), 51 ($14,131.13), 82 ($641), 83 ($60.89), 89 ($1,869.57), 91 ($439.72), 92 (11,238.56), 97 ($9,499.21), 98 ($9,430), 110 ($9,241.49), 114 ($1,093.99), and 116 ($2,202.66). $61,023.67 N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $29,768.13 $29,768.13 See Exhibit 8A. Final costs exceeded original estimate. Please see Exhibits 111 & 112. $29,768.13 After the original estimates, it was determined that unused equipment could be moved to make room for electrical disconnects. This required removal and disposal of 6 racks of unused equipment.
BLM or NFS Coordination $1,000.00 $1,000.00 See Exhibit 5B. $1,000.00 N/A
Non-zoning permits $750.00 $750.00 The cost of preparation and submission of the needed forms (excluding permit drawing package) for permits for jurisdictional permits required for electrical, building and other repack required tasks. See Exhibit 5B. N/A N/A
FCC Filing Fees - Special Temporary Authorization request $195.00 $190.00 N/A N/A N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $335.00 N/A $335.00 N/A
DTV Medical Facility Notification $11,550.00 $5,250.00 See Exhibit 9. $5,250.00 N/A

Components

Actual Information Description File Name
TX Removal and Installation Cont'd

Component Description:
Progress payment invoice divided among five cost categories. Please see Exhibit 106A for details.
Amount:
$3,795.16
TX Removal and Installation

Component Description:
Invoice represents 12.4638% of estimated transmitter removal and installation cost. Please see Exhibit 89C.
Amount:
$17,137.68

Component Description:
Invoice is for 1/2 Down Payment as specified in quote (Exhibit 8A). This cost represents 1/2 of Exhibit 8A items except equipment storage, transportation, disposal, and 2/3 of Verdugo Peak combiner installation which will be shared with other stations.
Amount:
$68,750.00

Component Description:
30% Progress Payment per quote (Exhibit 8A). This cost represents 30% of Exhibit 8A items except equipment storage, transportation, disposal, and 2/3 of Verdugo Peak combiner installation which will be shared with other stations.
Amount:
$41,250.00
Self-Assessed Sales Tax

Component Description:
Sales and Use Tax for invoices that did not include tax or had a tax rate lower than the prevailing rate. See Exhibit 118A.
Amount:
$63,131.39
In-House Labor

Component Description:
Internal labor. Please see Exhibit 117A for necessary documentation.
Amount:
$2,861.63
GPS Antenna Kits

Component Description:
Four GPS Antenna Kits. Two required for primary and auxiliary transmitter exciters.
Amount:
$1,364.86
Fire Suppression Engineering Parts and Labor

Component Description:
Please see American Towers LLC Exhibit 112 Item 1-B-1. Halon nozzles had to be relocated to accommodate new transmitters. Code required halon system to be upgraded to FM-200 with any modification.
Amount:
$108,069.00
Cable Tray Hardware

Component Description:
Includes items 1-5 shown on quotation 105486 (Exhibit 55). Items 1-5 used at KCBS-TV interim site.
Amount:
$1,374.40
MVPD Notification of Channel Change Information not provided.
Develop and air announcement of upcoming channel change Information not provided.
Equipment Storage

Component Description:
Invoice represents 2.76% of estimated equipment storage cost. Please see Exhibit 106A.
Amount:
$138.01

Component Description:
Invoice is for 30% Progress per quote (Exhibit 8A). This cost represents 30% of Equipment Storage.
Amount:
$1,500.00

Component Description:
Invoice is for 1/2 Down Payment as specified in quote (Exhibit 8A). This cost represents 1/2 of Equipment Storage.
Amount:
$2,500.00

Component Description:
Invoice represents 12.4638% of estimated equipment storage cost. Please see Exhibit 89C.
Amount:
$623.19
Equipment Delivery and Handling Charges

Component Description:
30% Progress Payment as specified in quote (Exhibit 8A). This cost represents 30% of Equipment Transportation.
Amount:
$4,500.00

Component Description:
Shipping sales tax for Verdugo Peak auxiliary antenna combiner used by two other stations. Shipping tax cost split three ways. See Exhibit 83A.
Amount:
$60.89

Component Description:
Freight shipping and handling for cut line sections. Please see Exhibit 113 for quotation.
Amount:
$1,093.99

Component Description:
Receive transmission line and reload it to a smaller truck that's permitted on the Mt. Wilson access road. Please see Exhibits 98 and 99.
Amount:
$9,430.00

Component Description:
Shipping for custom-cut transmission line. See Exhibit 91.
Amount:
$439.72

Component Description:
Shipping for Verdugo Peak auxiliary ntenna combiner used by two other stations. Shipping cost split three ways. See Exhibit 82.
Amount:
$641.00

Component Description:
Invoice represents 2.76% of estimated equipment delivery and handling cost. Please see Exhibit 106A.
Amount:
$414.02

Component Description:
Freight for Coaxial Switch, Controller, and Cable. Please see quote in Exhibit 87.
Amount:
$2,202.66

Component Description:
Shipping for various custom cut pieces of transmission line. See Exhibit 97A.
Amount:
$9,499.21

Component Description:
Antenna and elbow complex shipping. See Exhibit 51A.
Amount:
$14,131.13

Component Description:
Invoice is for 1/2 Down Payment as specified in quote (Exhibit 8A). This cost represents 1/2 of Equipment Transportation.
Amount:
$7,500.00

Component Description:
Auxiliary transmitter freight. Please see exhibit 110A.
Amount:
$9,241.49

Component Description:
Progress Payment as specified in quote (Exhibit 8A). This cost represents 12.4638% of Equipment Transportation. See Exhibit 89B. (Rounded Down $0.01 per RFI 10 Dec 2019)
Amount:
$1,869.56
Disposal Costs (for equipment and other waste, net of any salvage value)

Component Description:
Invoice is for 1/2 Down Payment as specified in quote (Exhibit 8A). This cost represents 1/2 of Equipment Disposal.
Amount:
$5,000.00

Component Description:
It was determined that unused equipment could be moved to make room for electrical disconnects. This required removal of 6 racks of unused equipment.
Amount:
$20,245.75

Component Description:
Invoice represents 2.76% of estimated equipment delivery and handling cost. Please see Exhibit 106A.
Amount:
$276.00

Component Description:
30% Progress Payment per quote (Exhibit 8A). This cost represents 30% of Equipment Disposal.
Amount:
$3,000.00

Component Description:
Invoice represents 12.4638% of estimated equipment disposal cost. Please see Exhibit 89C.
Amount:
$1,246.38
BLM or NFS Coordination

Component Description:
Invoice is 25% Milestone 3 Payment for American Tower at Deer Park Site. This cost is 25% of BLM coordination. See Quote Exhibit 5B Item 1-A-3.
Amount:
$250.00

Component Description:
Invoice is 50% Progress Payment for American Tower at Deer Park Site. This cost is 50% of BLM coordination. See Quote Exhibit 5B Item 1-A-3.
Amount:
$500.00

Component Description:
Invoice is 25% Down Payment for American Tower at Deer Park Site. This cost is 25% of BLM coordination. See Quote Exhibit 5B Item 1-A-3.
Amount:
$250.00
Non-zoning permits Information not provided.
FCC Filing Fees - Special Temporary Authorization request Information not provided.
FCC Filing Fees - Form 2100 license to cover application

Component Description:
FCC Filing Fee for KCBS-TV License Application "to cover" Construction Permit facility.
Amount:
$335.00
DTV Medical Facility Notification

Component Description:
Please see quote provided as Exhibit 9.
Amount:
$5,250.00

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $6,911,945.19 $4,684,115.23 $3,990,264.57

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. Yes
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Andrew J Siegel

Assistant Secretary


10/05/2020

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Andrew J Siegel

Assistant Secretary


10/05/2020