FCC Form 399: Reimbursement Request

Approved by OMB 3060-1178
Go to the Federal Communications Commission homepage at www.fcc.gov

(REFERENCE COPY - Not for submission) FCC Form 399: Reimbursement Request

Facility ID:
48813
Service:
DTV
Call Sign:
WUVG-DT
Channel:
18 (UHF)
File Number:
0000028535
FRN:
0005414891
Date Submitted:
04/23/2020

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

UNIVISION ATLANTA LLC

Doing Business As: UNIVISION ATLANTA LLC

Christopher G. Wood

5999 CENTER DRIVE

LOS ANGELES, CA 90045

United States

+1 (310) 348-3600 CWOOD@UNIVISION.NET Limited Liability Company

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

Theodore Stoner

VP Distribution Technology Strategy

Univision Communications Inc.

Theodore Stoner

9405 NW 41st Street

Miami, FL 33178

United States

+1 (513) 608-0308 tstoner@univision.net

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. Yes
Briefly describe transition plan Establish temporary transmitting facilities at ATC Chester Avenue site, replace all transmitting equipment at Briarcliff, and remove/repurpose Chester Avenue site equipment following cutover. See attached Implementation Plan.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model CD3260P2
Year 2003
Type Inductive Output Tube
IOT Power Type Two
Power Capacity 50.8 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model THU9-48 Evo
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 73.5 kW
Justification for New Transmitter Current transmitter solid-state intermediate power amplifiers are banded, limited to operation at channel 40 and higher. Transmitter is obsolete and parts and technical support to reband amplifiers are unavailable

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring Yes
Size 4 inches
Length 200.0 feet
Other Electrical Service Yes
Description Remove previous electrical equipment; provide and install gear and equipment to connect new transmitter. This includes breakers, panels, connectors, and other electrical equipment required for the new transmitter
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Interim Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Interim
Description of Use N/A
Change Type Purchase
Manufacturer
Model THU9-16evo
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 25.5 kW
Justification for New Transmitter WUVG-DT is requesting an interim transmitter to be utilized at a temporary transmitting facility at ATC Chester Avenue site during transition, while the current tower is modified.

Interim Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) Yes
Switchgear (industrial 800 amp) Yes
Transformer (480V) Yes
Power 150 kVA
Rigid Conduit and Wiring Yes
Size 2 inches
Length 200.0 feet
Other Electrical Service No
Description N/A
HVAC Service Does the replacement transmitter require HVAC Service? Yes
Type Cooling Only
Size 10 tons
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? Yes
Size 1500.0 square feet
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A
Inside RF System Is an additional interior RF system required to support this interim transmitter? Yes

Interim Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Unistrut Grid

Unistrut Grid in antenna combiner room ceiling

Electrical Sub-Panels

Provide new sub panels at approximately 200 amps each, to provide proper voltage and current for each additional transmitter, house power, HVAC, and ancillary equipment.

Combiner Room Generator

Temporary generator for interim operations in combiner room

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Lease New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Leased
Owner American Tower Corporation
Site N/A
Is the existing antenna shared with another station or stations? Yes
Is the existing antenna directional? No
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? Yes
Existing Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Bottom
Polarization Horizontal
Type Broadband Panel
Number of Stations Supported 3
Number of Panels 70
Design power capacity in use 50.0 %
Lower Limit 488.00 MHz
Upper Limit 680.00 MHz
Other Antenna Type N/A
ERP: 1000.0 kW
Manufacturer
Model TUD-05-14/70U-2-B
Year 2003

Facility ID's and Call Signs of all stations with whom the antenna is shared.

Facility ID Call Sign
64033 WPCH-TV
68058 WHSG-TV

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Lease New
Is this a request for upgraded equipment? Yes
Ownership Leased
Owner American Tower Corporation
Is antenna shared? Yes
Is antenna directional? No
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Types Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Circular
Type Broadband Panel
Number of Stations Supported 4
Number of Panels/Bays 56
Lower Limit 470.00 MHz
Upper Limit 608.00 MHz
Design power capacity in use 70.0 %
Other Antenna Type N/A
ERP: 1000.0 kW
Manufacturer
Model PEP70E
Year 2018
Justification for New Antenna American Tower's disconnection of existing broadband panel antenna and substitution of new system.

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? Yes
Type New
Number of channels supported 4
Frequencies of channels supported RF channel
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? Yes
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? Broadband
Feed Line Size 8 3/16 inches inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna?
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Enter a list of RF channel numbers.

RF Channel Number
36
18
22
31

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Combiner Installation

Removal of existing combiner and installation of new combiner for new broadband antenna

Interim Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Interim
Description of Use N/A
Change Type Rent Temporary
Ownership Leased
Owner American Tower Corporation
Is antenna shared? Yes
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Elliptical
Type Broadband Panel
Number of Stations Supported 3
Number of Panels/Bays 48
Lower Limit 470.00 MHz
Upper Limit 698.00 MHz
Design power capacity in use 80.0 %
Other Antenna Type N/A
ERP: 850.0 kW
Manufacturer
Model PEPL48D-C170-2-6
Year 2018
Justification for New Antenna Maintain continuity of service during new antenna installation and transmission line repurposing at Briarcliff main site, to the phase cutover date.

Interim Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? Yes
Type New
Number of channels supported 4
Frequencies of channels supported Upper and lower frequency
Frequency 470.0 MHz - 698.0 MHz
Do you need a combiner output splitter/switcher for dual feed lines? No
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? B
Feed Line Size 8 3/16 inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for an antenna? No
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Interim Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Combiner Installation

ATC installation of combiner system for 3 stations.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Utilize Existing
Use Primary (Main)
Description of Use N/A
Ownership Leased
Owner American Tower Corporation
Site N/A
Is the existing transmission line shared with another station or stations? Yes
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer Dielectric
Type Rigid
Diameter 7 3/16 inches
Other Diameter N/A
Segment Length Broadband
Other Segment Length N/A
Number of parallel runs 2
Length 1158 feet per run

Facility ID's and Call Signs of all stations with whom the transmission line is shared.

Facility ID Call Sign
68058 WHSG-TV
64033 WPCH-TV

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Existing Line Relocation

ATC relocation and refurbishment of existing dual 8-3/16" lines from existing broadband antenna to new broadband antenna

Interim Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Interim
Description of Use N/A
Change Type Lease New
Type Rigid
Diameter 8 3/16 inches
Segment Length Broadband
Other Segment Length
Number of parallel runs 1
Length 1151 feet per run
Justification for New Transmission Line This line is for interim use while candelabra and master broadband antenna on primary tower are modified and constructed

Interim Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Nitrogen Generator

Required for new interim transmission line pressurization

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Description of Use N/A
Ownership Leased
Is this tower consider Complex? Candelabra
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users No
Is tower documented for structural analysis? Unknown
Is tower compliant with Rev G? Unknown
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1223132
Coordinates (NAD83) Latitude (NAD83) 33° 48' 26.4" N-
Longitude (NAD83) 084° 20' 21.5" W-
Overall Structure Height 1182.07 feet
Support Structure Height 1056.09 feet
Ground Elevation Above Mean Sea Level (AMSL) 867.12 feet
Structure Type GTOWER - Guyed Structure Used for Communication Purposes
Tower Owner American Tower, LLC
Date Constructed 03/27/2002

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
22819 WATL DTV
168812 WANN-CD DTV
72120 WGCL-TV DTV
73345 WWWQ FM
64033 WPCH-TV DTV
11275 WWPW FM
68058 WHSG-TV DTV
13805 WZGC FM
54585 WRFG FM
11675 WCLK FM
29735 WUBL FM
73161 WKHX-FM FM
48813 WUVG-DT DTV
15897 WGNE-FM FM
6900 WUPA DTV

Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for tower with candelabra
Tower Reinforcements Please select whether tower reinforcements are needed: Serious Reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Candelabra
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Information not provided.

Interim Tower

Back to Top

Tower Construction Costs

Section Question Response
Construct New Tower Use Interim
Description of Use N/A
Height 1089.00 feet
Justification for New Tower Required construction on the top of American Tower primary WUVG Briarcliff site requires interim operation from American Tower Chester Road Site. Existing Chester Road tower will be modified for interim operation

Interim Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Candelabra
Helicopter Services Required Are helicopter services required? No

Interim Tower

Back to Top

Other Tower Expenses Not Listed

Name Description

Minor Tower Reinforcement

It is expected that the additional loads imposed on the tower by the new appurtenances required for the repack project will cause the tower to fail. The structural failure is expected to be in the major category and the replacement o structural members.

Structural engineering tower load study for a documented tower with candelabra

Structural tower mapping to ensure the proper structural information is relayed to engineering for the rigourous structural assessment for the proposed repack equipment.

FM Move Rigging

Relocation cost of 2 FM to make room; includes quoted cost, materials, labor, parts, pattern studies

Construction Project Management

Project management fee for preconstruction services (including initial antenna placement and RF compatibility review zoning and permitting requirements review leasing application services) to support the transition of one broadcasters

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 800
Explanation Univision stations are only staffed for daily station operations and minor equipment changes, major projects are contracted out externally. The large volume of work associated with repack schedule requires using external project management resources.
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
NEPA Section 106 environmental review No
Environmental Assessment No
ASR Modification No
FAA Consultation (including preparation of FAA Form 7460) No
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study No
RF exposure measurements Yes
Additional Field Engineering Service Yes
Number of Days 4
Justification Testing of combiner to ensure all frequencies are tuned for optimal patterns, for both primary site BBA and interim BBA.

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Information not provided.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning No
Non-zoning permits Yes
BLM or NFS Coordination No
FCC Construction Permit Minor Change No
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? Yes
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? No
Does this relocation require MVPD Notification of a Channel Change? No

Other Expenses

Back to Top

Other Expenses Not Listed

Name Description

RF System Test

ATC Capital contribution - RF System Test

Site Permit Drawing Package

ATC cost for drawing package to support local building/facilities construction permit acquistion.

Site Security

ATC Capital contribution - Site Security

Station Coordination Meeting

ATC Capital contribution - Site coordination meeting

Tower Permit Drawing Package

ATC cost for drawing package to support local tower construction permit acquisition.

Demolition of old HVAC and electrical to make room for combiner

Demolition of old hvac and electrical to make room for combiner

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $3,358,297.53 $2,663,130.54 N/A $2,172,604.00 N/A
Total for all systems $10,721,785.66 $4,071,326.81 N/A $2,759,002.34 N/A
Interim Transmitter THU9-16evo $1,252,837.53 $865,642.73 $714,971.79
Combiner Room Generator $14,864.00 $14,864.00 Please see WUVG-DT American Towers 460224988 N/A N/A
Electrical Sub-Panels $6,000.00 $6,000.00 Please see WUVG-DT American Towers 460224988 N/A N/A
Unistrut Grid $3,466.66 $3,466.66 Please see WUVG-DT American Towers 460224988 N/A N/A
UHF inside RF system including switching $147,500.00 $60,000.00 N/A $33,173.25 N/A
Other -- Building Addition Size: 1500.0 $11,756.87 $11,756.87 Building addition between 600 - 1500 sq feet Please see WUVG-DT American Towers 460224988 N/A N/A
10 Ton system $38,900.00 $27,353.00 Two 10 ton HVAC units Split Units required to maintain operational temperatures for the new repack transmitters. Please see WUVG-DT American Towers 460224988 N/A N/A
2" Rigid Conduit and Wiring (Cost per foot) $5,200.00 $6,666.66 see Estimated Cost Justification WUVG-DT-180-Interim Transmitter - 2in Rigid Conduit and Wiring v0 $0.00 N/A
Transformer 3 phase/480v - 150 KVA $25,550.00 $24,300.00 N/A $13,900.00 N/A
Switchgear - industrial 800 amp $38,200.00 $36,300.00 N/A N/A N/A
Service entrance 3 phase/800 amp/208 volt $14,400.00 $7,037.00 Justification of cost will be, “Please see WUVG-DT American Towers 460224988 N/A N/A
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW $947,000.00 $667,898.54 Please see the attached invoice from Rohde & Schwarz # 9500090892 and the attached quote from Rohde & Schwarz #802-051617.1; Justifying Invoice-WUVG RE Services WUVG-1 $667,898.54 N/A
Primary Transmitter THU9-48 Evo $2,105,460.00 $1,797,487.81 $1,457,632.21
Other Electrical Service: Remove previous electrical equipment; provide and install gear and equipment to connect new transmitter. This includes breakers, panels, connectors, and other electrical equipment required for the new transmitter $86,260.00 $86,260.00 See RE Services Group Proposal dated 04/18/19 $86,260.00 N/A
UHF - Liquid Cooled Solid State Transmitter 68.5 - 75 kW $1,999,000.00 $1,692,027.81 Estimated Cost Justification WUVG-DT-110-1st Primary Transmitter - UHF Two IOT Transmitter v0 $1,371,372.21 N/A
4" Rigid Conduit and Wiring (Cost per foot) $20,200.00 $19,200.00 N/A N/A N/A

Components

Actual Information Description File Name
Combiner Room Generator Information not provided.
Electrical Sub-Panels Information not provided.
Unistrut Grid Information not provided.
UHF inside RF system including switching

Component Description:
Equipment Rental from 04/23/19 thru 05/21/19
Amount:
$4,116.42

Component Description:
Equipment rental
Amount:
$4,116.42

Component Description:
Equipment rental
Amount:
$4,116.42

Component Description:
Equipment Rental
Amount:
$142.11

Component Description:
EQUIPMENT RENTAL
Amount:
$4,116.42

Component Description:
EQUIPMENT RENTAL FROM 03/26/19 THRU 04/23/19
Amount:
$4,627.62

Component Description:
Equipment Rental
Amount:
$4,116.42

Component Description:
Equipment Rental
Amount:
$4,116.42

Component Description:
DTV Interface Transport Stream Converter ASI/310M and IP Interface
Amount:
$3,705.00
Other -- Building Addition Size: 1500.0 Information not provided.
10 Ton system Information not provided.
2" Rigid Conduit and Wiring (Cost per foot) Information not provided.
Transformer 3 phase/480v - 150 KVA

Component Description:
generator/ATS installation
Amount:
$13,900.00
Switchgear - industrial 800 amp Information not provided.
Service entrance 3 phase/800 amp/208 volt Information not provided.
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW

Component Description:
DP 35% Final Milestone Payment PO# Line 1
Amount:
$257,727.86

Component Description:
THU9-16EVO 25 kW ATSC-1 UHF television transmitter, Installation services, Reject loads and interconnecting components, Mask filter, switch, & interconnecting coax subsystem, etc.
Amount:
$167,448.00

Component Description:
THU9-16EVO 25 kW ATSC-1 UHF television transmitter, Reject loads and interconnecting components, Mask filter, switch, & interconnecting coax subsystem, etc.
Amount:
$212,742.68

Component Description:
electrical installation
Amount:
$29,980.00
Other Electrical Service: Remove previous electrical equipment; provide and install gear and equipment to connect new transmitter. This includes breakers, panels, connectors, and other electrical equipment required for the new transmitter

Component Description:
electrical installation at Briarcliff site
Amount:
$86,260.00
UHF - Liquid Cooled Solid State Transmitter 68.5 - 75 kW

Component Description:
BELDEN 2pr. AUDIO CABLE/ON REEL
Amount:
$185.05

Component Description:
OTHER Freight And Shipping
Amount:
$1,267.18

Component Description:
WUVG-DT THU9-48evo Dual Drive
Amount:
$505,024.19

Component Description:
WUVG-DT THU9-48evo Dual Drive
Amount:
$411,143.04

Component Description:
QT# 210206.0 Elbow PO LI#11
Amount:
$2,927.23

Component Description:
GA Sales Tax - Invoice 542024
Amount:
$112.78

Component Description:
This invoice has been moved to the correct category
Amount:
N/A

Component Description:
Forecast deposit: $1,000 per transmitter
Amount:
$447,367.21

Component Description:
CABLE 3643.3106.02
Amount:
$3,321.00

Component Description:
This invoice has been moved to another component
Amount:
N/A

Component Description:
TYTON 15"/50LB. BLK. CABLE TIES/100
Amount:
$24.53
4" Rigid Conduit and Wiring (Cost per foot) Information not provided.

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,701,438.75 $509,066.20 N/A $215,480.00 N/A
Total for all systems $10,721,785.66 $4,071,326.81 N/A $2,759,002.34 N/A
Interim Antenna PEPL48D-C170-2-6 $312,975.00 $176,795.00 $144,146.25
New combiner, cost per channel (without antenna) $84,200.00 $22,500.00 N/A $16,875.00 N/A
Combiner Installation $5,800.00 $5,800.00 see Estimated Cost Justification WUVG-DT-280-Interim Antenna - Combiner Installation v0 $3,750.00 N/A
Interim antenna rental and installation - Cost will depend on antenna size and height and/or complexity of tower. $115,500.00 $60,600.00 per American Tower Inv 460203568 $57,600.00 N/A
Elbow complex, broadband, at antenna input, per 8 3/16. feedline (if needed) $18,950.00 $3,600.00 N/A $2,700.00 N/A
UHF - High Power Top Mount Three Station broadband panel antenna elliptically or circularly polarized $81,795.00 $81,795.00 Pro-rata share of ATC-provided antenna, per attached ATC Chester Avenue cost estimate spreadsheet, line 54. $61,346.25 N/A
Sweep test of existing antenna $6,730.00 $2,500.00 N/A $1,875.00 N/A
Primary Antenna PEP70E $1,388,463.75 $332,271.20 $71,333.75
UHF - High Power Top Mount (200-1000 kW), Four Station broadband panel antenna, elliptically or circularly polarized $1,090,000.00 $180,379.45 Please see Estimated Cost Justification WUVG-DT-210-Primary Antenna - UHF High Power Top Mount 5 Station Broadband Panel, E-POL v0, less amount reimbursed in superseded category N/A N/A
UHF - High Power Top Mount Five Station broadband panel antenna elliptically or circularly polarized $44,583.75 $44,583.75 ***System Notice: Estimate adjusted and locked because line has been superseded.***see Estimated Cost Justification WUVG-DT-210-Primary Antenna - UHF High Power Top Mount 5 Station Broadband Panel, E-POL v0 $44,583.75 N/A
Combiner Installation $18,000.00 $18,000.00 Pro-rata share, per attached ATC Briarcliff cost estimate spreadsheet, line 110. $4,500.00 N/A
Elbow complex, broadband, at antenna input, per 8 3/16. feedline (if needed) $18,950.00 $18,308.00 see Estimated Cost Justification WUVG-DT-210-Primary Antenna - Elbow Complex, 8 3_16_, Broadband v0 $4,500.00 N/A
Combiner output splitting/switching for dual feed lines, if applicable $126,000.00 $0.00 N/A N/A N/A
Sweep test of existing antenna $6,730.00 $5,000.00 N/A $1,250.00 N/A
New combiner, cost per channel (without antenna) $84,200.00 $66,000.00 N/A $16,500.00 N/A

Components

Actual Information Description File Name
New combiner, cost per channel (without antenna)

Component Description:
WUVG-DT Interim Antenna- New Combiner
Amount:
$5,625.00

Component Description:
WUVG-DT Interim Antenna- New Combiner
Amount:
$11,250.00
Combiner Installation

Component Description:
WUVG-DT Interim Antenna- Combiner Installation
Amount:
$2,500.00

Component Description:
WUVG-DT Interim Antenna- Combiner Installation
Amount:
$1,250.00
Interim antenna rental and installation - Cost will depend on antenna size and height and/or complexity of tower.

Component Description:
BROADCAST RENT
Amount:
$57,600.00
Elbow complex, broadband, at antenna input, per 8 3/16. feedline (if needed)

Component Description:
WUVG-DT Interim Antenna- Elbow Complex, 8 3/16in
Amount:
$1,800.00

Component Description:
WUVG-DT Interim Antenna- Elbow Complex, 8 3-16in
Amount:
$900.00
UHF - High Power Top Mount Three Station broadband panel antenna elliptically or circularly polarized

Component Description:
CAPITAL CONTRIBUTION
Amount:
$40,897.50

Component Description:
Capital Contribution, Milestone, Broadcast Repack
Amount:
$20,448.75
Sweep test of existing antenna

Component Description:
WUVG-DT Interim Antenna- Sweep Test
Amount:
$1,250.00

Component Description:
WUVG-DT Interim Antenna- Sweep Test
Amount:
$625.00
UHF - High Power Top Mount (200-1000 kW), Four Station broadband panel antenna, elliptically or circularly polarized Information not provided.
UHF - High Power Top Mount Five Station broadband panel antenna elliptically or circularly polarized

Component Description:
Antenna
Amount:
$44,583.75
Combiner Installation

Component Description:
WUVG Primary Antenna- Combiner Installation
Amount:
$4,500.00
Elbow complex, broadband, at antenna input, per 8 3/16. feedline (if needed)

Component Description:
WUVG Primary AntennaElbow Complex, 8 3/16
Amount:
$4,500.00
Combiner output splitting/switching for dual feed lines, if applicable Information not provided.
Sweep test of existing antenna

Component Description:
WUVG Primary Antenna- Sweep Test
Amount:
$1,250.00
New combiner, cost per channel (without antenna)

Component Description:
WUVG Primary Antenna- New Combiner
Amount:
$16,500.00

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $533,091.05 $119,963.05 N/A $75,796.88 N/A
Total for all systems $10,721,785.66 $4,071,326.81 N/A $2,759,002.34 N/A
Interim Transmission Line $461,257.05 $48,129.05 $37,744.31
Nitrogen Generator $2,008.05 $2,008.05 Please see WUVG-DT American Towers 460224988 N/A N/A
Rigid Transmission Line - copper, 8 3/16" broadband $459,249.00 $46,121.00 N/A $37,744.31 N/A
Primary Transmission Line $71,834.00 $71,834.00 $38,052.57
Existing Line Relocation $71,834.00 $71,834.00 Pro-rata share pass-thru, per attached ATC Briarcliff cost estimate spreadsheet line 127. $38,052.57 N/A

Components

Actual Information Description File Name
Nitrogen Generator Information not provided.
Rigid Transmission Line - copper, 8 3/16" broadband

Component Description:
WUVG-DT Interim Transmission Line- 8 3_16in, Rigid
Amount:
$23,060.50

Component Description:
WUVG-DT Interim Transmission Line- 8 3-16in, Rigid
Amount:
$11,530.25

Component Description:
ELBOW 4-50 TUNABLE 6.0 X 20.5 CH14-37
Amount:
$3,153.56
Existing Line Relocation

Component Description:
T/L TUNER SECTION 8-75 CH 14-37 18.00
Amount:
$4,374.20

Component Description:
Other Freight and Shipping
Amount:
$2,470.01

Component Description:
GA Sales Tax - Invoice 559033
Amount:
$389.30

Component Description:
Transmission Line
Amount:
$11,704.50

Component Description:
GA Sales Tax - Invoice 562038
Amount:
$219.83

Component Description:
WUVG Primary Transmission Line- 8 3/16 Rigid
Amount:
$17,958.37

Component Description:
GA Sales Tax - Invoice 541006
Amount:
$936.36

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $4,825,840.32 $462,019.01 N/A $125,397.11 N/A
Total for all systems $10,721,785.66 $4,071,326.81 N/A $2,759,002.34 N/A
Primary Tower GTOWER $1,493,000.00 $369,248.69 $77,070.86
Serious tower reinforcement/modifications $1,052,000.00 $157,500.00 N/A $39,375.00 N/A
Structural engineering tower load study for a documented tower with candelabra $20,000.00 $14,784.00 N/A $3,695.86 N/A
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $196,964.69 see Estimated Cost Justification WUVG-DT-410-Existing Primary Tower - Complex Tower - Tower Rigging and Equipment v0 $34,000.00 N/A
Interim Tower $3,332,840.32 $92,770.32 $48,326.25
New tower between 1000' and 1500' without elevator, presumptive soil conditions $2,864,070.00 $0.00 Existing tower will support temporary antenna. N/A N/A
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $45,000.00 N/A $33,750.00 N/A
Structural engineering tower load study for a documented tower with candelabra $4,435.00 $4,435.00 $2,480 tower mapping plus $1,955 structural analysis, per attached ATC Chester Avenue cost estimate, lines 148 & 150. $3,326.25 N/A
Minor Tower Reinforcement $15,000.00 $15,000.00 Pro-rata share, per attached ATC Chester Avenue cost estimate, line 152 $11,250.00 N/A
Construction Project Management $7,333.32 $7,333.32 Please see WUVG-DT American Towers 460224988 N/A N/A
FM Move Rigging $21,002.00 $21,002.00 Please see WUVG-DT American Towers 460224988 N/A N/A

Components

Actual Information Description File Name
Serious tower reinforcement/modifications

Component Description:
WUVG Existing Primary Tower- Serious Tower Reinforcement/ Modifications
Amount:
$39,375.00
Structural engineering tower load study for a documented tower with candelabra

Component Description:
WUVG Existing Primary Tower- Structural Engineering Load Study
Amount:
$3,695.86
Complex Tower (includes, for example, those with candelabras and/or stacked antennas)

Component Description:
WUVG Existing Primary Tower- Complex Tower- Tower Rigging
Amount:
$34,000.00
New tower between 1000' and 1500' without elevator, presumptive soil conditions Information not provided.
Complex Tower (includes, for example, those with candelabras and/or stacked antennas)

Component Description:
WUVG-DT Interim Tower- Complex Tower- Tower Rigging
Amount:
$22,500.00

Component Description:
WUVG-DT Interim Tower- Complex Tower- Tower Rigging
Amount:
$11,250.00
Structural engineering tower load study for a documented tower with candelabra

Component Description:
WUVG-DT Interim Tower- Structural Engineering Load Study
Amount:
$2,217.50

Component Description:
WUVG-DT Interim Tower- Structural Engineering Load Study
Amount:
$1,108.75
Minor Tower Reinforcement

Component Description:
8. WUVG-DT Interim Tower- Minor Tower Reinforcement $7,500.00.
Amount:
$7,500.00

Component Description:
WUVG-DT Interim Tower- Minor Tower Reinforcement
Amount:
$3,750.00
Construction Project Management Information not provided.
FM Move Rigging Information not provided.

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $200,265.00 $217,860.00 N/A $127,539.48 N/A
Total for all systems $10,721,785.66 $4,071,326.81 N/A $2,759,002.34 N/A
Outside Professional Services $200,265.00 $217,860.00 $127,539.48
Project management of the transition $126,400.00 $148,960.00 Pre-determined amount for Univision project management, plus $28,960 pro-rata share of ATC project management fees, per lines 170 and 174 of attached ATC Briarcliff and Chester Avenue cost estimate spreadsheets. $108,914.48 N/A
Additional Field Engineering Service, 4 Days $10,000.00 $10,000.00 Pro-rata share of ATC antenna/line/combiner system tuning and testing, per attached ATC Briarcliff and Chester Avenue cost estimate spreadsheets, line 194, $5K each. N/A N/A
RF Exposure Measurements $21,050.00 $5,000.00 per attached WUVG-DT Briarcliff T2 cost estimate line 190 $1,250.00 N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $3,680.00 $3,500.00 N/A N/A N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $4,210.00 $4,000.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $2,250.00 N/A N/A N/A
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application $4,210.00 $2,000.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $5,000.00 N/A N/A N/A
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application $1,580.00 $1,500.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A N/A N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $8,500.00 American Tower coordination fees, per attached ATC Briarcliff and Chester Avenue cost estimate spreadsheets, lines 175 & 192. $2,500.00 N/A
Prepare and or review reimbursement form $2,630.00 $2,500.00 N/A N/A N/A
Prepare request for Special Temporary Authorization $2,050.00 $1,500.00 N/A N/A N/A
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application $2,105.00 $2,000.00 N/A $937.50 N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $3,250.00 du Treil, Lundin & Rackley, Inc. Invoice #240771 $3,250.00 N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $16,400.00 see Estimated Cost Justification WUVG-DT-530-RF Eng - Engineering Study for New Channel Assignment v1 $10,687.50 invoices

Components

Actual Information Description File Name
Project management of the transition

Component Description:
Project Management and Repack Implementation Engineering Services
Amount:
$75.00

Component Description:
Project management services
Amount:
$187.50

Component Description:
Project management services
Amount:
$276.00

Component Description:
Project Management
Amount:
$1,483.60

Component Description:
Project Management Services
Amount:
$462.50

Component Description:
Project Management
Amount:
$7,162.70

Component Description:
Project management Services
Amount:
$806.25

Component Description:
Project management Services
Amount:
$497.50

Component Description:
Project Management Services
Amount:
$298.75

Component Description:
Project management Services
Amount:
$306.25

Component Description:
Project management Services
Amount:
$240.50

Component Description:
Project management Services
Amount:
$246.35

Component Description:
Project Management
Amount:
$4,837.50

Component Description:
Project Management
Amount:
$2,729.60

Component Description:
Project management Services
Amount:
$525.00

Component Description:
Project Management Services
Amount:
$521.25

Component Description:
Project Management
Amount:
$5,975.90

Component Description:
Project Management Services including: coordinate tower rigging projects with local engineers
Amount:
$123.00

Component Description:
Project management Services
Amount:
$512.20

Component Description:
Project management Services, including: invoice processing
Amount:
$672.10

Component Description:
Project Management
Amount:
$112.50

Component Description:
Project management Services
Amount:
$479.70

Component Description:
Project Management Services including: coordinate tower rigging projects
Amount:
$114.00

Component Description:
Project Management Services including: coordinate tower rigging projects with local engineers
Amount:
$252.00

Component Description:
Generator rental cost analysis
Amount:
$225.00

Component Description:
Project Management Services including: coordinate tower rigging projects with local engineers
Amount:
$132.00

Component Description:
Project Management
Amount:
$2,833.10

Component Description:
Project Management Services
Amount:
$42.00

Component Description:
Project management Services
Amount:
$291.25

Component Description:
WUVG-DT Project Management
Amount:
$4,740.00

Component Description:
Project Management Services
Amount:
$575.84

Component Description:
Project Management Services
Amount:
$710.36

Component Description:
Project Management Services including: coordinate tower rigging projects with local engineers
Amount:
$202.50

Component Description:
Project Management
Amount:
$4,217.05

Component Description:
Project management Services
Amount:
$629.85

Component Description:
Generator cost splitting / invoicing
Amount:
$412.50

Component Description:
Project Management
Amount:
$4,217.95

Component Description:
Project management Services
Amount:
$402.35

Component Description:
Project management Services
Amount:
$338.75

Component Description:
Project management Services
Amount:
$1,030.00

Component Description:
Project Management
Amount:
$112.50

Component Description:
Project management Services
Amount:
$718.75

Component Description:
Project Management Services including: coordinate tower rigging projects
Amount:
$171.00

Component Description:
Project management Services
Amount:
$1,011.25

Component Description:
Project Management Services including: coordinate tower rigging projects
Amount:
$504.00

Component Description:
Project Management
Amount:
$6,650.90

Component Description:
Project management Services
Amount:
$456.25

Component Description:
WUVG Project Management
Amount:
$4,870.00

Component Description:
Project Management Services
Amount:
$428.34

Component Description:
Project Management Services
Amount:
$395.20

Component Description:
Project management services
Amount:
$397.50

Component Description:
Project management Services
Amount:
$303.55

Component Description:
Project Management Services
Amount:
$628.94

Component Description:
Project management Services
Amount:
$624.65

Component Description:
K. Lahm - FCC DRT record identification
Amount:
$37.50

Component Description:
Project Management Services
Amount:
$280.00

Component Description:
Project management Services
Amount:
$401.05

Component Description:
Project Management
Amount:
$4,693.75

Component Description:
Project management Services
Amount:
$399.75

Component Description:
Project Management Services
Amount:
$590.00

Component Description:
Project Management
Amount:
$33.00

Component Description:
Emergency Gen proposal review
Amount:
$75.00

Component Description:
Project Management
Amount:
$7,921.65

Component Description:
Project Management
Amount:
$2,833.10

Component Description:
Place of the Sun, LLC
Amount:
$246.35

Component Description:
Project management Services
Amount:
$624.65

Component Description:
Project Management Services including: coordinate tower rigging projects
Amount:
$129.00

Component Description:
Project management services
Amount:
$225.00

Component Description:
Project Management
Amount:
$2,754.45

Component Description:
WUVG-DT Project Management
Amount:
$2,370.00

Component Description:
Project management Services
Amount:
$1,247.50

Component Description:
Project management Services
Amount:
$399.75

Component Description:
WUVG-DT-510-Project Management
Amount:
$150.00

Component Description:
Project Management
Amount:
$2,055.75

Component Description:
Project Management
Amount:
$3,738.80

Component Description:
Information Technology Consulting Services
Amount:
$200.00

Component Description:
Project management Services
Amount:
$863.75

Component Description:
Project management Services
Amount:
$402.35

Component Description:
Project management Services
Amount:
$232.50

Component Description:
Project Management Services including: coordinate tower rigging projects with local engineers
Amount:
$153.00

Component Description:
Project Management
Amount:
$5,046.80

Component Description:
Project Management
Amount:
$1,829.40

Component Description:
Project management Services
Amount:
$757.50

Component Description:
Project management services
Amount:
$58.50

Component Description:
Project Management
Amount:
$4,390.75

Component Description:
Project Management
Amount:
$1,237.30

Component Description:
Project management services
Amount:
$109.50

Component Description:
Invoice revisions to meet FCC submittal requirements
Amount:
$45.00

Component Description:
Project Management
Amount:
$3,530.30

Component Description:
Project management Services
Amount:
$636.25

Component Description:
Project management Services
Amount:
$629.85

Component Description:
Project Management Services including: coordinate tower rigging projects with local engineers
Amount:
$244.50
Additional Field Engineering Service, 4 Days Information not provided.
RF Exposure Measurements

Component Description:
WUVG Field Engineering Service- RF Exposure Measurements
Amount:
$1,250.00
Attorney Fees - Prepare and File request for Special Temporary Authorization Information not provided.
Attorney Fees - Negotiation of lease and other matters for shared locations Information not provided.
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application Information not provided.
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
Address transition timing and coordination issues w/ other stations and wireless

Component Description:
WUVG-DT Transition Timing and Coordination
Amount:
$1,250.00

Component Description:
WUVG Transition Timing and Coordination
Amount:
$625.00

Component Description:
WUVG-DT Transition Timing and Coordination
Amount:
$625.00
Prepare and or review reimbursement form Information not provided.
Prepare request for Special Temporary Authorization Information not provided.
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application

Component Description:
K. Lahm - Antenna change CP modification preparation
Amount:
$937.50
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application

Component Description:
WUVG-DT-530-RF Eng - Construction Permit Application (Main)
Amount:
$3,250.00
Perform engineering study for new channel assignment and antenna development

Component Description:
Professional Services
Amount:
$5,000.00

Component Description:
WUVG-DT RF Eng- Engineering Study for New Channel Assignment
Amount:
$1,250.00

Component Description:
WUVG-DT RF Eng- Engineering Study for New Channel Assignment
Amount:
$2,500.00

Component Description:
WUVG RF Eng- Engineering Study for New Channel Assignment
Amount:
$1,250.00

Component Description:
"Engineering study work for new channel assignment and antenna development (Custom Antenna). Preparation of the engineering portion of FCC Form 2100"
Amount:
$500.00

Component Description:
WUVG-DT-530-RF Eng - Engineering Study for New Channel Assignment
Amount:
$187.50

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $102,853.01 $99,288.01 N/A $42,184.87 N/A
Total for all systems $10,721,785.66 $4,071,326.81 N/A $2,759,002.34 N/A
Other Expenses $102,853.01 $99,288.01 $42,184.87
Demolition of old HVAC and electrical to make room for combiner $8,200.00 $8,200.00 Please see WUVG-DT American Tower Customer Project Cost Estimation Atlanta Briarcliff T2 282650 N/A N/A
RF System Test $10,000.00 $10,000.00 Please see the attached invoices from ATC #460200910, 460197967 $5,000.00 N/A
Equipment Storage $1,420.00 $1,420.00 Please see WUVG-DT American Tower Customer Project Cost Estimation Atlanta Briarcliff T2 282650 N/A N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $325.00 N/A N/A N/A
FCC Filing Fees - Special Temporary Authorization request $195.00 $190.00 N/A N/A N/A
Non-zoning permits $1,500.00 $1,500.00 Pro-rata share, per attached ATC cost estimate spreadsheets for Briarcliff and Chester Avenue sites, line 202, $750 each. $750.00 N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $33,840.00 $33,840.00 $2,667 pro-rata share of ATC cost, per attached ATC Briarcliff cost estimate spreadsheet, line 206, plus $31,172 for existing transmitter removal, see attached quote for removal of physically identical transmitter at sister station WAMI-DT. $15,496.53 N/A
Equipment Delivery and Handling Charges $11,713.01 $11,713.01 see Estimated Cost Justification WUVG-DT-610-Equipment Delivery and Handling v0 $5,463.34 N/A
Tower Permit Drawing Package $9,400.00 $9,400.00 Pro-rata share of ATC cost, per attached ATC cost spreadsheets for Briarcliff and Chester Avenue sites, line 167, $4,700 each. $4,700.00 N/A
DTV Medical Facility Notification $11,550.00 $8,000.00 N/A $4,250.00 N/A
Site Permit Drawing Package $9,400.00 $9,400.00 Pro-rata share of ATC cost, per attached ATC cost spreadsheets for Briarcliff and Chester Avenue sites, line 168, $4,700 each. $4,700.00 N/A
Station Coordination Meeting $3,500.00 $3,500.00 Please see the attached invoices from ATC #460200910, 460197967 $1,375.00 N/A
Site Security $1,800.00 $1,800.00 N/A $450.00 N/A

Components

Actual Information Description File Name
Demolition of old HVAC and electrical to make room for combiner Information not provided.
RF System Test

Component Description:
WUVG-DT ATC- Capital Contribution- RF System Testing
Amount:
$2,500.00

Component Description:
WUVGATC- Capital Contribution- RF System Testing
Amount:
$1,250.00

Component Description:
WUVG-DT ATC- Capital Contribution- RF System Testing
Amount:
$1,250.00
Equipment Storage Information not provided.
FCC Filing Fees - Form 2100 license to cover application Information not provided.
FCC Filing Fees - Special Temporary Authorization request Information not provided.
Non-zoning permits

Component Description:
WUVG-DT Non-Zoning Permits
Amount:
$375.00

Component Description:
WUVG Non-Zoning Permits
Amount:
$187.50

Component Description:
WUVG-DT Non-Zoning Permits
Amount:
$187.50
Disposal Costs (for equipment and other waste, net of any salvage value)

Component Description:
"WUVG 1800 Briarcliff Rd NE Atlanta, GA Contract Demolition"
Amount:
$14,829.87

Component Description:
WUVG Disposal Costs
Amount:
$666.66
Equipment Delivery and Handling Charges

Component Description:
Storage of WUVG Aux Transmitter, Comps.
Amount:
$3,380.01

Component Description:
WUVG Equipment Delivery and Handling
Amount:
$2,083.33
Tower Permit Drawing Package

Component Description:
WUVG-DT Tower Permit Drawing Package
Amount:
$2,350.00

Component Description:
WUVG Tower Permit Drawing Package
Amount:
$1,175.00

Component Description:
WUVG-DT Tower Permit Drawing Package
Amount:
$1,175.00
DTV Medical Facility Notification

Component Description:
Medical Notification
Amount:
$4,250.00
Site Permit Drawing Package

Component Description:
WUVG-DT Site Permit Drawing Package
Amount:
$2,350.00

Component Description:
WUVG Site Permit Drawing Package
Amount:
$1,175.00

Component Description:
WUVG-DT Site Permit Drawing Package
Amount:
$1,175.00
Station Coordination Meeting

Component Description:
WUVG-DT ATC- Capital Contribution-Site Coordination
Amount:
$500.00

Component Description:
WUVG ATC- Capital Contribution-Site Coordination
Amount:
$625.00

Component Description:
WUVG-DT ATC- Capital Contribution-Site Coordination
Amount:
$250.00
Site Security

Component Description:
WUVG Site Security
Amount:
$450.00

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $10,721,785.66 $4,071,326.81 $2,759,002.34

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. No
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

JOSE E FRANCHI , FRANCHI .

VP FINANCE


04/23/2020

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

JOSE E FRANCHI , FRANCHI .

VP FINANCE


04/23/2020

Attachments

Back to Top