Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
Tribune Broadcasting Company II LLC Doing Business As: TRIBUNE BROADCASTING OKLAHOMA CITY LICENSE,LLC |
Elizabeth Ryder 545 E. John Carpenter Freeway Suite 700 Irving, TX 75062 United States |
+1 (972) 373-8800 | eryder@nexstar.tv | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Bill Vanduynhoven , Vanduynhov . Sr Director of Engineering RF Systems NEXSTAR BROADCASTING, INC. |
Bill Vanduynhoven 2211 Rabbit Hill Cir Dacula, GA 30019 United States |
+1 (404) 312-8693 | Bvanduynhoven@Nexstar.tv |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | Move KAUT to a an existing Tribune owned site and install a Broadband antenna. Site requires renovation to support the operation. KOPX also repacked will be a tenant on the new antenna. KFOR a non repacked station will also move to this site. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | Sigma CD P3 | |
Year | 2006 | |
Type | Inductive Output Tube | |
IOT Power Type | Three | |
Power Capacity | 90 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | ULXTE-60 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 36 kW | |
Justification for New Transmitter | Current transmitter has be stated by Manufacturer as not re-tunable. KAUT is moving to another tower and will install replacement transmitter at new site. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | Yes |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 300 kVA | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | Yes | |
Description | New electrical distribution | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Heating and Cooling | |
Size | 30 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 2000.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Asbestos abatement |
Clean building and make safe for new system |
Removal Disposal |
Clear Suite at current site |
Ice protection |
Ice shield over critical equipment |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 1000.0 kW | |
Manufacturer | ||
Model | TFU-30DSC-R 03 | |
Year | 2006 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | Yes | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Broadband Panel | |
Number of Stations Supported | 2 | |
Number of Panels/Bays | 25 | |
Lower Limit | 490.00 MHz | |
Upper Limit | 590.00 MHz | |
Design power capacity in use | 60.0 % | |
Other Antenna Type | N/A | |
ERP: | 2000.0 kW | |
Manufacturer | ||
Model | TUM25-04-16/64H-2-R-T | |
Year | 2018 | |
Justification for New Antenna | Current antenna will not work on assigned channel. Moving to different site |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 3 | |
Frequencies of channels supported | RF channel | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | Yes | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Broadband | |
Feed Line Size | 8 3/16 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
RF Channel Number |
---|
27 |
18 |
19 |
Name | Description |
---|---|
KAUT Combiner install |
Install of KAUT combiner |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 7 3/16 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1600 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 8 3/16 inches | |
Other Diameter | N/A | |
Segment Length | Broadband | |
Other Segment Length | N/A | |
Number of parallel runs | 2 | |
Length | 1900 feet per run | |
Justification for New Transmission Line | Moving to different site. Current line would not support power or channel required. Tower would not support operation from the original site |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1043710 | |
Coordinates (NAD83) | Latitude (NAD83) | 35° 34' 07.0" N- |
Longitude (NAD83) | 097° 29' 21.0" W- | |
Overall Structure Height | 1602.01 feet | |
Support Structure Height | 1508.84 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 1146.97 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Local TV Oklahoma, LLC | |
Date Constructed | 04/06/1965 |
Facility ID | Call Sign | Service |
---|---|---|
69175 | KROU | FM |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for undocumented/poorly documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Serious Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | Candelabra | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1045226 | |
Coordinates (NAD83) | Latitude (NAD83) | 35° 35' 52.1" N- |
Longitude (NAD83) | 097° 29' 23.2" W- | |
Overall Structure Height | 1646.96 feet | |
Support Structure Height | 1549.85 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 1102.02 feet | |
Structure Type | GTOWER - Guyed Structure Used for Communication Purposes | |
Tower Owner | American Towers, LLC. | |
Date Constructed | 02/01/1999 |
Facility ID | Call Sign | Service |
---|---|---|
58390 | KTST | FM |
58389 | KXXY-FM | FM |
38214 | KSBI | DTV |
84225 | KOCM | DTV |
66222 | KFOR-TV | DTV |
11918 | KJYO | FM |
11964 | KBRU | FM |
2566 | KOPX-TV | DTV |
25382 | KWTV-DT | DTV |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Candelabra |
Helicopter Services Required | Are helicopter services required? | Yes |
Name | Description |
---|---|
Removal of current |
Lease requirement to remove the current antenna and line |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 1000 | |
Explanation | Construction supervision by Manhattan construction. Extensive site work required | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | No |
For Auxiliary Facility | N/A | |
For Main Facility | N/A | |
Prepare and file Form FCC License to Cover Application | No | |
For Auxiliary Facility | N/A | |
For Main Facility | N/A | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | No | |
Address transition timing and coordination issues w/ other stations and wireless providers | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | Yes | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
Binding and insurance |
Insurance for the construction |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | No | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
Design fees |
Architectural design fees |
Security |
Armed Security |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $2,488,400.00 | $2,260,700.00 | N/A | $832,863.86 | N/A |
Total for all systems | $7,490,575.00 | $5,574,500.00 | N/A | $1,404,146.99 | N/A |
Primary Transmitter ULXTE-60 | $2,488,400.00 | $2,260,700.00 | $832,863.86 | ||
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW | $1,473,000.00 | $1,275,000.00 | N/A | $832,863.86 | N/A |
Removal Disposal | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Asbestos abatement | $0.00 | $0.00 | N/A | $0.00 | N/A |
Other -- Building Addition Size: 2000.0 | $150,000.00 | $150,000.00 | N/A | N/A | N/A |
30 Ton system | $166,000.00 | $162,000.00 | N/A | N/A | N/A |
Other Electrical Service: New electrical distribution | $285,000.00 | $285,000.00 | N/A | N/A | N/A |
Transformer 3 phase/480v - 300 KVA | $36,800.00 | $30,000.00 | N/A | N/A | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $20,000.00 | N/A | N/A | N/A |
Service entrance 3 phase/800 amp/208 volt | $14,400.00 | $13,700.00 | N/A | N/A | N/A |
Ice protection | $300,000.00 | $300,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW | |
Removal Disposal | Information not provided. |
Asbestos abatement | Information not provided. |
Other -- Building Addition Size: 2000.0 | Information not provided. |
30 Ton system | Information not provided. |
Other Electrical Service: New electrical distribution | Information not provided. |
Transformer 3 phase/480v - 300 KVA | Information not provided. |
Switchgear - industrial 800 amp | Information not provided. |
Service entrance 3 phase/800 amp/208 volt | Information not provided. |
Ice protection | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,063,880.00 | $919,050.00 | N/A | $113,333.01 | N/A |
Total for all systems | $7,490,575.00 | $5,574,500.00 | N/A | $1,404,146.99 | N/A |
Primary Antenna TUM25-04-16/64H-2-R-T | $1,063,880.00 | $919,050.00 | $113,333.01 | ||
Elbow complex, broadband, at antenna input, per 8 3/16. feedline (if needed) | $18,950.00 | $16,650.00 | N/A | $0.00 | N/A |
KAUT Combiner install | $60,000.00 | $60,000.00 | N/A | $27,011.31 | N/A |
Combiner output splitting/switching for dual feed lines, if applicable | $126,000.00 | $50,000.00 | N/A | N/A | N/A |
New combiner, cost per channel (without antenna) | $84,200.00 | $96,000.00 | CIF Combiner with Mask Filter | $86,321.70 | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | $0.00 | N/A |
UHF - High Power Top Mount (200-1000 kW), Two Station broadband panel antenna, elliptically or circularly polarized | $768,000.00 | $690,000.00 | N/A | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
Elbow complex, broadband, at antenna input, per 8 3/16. feedline (if needed) | |
KAUT Combiner install | |
Combiner output splitting/switching for dual feed lines, if applicable | Information not provided. |
New combiner, cost per channel (without antenna) | |
Sweep test of existing antenna | |
UHF - High Power Top Mount (200-1000 kW), Two Station broadband panel antenna, elliptically or circularly polarized |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,516,200.00 | $900,000.00 | N/A | $0.00 | N/A |
Total for all systems | $7,490,575.00 | $5,574,500.00 | N/A | $1,404,146.99 | N/A |
Primary Transmission Line | $1,516,200.00 | $900,000.00 | $0.00 | ||
Rigid Transmission Line - copper, 8 3/16" broadband | $1,516,200.00 | $900,000.00 | N/A | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
Rigid Transmission Line - copper, 8 3/16" broadband |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $2,009,800.00 | $1,110,000.00 | N/A | $420,936.12 | N/A |
Total for all systems | $7,490,575.00 | $5,574,500.00 | N/A | $1,404,146.99 | N/A |
Primary Tower TOWER | $1,408,800.00 | $805,000.00 | $420,936.12 | ||
Serious tower reinforcement/modifications | $1,052,000.00 | $560,000.00 | N/A | $356,121.48 | N/A |
Tall Tower (greater than 500') | $210,500.00 | $100,000.00 | N/A | $64,814.64 | N/A |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study | $26,300.00 | $25,000.00 | N/A | N/A | N/A |
Tower Helicopter Lift | $120,000.00 | $120,000.00 | N/A | N/A | N/A |
Primary Tower GTOWER | $601,000.00 | $305,000.00 | $0.00 | ||
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $125,000.00 | N/A | N/A | N/A |
Tower Helicopter Lift | $80,000.00 | $80,000.00 | Only if joint operation with other stations | N/A | N/A |
Removal of current | $100,000.00 | $100,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Serious tower reinforcement/modifications | |
Tall Tower (greater than 500') | |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study | Information not provided. |
Tower Helicopter Lift | Information not provided. |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | Information not provided. |
Tower Helicopter Lift | Information not provided. |
Removal of current | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $255,245.00 | $235,500.00 | N/A | $0.00 | N/A |
Total for all systems | $7,490,575.00 | $5,574,500.00 | N/A | $1,404,146.99 | N/A |
Outside Professional Services | $255,245.00 | $235,500.00 | $0.00 | ||
Binding and insurance | $60,000.00 | $60,000.00 | Required by Manhattan construction | N/A | N/A |
RF Exposure Measurements | $21,050.00 | $11,000.00 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $4,100.00 | $3,000.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | N/A | N/A |
Project management of the transition | $158,000.00 | $150,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $157,050.00 | $149,250.00 | N/A | $37,014.00 | N/A |
Total for all systems | $7,490,575.00 | $5,574,500.00 | N/A | $1,404,146.99 | N/A |
Other Expenses | $157,050.00 | $149,250.00 | $37,014.00 | ||
Security | $35,000.00 | $35,000.00 | N/A | $33,264.00 | N/A |
Design fees | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
MVPD Notification of Channel Change | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
Equipment Storage | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $20,500.00 | $20,500.00 | N/A | $0.00 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Local Zoning | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $3,750.00 | N/A | $3,750.00 | N/A |
Actual Information Description | File Name |
---|---|
Security | |
Design fees | Information not provided. |
MVPD Notification of Channel Change | Information not provided. |
Equipment Storage | Information not provided. |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
Local Zoning | Information not provided. |
DTV Medical Facility Notification |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $7,490,575.00 | $5,574,500.00 | $1,404,146.99 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Teri Ann Guillory Broadcasting Operations 03/04/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Teri Ann Guillory Broadcasting Operations 03/04/2021 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Teri Ann Guillory Broadcasting Operations 03/04/2021 |