Go to the Federal Communications Commission homepage at www.fcc.gov

FCC Form 399: Reimbursement Request

Approved by OMB 3060-1178
Go to the Federal Communications Commission homepage at www.fcc.gov

(REFERENCE COPY - Not for submission) FCC Form 399: Reimbursement Request

Facility ID:
74118
Service:
LPT
Call Sign:
WKMG-LD
Channel:
21 (UHF)
File Number:
0000087862
FRN:
0003582384
Eligibility Status:
Eligible
Date Submitted:
08/07/2020

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

GRAHAM MEDIA GROUP, ORLANDO, INC.

Doing Business As: GRAHAM MEDIA GROUP, ORLANDO, INC.

Frank Torbert

4466 JOHN YOUNG PARKWAY

ORLANDO, FL 32804

United States

+1 (407) 521-1200 ftorbert@wkmg.com Corporation

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

William T. Godfrey , Jr .

Consulting Engineers

Kessler and Gehman Associates, Inc.

William T. Godfrey, Jr.

Kessler and Gehman Associates, Inc.

507-D NW 60th Street

Gainesville, FL 32607

United States

+1 (352) 332-3157 bill@kesslerandgehman.com

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan Replace existing equipment that cannot operate on new displaced channel with new equipment. Analyze and modify 222-G tower as required. Installation and decommission services as required.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Retune Existing
Use Primary (Main)
Ownership Owned
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer Larcan
Model MXi802U
Year 2010
Type Solid State
Solid State Cooling Air Cooled
Solid State Power capacity 500 W

Primary Transmitter

Back to Top

Retuning Transmitter Costs

Section Question Response
New Mask Filter Does the transmitter require a new mask filter? Yes
Mask Filter Type Full Service
Power 1kW
New Exciter Is a new exciter needed? Yes
Exciter Type Single frequency agile

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Other Transmitter Costs
Does the transmitter installation require a Transmitter Building Site Survey/Installation? Yes
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Rigid Conduit and Wiring Yes
Size 3 inches
Length 100.0 feet
Other Electrical Service No
HVAC Service Does the replacement transmitter require HVAC Service? No
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Ownership Owned
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? No
Existing Antenna Manufacturer and Type
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Other
Other Antenna Type Parapanel
ERP: 7.1 kW
Manufacturer
Model 4DR-12S
Year 2011

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Change Type Purchase New
Ownership Owned
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? No
New Antenna Manufacturer and Types
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Other
Other Antenna Type Parapanel
ERP: 4.9 kW
Manufacturer
Model SCA-4DR4SCH21
Year 2019
Justification for New Antenna Existing Channel 42 antenna cannot operate on new displaced channel. A new antenna must be purchased so that the displaced TV Translator facility can operate on the new channel.

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Elbow Complex Do you require the separate purchase of the Elbow Complex? No
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna? No
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? Yes
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

FEEDER CABLES

SCALA BAY FEEDER CABLES Quote #: 546580

POWER DIVIDER

SCALA 3 WAY POWER DIVIDER Quote #: 546580

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Utilize Existing
Use Primary (Main)
Ownership Owned
Is the existing transmission line shared with another station or stations? No
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer Andrew
Type Flexible Foam
Diameter 1 5/8 inches
Number of parallel runs 1
Length 450 feet per run

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Sweep

Transmission Line Sweep required to verify line measures well on new channel

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Ownership Leased
Is this tower consider Complex? No
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users No
Is tower documented for structural analysis? No
Is tower compliant with Rev G? No
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1036814
Coordinates (NAD83) Latitude (NAD83) 29° 16' 06.0" N-
Longitude (NAD83) 082° 04' 50.0" W-
Overall Structure Height 1366.78 feet
Support Structure Height 1272.95 feet
Ground Elevation Above Mean Sea Level (AMSL) 82.02 feet
Structure Type TOWER - Free Standing or Guyed Structure
Tower Owner Saga South Communications, LLC
Date Constructed 01/01/1986

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
49962 WOGK FM

Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Tower mapping and report for structural engineer
Tower Reinforcements Please select whether tower reinforcements are needed: Minor Reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower N/A
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Information not provided.

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 200
Explanation It will be necessary to complete progress reports, and update Schedule 399s. Station does not have available personnel or personnel trained in project management for such complex projects.
Outside RF consulting Engineering Services Perform engineering study for displacement application Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Prepare Form 601 Yes
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Negotiation of Lease and other Matter for Shared Locations No
Prepare or Review FCC Form 399 for Reimbursement Yes
Form 399 assistance or other program management costs Yes
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements Yes
Additional Field Engineering Service Yes
Number of Days 5
Justification Other field engineering services may be required

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Information not provided.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Permit and Filing Costs FCC Construction Permit Major Change No
FCC Construction Permit Minor Change No
FCC License to Cover Application No
FCC Special Temporary Authority Application No
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? Yes
Point to Point Microwave (STL/ICR) Frequency Coordination for Unidirection System No
Frequency Coordination for Bi-Direction System No
New Point to Point Microwave System No

Other Expenses

Back to Top

Other Expenses Not Listed

Name Description

Sales Tax

Sales Tax for displacement equipment and services

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $50,600.00 $47,750.00 N/A $2,500.00 N/A
Total for all systems $410,080.81 $205,146.32 N/A $19,346.34 N/A
Primary Transmitter MXi802U $50,600.00 $47,750.00 $2,500.00
Transmitter Building Site Survey/Installation $10,000.00 $10,000.00 N/A N/A N/A
3" Rigid Conduit and Wiring (Cost per foot) $5,200.00 $5,200.00 N/A N/A N/A
Single frequency agile exciter $21,050.00 $21,050.00 N/A N/A N/A
1kW w mask filter Full Service $3,350.00 $2,500.00 N/A $2,500.00 N/A
Retune - UHF and VHF - minor re-channel issues $11,000.00 $9,000.00 N/A $0.00 N/A

Components

Actual Information Description File Name
Transmitter Building Site Survey/Installation Information not provided.
3" Rigid Conduit and Wiring (Cost per foot) Information not provided.
Single frequency agile exciter Information not provided.
1kW w mask filter Full Service

Component Description:
Quote was for $2,868.33 but discounted price is $2,500 as seen in Invoice Number 0432202.
Amount:
$2,500.00
Retune - UHF and VHF - minor re-channel issues

Component Description:
Transmitter Re-tune
Amount:
$9,000.00

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $15,493.31 $11,623.31 N/A $6,623.31 N/A
Total for all systems $410,080.81 $205,146.32 N/A $19,346.34 N/A
Primary Antenna SCA-4DR4SCH21 $15,493.31 $11,623.31 $6,623.31
UHF-Low Power, Side Mount, Other, 4.9kW input, Horizontal $2,863.32 $2,863.32 N/A $2,863.32 N/A
POWER DIVIDER $1,320.00 $1,320.00 See Line Item #2 in attached Broadcasters General Store Quote #: 546580 $1,320.00 N/A
FEEDER CABLES $579.99 $579.99 See Line Item #3 in attached Broadcasters General Store Quote #: 546580 $579.99 N/A
Pattern scatter analysis for side mount (if not included in antenna base cost) $5,000.00 $5,000.00 N/A N/A N/A
Sweep test of transmission line and antenna $5,730.00 $1,860.00 N/A $1,860.00 N/A

Components

Actual Information Description File Name
UHF-Low Power, Side Mount, Other, 4.9kW input, Horizontal

Component Description:
Item Number SCA-4DR4SCH21 in attached invoice and Line Item 1 in attached quote. See discounted total.
Amount:
$2,863.32

Component Description:
Item Deleted
Amount:
N/A
POWER DIVIDER

Component Description:
Item Number SCA-PHD333350 in attached invoice and Line Item 2 in attached quote. See discounted total.
Amount:
$1,320.00
FEEDER CABLES

Component Description:
Item Number SCA-RFF12NMNM6 in attached invoice and Line Item 3 in attached quote. See discounted total.
Amount:
$579.99
Pattern scatter analysis for side mount (if not included in antenna base cost) Information not provided.
Sweep test of transmission line and antenna

Component Description:
Sweep test of transmission line and antenna
Amount:
$1,860.00

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $6,400.00 $6,400.00 N/A $0.00 N/A
Total for all systems $410,080.81 $205,146.32 N/A $19,346.34 N/A
Primary Transmission Line $6,400.00 $6,400.00 $0.00
Sweep $6,400.00 $6,400.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $188,750.00 $25,200.00 N/A $0.00 N/A
Total for all systems $410,080.81 $205,146.32 N/A $19,346.34 N/A
Primary Tower TOWER $188,750.00 $25,200.00 $0.00
Minor tower reinforcement/modifications $10,000.00 $10,000.00 N/A N/A N/A
Tower Rigging Tall Tower (greater than 500') $157,750.00 $5,200.00 See attached Midwest Systems, Inc. Quote N/A N/A
Tower mapping and report for structural engineer $21,000.00 $10,000.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $123,837.50 $89,173.01 N/A $9,005.01 N/A
Total for all systems $410,080.81 $205,146.32 N/A $19,346.34 N/A
Outside Professional Services $123,837.50 $89,173.01 $9,005.01
Additional Field Engineering Service, 5 Days $12,500.00 $12,500.00 N/A N/A N/A
RF Exposure Measurements $12,100.00 $7,500.00 N/A N/A N/A
Comprehensive coverage verification via field study, if needed $52,600.00 $15,000.00 N/A N/A N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $2,235.00 $9,005.01 See attached Invoices $9,005.01 N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $1,577.50 $2,343.00 See attached Invoice #60872958 and refer to yellow highlighted services for the license to cover application. $0.00 N/A
Prepare Form 601 $755.00 $755.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $3,025.00 $3,025.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,052.50 $1,052.50 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $2,102.50 $2,102.50 N/A N/A N/A
Prepare request for Special Temporary Authorization $1,280.00 $1,280.00 N/A N/A N/A
Perform engineering study for displacement application $1,800.00 $1,800.00 N/A N/A N/A
Project management of the transition $21,100.00 $21,100.00 N/A N/A N/A
Prepare/ Review 399 reimbursement form $1,710.00 $1,710.00 N/A N/A N/A
Form 399 assistance or other Program Management costs $10,000.00 $10,000.00 N/A $0.00 N/A

Components

Actual Information Description File Name
Additional Field Engineering Service, 5 Days Information not provided.
RF Exposure Measurements Information not provided.
Comprehensive coverage verification via field study, if needed Information not provided.
Attorney Fees - Prepare and File request for Special Temporary Authorization

Component Description:
See attached Invoice #60867437 for legal services during month of September 2020
Amount:
$1,976.55

Component Description:
See attached Invoice #60872958 for legal services during month of October 2020
Amount:
$6,668.46

Component Description:
See attached Invoice #60863113 for legal services during month of August 2020
Amount:
$360.00
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application

Component Description:
Item Deleted
Amount:
N/A
Prepare Form 601 Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application Information not provided.
Prepare request for Special Temporary Authorization Information not provided.
Perform engineering study for displacement application Information not provided.
Project management of the transition Information not provided.
Prepare/ Review 399 reimbursement form Information not provided.
Form 399 assistance or other Program Management costs

Component Description:
Item Deleted
Amount:
N/A

Component Description:
Item Deleted
Amount:
N/A

Component Description:
Item Deleted
Amount:
N/A

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $25,000.00 $25,000.00 N/A $1,218.02 N/A
Total for all systems $410,080.81 $205,146.32 N/A $19,346.34 N/A
Other Expenses $25,000.00 $25,000.00 $1,218.02
Equipment Storage $5,000.00 $5,000.00 N/A N/A N/A
Equipment Delivery and Handling Charges $5,000.00 $5,000.00 N/A $757.22 N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $5,000.00 $5,000.00 N/A N/A N/A
Sales Tax $10,000.00 $10,000.00 N/A $460.80 N/A

Components

Actual Information Description File Name
Equipment Storage Information not provided.
Equipment Delivery and Handling Charges

Component Description:
See shipping in Invoice Number 0432202
Amount:
$757.22
Disposal Costs (for equipment and other waste, net of any salvage value) Information not provided.
Sales Tax

Component Description:
See sales tax in Invoice Number 0432202
Amount:
$460.80

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $410,080.81 $205,146.32 $19,346.34

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. Yes
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

William T. Godfrey , Jr. .

KGA - Consulting Engineers


08/07/2020

Attachments