Go to the Federal Communications Commission homepage at www.fcc.gov

FCC Form 399: Reimbursement Request

Approved by OMB 3060-1178
Go to the Federal Communications Commission homepage at www.fcc.gov

(REFERENCE COPY - Not for submission) FCC Form 399: Reimbursement Request

Facility ID:
25219
Service:
LPD
Call Sign:
KLDY-LD
Channel:
31 (UHF)
File Number:
0000088570
FRN:
0032881088
Eligibility Status:
Eligible
Date Submitted:
05/12/2020

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

KETCHIKAN TV, LLC

Doing Business As: KETCHIKAN TV, LLC

David Drucker

PO BOX 1471

EVERGREEN, CO 80437

United States

+1 (303) 478-5647 DDRUCKER@WILDBLUE.NET Limited Liability Company

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

The Preparer is same as the reimbursement contact.

 

 

 

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan KLDY-LD displaced from Ch 41 to Ch 31. Transmitter and combiner need replacement.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Ownership Owned
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model ACT-560U
Year 2013
Type Solid State
Solid State Cooling Air Cooled
Solid State Power Capacity .6 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? No
Manufacturer
Model UAXTE-3P-C
Transmitter Type Solid State
Solid State Cooling Air Cooled
Solid State Power capacity .6 kW
Justification for New Transmitter Old transmitter cannot be retuned to Ch 31.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Other Transmitter Costs
Does the transmitter installation require a Transmitter Building Site Survey/Installation? Yes
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Rigid Conduit and Wiring No
Other Electrical Service No
HVAC Service Does the replacement transmitter require HVAC Service? No
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Retune Existing
Antenna Use Primary (Main)
Ownership Owned
Is the existing antenna shared with another station or stations? Yes
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? No
Existing Antenna Manufacturer and Type
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Other
Other Antenna Type K723147 ARRAY
ERP: 5.0 kW
Manufacturer Kathrein
Model K723147 Array
Year 2011

Facility ID's and Call Signs of all stations with whom the antenna is shared.

Facility ID Call Sign
25221 KDMD

Primary Antenna

Back to Top

Adjustment to Existing Antenna

Section Question Response
Sweep Test of Existing Antenna Do you need a sweep test of existing antenna?

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? Yes
Type New
Number of channels supported 2
Frequencies of channels supported RF channel
Frequency N/A

Enter a list of RF channel numbers.

RF Channel Number
33
31

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? No

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? No

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? No
Outside RF consulting Engineering Services Perform engineering study for displacement application No
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority No
Prepare Form 601 No
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application No
Prepare and file Form FCC License to Cover Application No
Prepare request for Special Temporary Authority No
Negotiation of Lease and other Matter for Shared Locations No
Prepare or Review FCC Form 399 for Reimbursement Yes
Form 399 assistance or other program management costs Yes
RF Field Engineering Services Comprehensive coverage verification via field study No
RF exposure measurements No
Additional Field Engineering Service No

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Information not provided.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Permit and Filing Costs FCC Construction Permit Major Change No
FCC Construction Permit Minor Change No
FCC License to Cover Application Yes
FCC Special Temporary Authority Application No
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? No
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? No
Does this relocation require Equipment Storage? No
Point to Point Microwave (STL/ICR) Frequency Coordination for Unidirection System No
Frequency Coordination for Bi-Direction System No
New Point to Point Microwave System No

Other Expenses

Back to Top

Other Expenses Not Listed

Information not provided.

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $38,100.00 $25,353.61 N/A $0.00 N/A
Total for all systems $51,108.50 $36,157.11 N/A $9,968.50 N/A
Primary Transmitter UAXTE-3P-C $38,100.00 $25,353.61 $0.00
UHF - Air Cooled Solid State Transmitter 320 - 700 Watts $28,100.00 $20,353.61 N/A N/A N/A
Transmitter Building Site Survey/Installation $10,000.00 $5,000.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $6,808.50 $6,808.50 N/A $6,808.50 N/A
Total for all systems $51,108.50 $36,157.11 N/A $9,968.50 N/A
Primary Antenna K723147 Array $6,808.50 $6,808.50 $6,808.50
5.0 kW UHF Combiner $6,808.50 $6,808.50 Microwave Filter Company, Inc. Invoice 159780 $6,808.50 N/A

Components

Actual Information Description File Name
5.0 kW UHF Combiner

Component Description:
Ch 31 & Ch 33 combiner
Amount:
$6,808.50

Cost Information

Back to Top

Transmission Line

Information not provided.

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Information not provided.

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $5,865.00 $3,660.00 N/A $3,160.00 N/A
Total for all systems $51,108.50 $36,157.11 N/A $9,968.50 N/A
Outside Professional Services $5,865.00 $3,660.00 $3,160.00
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $2,102.50 $450.00 N/A $450.00 N/A
Prepare/ Review 399 reimbursement form $1,710.00 $1,710.00 See BWS Estimate KLDY.pdf $1,710.00 N/A
Form 399 assistance or other Program Management costs $1,000.00 $1,000.00 See BWS Estimate KLDY.pdf $1,000.00 N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,052.50 $500.00 N/A N/A N/A

Components

Actual Information Description File Name
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application

Component Description:
displacement to Ch 31
Amount:
$450.00
Prepare/ Review 399 reimbursement form

Component Description:
Cost for turnkey management of 399 reimbursement filings.
Amount:
$1,710.00
Form 399 assistance or other Program Management costs

Component Description:
Cost for turnkey management of 399 Eligibility and 1876 filings
Amount:
$1,000.00
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $335.00 $335.00 N/A $0.00 N/A
Total for all systems $51,108.50 $36,157.11 N/A $9,968.50 N/A
Other Expenses $335.00 $335.00 $0.00
FCC Filing Fees - Form 2100 license to cover application $335.00 $335.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $51,108.50 $36,157.11 $9,968.50

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. No
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Attachments

Back to Top