FCC Form 399: Reimbursement Request

Approved by OMB 3060-1178
Go to the Federal Communications Commission homepage at www.fcc.gov

(REFERENCE COPY - Not for submission) FCC Form 399: Reimbursement Request

Facility ID:
67792
Service:
DTV
Call Sign:
WAQP
Channel:
36 (UHF)
File Number:
0000028021
FRN:
0005077524
Date Submitted:
05/18/2020

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

Radiant Life Ministries, Inc.

Michael Daly

PO Box 1010

MARION, IL 62959

United States

+1 (618) 997-4700 mjd@tct.tv Not-for-Profit

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

The Preparer is same as the reimbursement contact.

 

 

 

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan WAQP has transitioned from ch. 48 to ch. 36 service at its existing transmission location. WAQP replaced its main and back up transmitters, as well as antenna and trans line. WAQP is presently operating on channel 36 facilities.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Auxiliary Transmitter

Back to Top

Add Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Auxiliary (Backup)
Description of Use Back up to main txmtr
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model Visionary
Year 2003
Type Inductive Output Tube
IOT Power Type Single
Power Capacity 30 kW

Auxiliary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Auxiliary (Backup)
Change Type Purchase New
Is this a request for upgraded equipment? No
Manufacturer
Model ULXTE-40
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 25.3 kW
Justification for New Transmitter This transmitter is no longer manufactured or supported (Axcera is no longer in business) and its components are not returnable for use on WAQP's repack channel, so quotes for an appropriately sized solid state transmitter and upgrade have been attached.

Auxiliary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) Yes
Power 150 kVA
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service Yes
Description WAQ will require the assistance of a licensed electrical contractor to disconnect and reconnect existing transmitter electrical service to the repack transmitter.
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Auxiliary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Transmitter removal

WAQP's existing IOT transmitter(s) will require complete removal and disposal. WAQP estimate of deconstruction and disposal costs attached.

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model Sigma
Year 2006
Type Inductive Output Tube
IOT Power Type Single
Power Capacity 30 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? No
Manufacturer
Model ULXTE-40
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 25.3 kW
Justification for New Transmitter Existing single IOT transmitter is no longer produced or supported by its manufacturer (Harris/Gates Air) and it is not able to be retuned to repack channel. Quotations attached are for an equivalent power level solid state transmitter and upgrade.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) Yes
Power 150 kVA
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service Yes
Description WAQP will require the assistance of a licensed electrical contractor to disconnect and reconnect existing transmitter electrical service to the repack transmitter.
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Transmitter removal

WAQP's existing IOT transmitter(s) will require physical removal and disposal to accommodate construction of repack transmitters). WAQP estimate of deconstruction and disposal costs attached.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? Yes
Existing Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels N/A
Design power capacity in use N/A
Lower Limit N/A
Upper Limit N/A
Other Antenna Type N/A
ERP: 851.0 kW
Manufacturer
Model ATW28H3-HTCU-49H
Year 2006

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Types Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Elliptical
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 673.0 kW
Manufacturer
Model ATW28H3-ETC1-36H
Year 2019
Justification for New Antenna WAQP's existing channel 48/49 antenna is channel specific and not compatible with the station's repack channel.

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna?
Type
Number of channels supported N/A
Frequencies of channels supported N/A
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? N/A
Elbow Complex Do you require the separate purchase of the Elbow Complex? No
Broadband or Single Channel? N/A
Feed Line Size N/A
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna?
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Interim Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Interim
Description of Use N/A
Change Type Purchase New
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? No
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Type Class Full Power
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 250.0 kW
Manufacturer
Model TFU 8B8-R
Year 2018
Justification for New Antenna Required to maintain on air station signal continuity during main antenna replacement operations.

Interim Antenna

Back to Top

Other Antenna Costs

Section Question Response
Elbow Complex Do you require the separate purchase of the Elbow Complex? No
Broadband or Single Channel? N/A
Feed Line Size N/A
Side Mount Brackets Do you require the separate purchase of side mount brackets for an antenna? No
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? No

Interim Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing transmission line shared with another station or stations? No
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer
Type Rigid
Diameter 6 1/8 inches
Other Diameter N/A
Segment Length 20 inches
Other Segment Length N/A
Number of parallel runs 1
Length 1150 feet per run

Primary Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? No
Type Rigid
Diameter 6 1/8 inches
Other Diameter N/A
Segment Length 19 3/4 inches
Other Segment Length N/A
Number of parallel runs 1
Length 1150 feet per run
Justification for New Transmission Line The existing line segment length is not compatible with channel 36.

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Information not provided.

Interim Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Interim
Description of Use N/A
Change Type Purchase New
Type Flexible Air
Diameter 3 inches
Segment Length N/A
Other Segment Length
Number of parallel runs 1
Length 1000 feet per run
Justification for New Transmission Line Required for interim antenna installation

Interim Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Information not provided.

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Move Equipment
Tower Use Primary (Main)
Description of Use N/A
Ownership Leased
Is this tower consider Complex? Candelabra
Is this tower currently shared with any other stations? No
One or more FM, AM or TV radio broadcaster(s) N/A
Others Types of Users N/A
Is tower documented for structural analysis? No
Is tower compliant with Rev G? Unknown
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1002081
Coordinates (NAD83) Latitude (NAD83) 43° 13' 18.0" N-
Longitude (NAD83) 084° 03' 14.0" W-
Overall Structure Height 988.83 feet
Support Structure Height 945.85 feet
Ground Elevation Above Mean Sea Level (AMSL) 609.90 feet
Structure Type TOWER - Free Standing or Guyed Structure
Tower Owner TRI STATE CHRISTIAN TV
Date Constructed 03/01/1985


Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Candelabra
Helicopter Services Required Are helicopter services required? Yes

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Name Description

Tower Inspection - Tower Mapping

Tower mapping required for equipment movement

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 595
Explanation WAQP does not have adequate qualified internal staff to manage the construction planning, scheduling, coordination and inspection tasks required to complete this project in a timely and safe manner.
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority No
Quantity N/A
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
NEPA Section 106 environmental review No
Environmental Assessment No
ASR Modification Yes
FAA Consultation (including preparation of FAA Form 7460) Yes
Negotiation of Lease and other Matter for Shared Locations No
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements No
Additional Field Engineering Service No
Number of Days N/A
Justification N/A

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Name Description

Construction management expense

Outside construction management fee

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning No
Non-zoning permits Yes
BLM or NFS Coordination No
FCC Construction Permit Minor Change No
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? No
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? Yes
Does this relocation require MVPD Notification of a Channel Change? Yes

Other Expenses

Back to Top

Other Expenses Not Listed

Name Description

Antenna system unloading

Rigging fee for unloading antenna system upon delivery

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,968,500.00 $1,412,503.92 N/A $1,400,924.53 N/A
Total for all systems $3,652,258.00 $2,867,419.09 N/A $2,021,539.35 N/A
Primary Transmitter ULXTE-40 $984,250.00 $742,109.16 $736,766.65
Transmitter removal $2,000.00 $2,000.00 see Estimated Cost Justification WAQP-110-1st Primary Transmitter - Transmitter Removal v0 $2,000.00 N/A
Other Electrical Service: WAQP will require the assistance of a licensed electrical contractor to disconnect and reconnect existing transmitter electrical service to the repack transmitter. $9,700.00 $9,700.00 see Estimated Cost Justification WAQP-110-1st Primary Transmitter - Other Electrical Service v0 $9,700.00 N/A
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW $947,000.00 $725,066.65 Please see Estimated Cost Justification WAQP-110-1st Primary Transmitter - UHF - Liquid Cooled Solid State Transmitter 25.3 kW v0 $725,066.65 x
Transformer 3 phase/480v - 150 KVA $25,550.00 $5,342.51 Please see transformer documentation called out on quote Q- 78038. $0.00 N/A
Auxiliary Transmitter ULXTE-40 $984,250.00 $670,394.76 $664,157.88
Transmitter removal $2,000.00 $2,000.00 see Estimated Cost Justification WAQP-150-1st Auxiliary Transmitter - Transmitter Removal v0 $2,000.00 N/A
Other Electrical Service: WAQ will require the assistance of a licensed electrical contractor to disconnect and reconnect existing transmitter electrical service to the repack transmitter. $9,700.00 $9,700.00 see Estimated Cost Justification WAQP-150-1st Auxiliary Transmitter - Other Electrical Service v0 $9,700.00 N/A
Transformer 3 phase/480v - 150 KVA $25,550.00 $6,236.88 Please see quote Q-59787 - this is for upgraded equipment. Like-for-like documentation called out on quote Q-78253 $0.00 N/A
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW $947,000.00 $652,457.88 per WAQP-150-1st Auxiliary Transmitter - UHF - Liquid Cooled Solid State Transmitter 25.3 kW Verified Budget Increase Justification v0 $652,457.88 x

Components

Actual Information Description File Name
Transmitter removal

Component Description:
WAQP-110-1st Primary Transmitter - Transmitter Removal
Amount:
$1,150.00

Component Description:
WAQP-110-1st Primary Transmitter - Transmitter Removal
Amount:
$850.00
Other Electrical Service: WAQP will require the assistance of a licensed electrical contractor to disconnect and reconnect existing transmitter electrical service to the repack transmitter.

Component Description:
Disconnection of wiring
Amount:
$5,550.00

Component Description:
Disconnection of wiring
Amount:
$4,150.00
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW

Component Description:
Transmitter
Amount:
$237,576.38

Component Description:
Transmitter
Amount:
$181,415.07

Component Description:
Transmitter
Amount:
$226,926.07

Component Description:
Transmitter
Amount:
$79,149.13
Transformer 3 phase/480v - 150 KVA

Component Description:
WAQP-110-1st Primary Transmitter - Transformer 3 phase/480v - 150 KVA
Amount:
$1,780.83

Component Description:
WAQP-110-1st Primary Transmitter - Transformer 3 phase/480v - 150 KVA
Amount:
$1,780.83
Transmitter removal

Component Description:
WAQP-150-1st Auxiliary Transmitter - Transmitter Removal
Amount:
$1,150.00

Component Description:
WAQP-150-1st Auxiliary Transmitter - Transmitter Removal
Amount:
$850.00
Other Electrical Service: WAQ will require the assistance of a licensed electrical contractor to disconnect and reconnect existing transmitter electrical service to the repack transmitter.

Component Description:
WAQP-150-1st Auxiliary Transmitter - Other Electrical Service
Amount:
$5,550.00

Component Description:
WAQP-150-1st Auxiliary Transmitter - Other Electrical Service
Amount:
$4,150.00
Transformer 3 phase/480v - 150 KVA

Component Description:
WAQP-150-1st Auxiliary Transmitter - Transformer 3 phase/480v - 150 KVA
Amount:
$1,780.83

Component Description:
WAQP-150-1st Auxiliary Transmitter - Transformer 3 phase/480v - 150 KVA
Amount:
$1,780.83
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW

Component Description:
Aux Transmitter
Amount:
$213,478.72

Component Description:
Aux Transmitter
Amount:
$159,959.18

Component Description:
Aux Transmitter
Amount:
$215,374.56

Component Description:
Transmitter
Amount:
$63,645.42

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $485,730.00 $504,685.95 N/A $229,616.60 N/A
Total for all systems $3,652,258.00 $2,867,419.09 N/A $2,021,539.35 N/A
Interim Antenna TFU 8B8-R $189,500.00 $51,325.00 $0.00
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized $189,500.00 $51,325.00 N/A $0.00 N/A
Primary Antenna ATW28H3-ETC1-36H $296,230.00 $453,360.95 $229,616.60
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized $289,500.00 $439,460.95 per WAQP-210-Primary Antenna - UHF High Power Top Mount, E-POL Verified Budget Increase Justification v0 $215,716.60 N/A
Sweep test of existing antenna $6,730.00 $13,900.00 see Estimated Cost Justification WAQP-210-Primary Antenna - Sweep Test v0 $13,900.00 N/A

Components

Actual Information Description File Name
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized Information not provided.
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized

Component Description:
UHF-High Power Top Mount (200-1000KW)
Amount:
$62,935.64

Component Description:
UHF-HIGH POWER TOP MOUNT (200-1000KW)
Amount:
$26,909.68

Component Description:
Primary Antenna
Amount:
$62,935.64

Component Description:
UHF-High Power Top Mount (200-1000KW) ATW28H3-ETC1-36H Top Mounted Elliptically Polarized UHF TRASAR Television Transmitting Antenna
Amount:
$62,935.64

Component Description:
Please deny this invoice.
Amount:
N/A
Sweep test of existing antenna

Component Description:
WAQP-210-Primary Antenna - Sweep Test
Amount:
$3,280.00

Component Description:
WAQP-210-Primary Antenna - Sweep Test-
Amount:
$3,540.00

Component Description:
Sweep Test
Amount:
$3,540.00

Component Description:
WAQP-210-Primary Antenna - Sweep Test
Amount:
$3,540.00

Component Description:
WAQP-210-Primary Antenna - Sweep Test
Amount:
$3,540.00

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $291,300.00 $211,389.57 N/A $0.00 N/A
Total for all systems $3,652,258.00 $2,867,419.09 N/A $2,021,539.35 N/A
Interim Transmission Line $59,000.00 $35,881.62 $0.00
Flexible Air Transmission Line - dielectric, 3" $59,000.00 $35,881.62 N/A $0.00 N/A
Primary Transmission Line $232,300.00 $175,507.95 $0.00
Rigid Transmission Line - copper, 6 1/8" $232,300.00 $175,507.95 N/A $0.00 N/A

Components

Information not provided.

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $655,568.00 $528,564.65 N/A $322,097.97 N/A
Total for all systems $3,652,258.00 $2,867,419.09 N/A $2,021,539.35 N/A
Primary Tower TOWER $655,568.00 $528,564.65 $322,097.97
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $293,996.65 Estimated Cost Justification WAQP-410-Existing Primary Tower - Tower Rigging, Complex Tower v0 $293,996.64 N/A
Tower Inspection - Tower Mapping $4,000.00 $4,000.00 Please see the attached invoice from Thumb Radio Inc # 3465 $3,200.00 N/A
Tower Helicopter Lift $230,568.00 $230,568.00 Please see the attached PO # S-17967 from T.C.T of Michigan, Inc. $24,901.33 N/A

Components

Actual Information Description File Name
Complex Tower (includes, for example, those with candelabras and/or stacked antennas)

Component Description:
40% prior to mobilization Antenna Installation
Amount:
$82,266.66

Component Description:
Revised Analysis and Modification Drawing
Amount:
$7,500.00

Component Description:
Modification Drawings
Amount:
$7,500.00

Component Description:
Antenna Installation
Amount:
$20,566.66

Component Description:
Custom Stub Tower Section & Installation
Amount:
$32,590.00

Component Description:
Antenna Installation
Amount:
$102,833.32

Component Description:
Drawings Purchased from Pirod
Amount:
$8,150.00

Component Description:
Custom Stub Tower Section & Installation
Amount:
$32,590.00
Tower Inspection - Tower Mapping

Component Description:
Tower Mapping, Relamp Tower
Amount:
$3,200.00
Tower Helicopter Lift

Component Description:
WAQP Existing Primary Tower- Helicopter Lift
Amount:
$12,450.67

Component Description:
WAQP-Existing Primary Tower-Helicopter Lift
Amount:
$2,490.13

Component Description:
WAQP-410-Existing Primary Tower - Helicopter Lift
Amount:
$9,960.53

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $223,080.00 $190,010.00 N/A $68,900.25 N/A
Total for all systems $3,652,258.00 $2,867,419.09 N/A $2,021,539.35 N/A
Outside Professional Services $223,080.00 $190,010.00 $68,900.25
Construction management expense $12,000.00 $12,000.00 N/A N/A N/A
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase $2,105.00 $2,000.00 N/A N/A N/A
Project management of the transition $94,010.00 $111,675.00 Please see the attached Widelity quote $68,900.25 N/A
Prepare and or review reimbursement form $2,630.00 $2,500.00 N/A N/A N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A N/A N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $7,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $3,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $5,000.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $2,250.00 N/A N/A N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $3,680.00 $3,585.00 N/A N/A N/A
ASR modification (prepare FCC Form 854) $2,105.00 $2,000.00 N/A N/A N/A
Comprehensive coverage verification via field study, if needed $84,200.00 $35,000.00 N/A N/A N/A

Components

Actual Information Description File Name
Construction management expense Information not provided.
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase Information not provided.
Project management of the transition

Component Description:
Project Management
Amount:
$2,917.45

Component Description:
Project Management
Amount:
$3,220.60

Component Description:
Project Management
Amount:
$80.30

Component Description:
Project Management
Amount:
$4,615.85

Component Description:
Project Management
Amount:
$3,885.40

Component Description:
Project Management
Amount:
$1,372.55

Component Description:
Project Management
Amount:
$2,228.75

Component Description:
Project Management
Amount:
$1,206.55

Component Description:
Project Management
Amount:
$4,727.50

Component Description:
Project Management
Amount:
$3,789.75

Component Description:
Project Management
Amount:
$2,915.05

Component Description:
Project Management
Amount:
$9,975.45

Component Description:
Project Management
Amount:
$1,558.20

Component Description:
Project Management
Amount:
$4,510.45

Component Description:
Project Management
Amount:
$1,915.75

Component Description:
Project Management
Amount:
$1,279.85

Component Description:
Project Management
Amount:
$40.95

Component Description:
Project Management
Amount:
$3,435.20

Component Description:
Project Management
Amount:
$1,415.75

Component Description:
Project Management
Amount:
$2,266.80

Component Description:
Project Management
Amount:
$6,575.90

Component Description:
Project Management
Amount:
$1,583.10

Component Description:
Project Management
Amount:
$1,120.95

Component Description:
Project Management
Amount:
$2,262.15
Prepare and or review reimbursement form Information not provided.
Address transition timing and coordination issues w/ other stations and wireless Information not provided.
Perform engineering study for new channel assignment and antenna development Information not provided.
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application Information not provided.
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Prepare and File request for Special Temporary Authorization Information not provided.
ASR modification (prepare FCC Form 854) Information not provided.
Comprehensive coverage verification via field study, if needed Information not provided.

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $28,080.00 $20,265.00 N/A $0.00 N/A
Total for all systems $3,652,258.00 $2,867,419.09 N/A $2,021,539.35 N/A
Other Expenses $28,080.00 $20,265.00 $0.00
Antenna system unloading $2,000.00 $2,000.00 N/A N/A N/A
MVPD Notification of Channel Change $2,000.00 $2,000.00 N/A N/A N/A
Develop and air announcement of upcoming channel change $2,000.00 $2,000.00 N/A N/A N/A
Equipment Delivery and Handling Charges $2,000.00 $2,000.00 N/A N/A N/A
Non-zoning permits $1,000.00 $1,000.00 N/A N/A N/A
FCC Filing Fees - Special Temporary Authorization request $195.00 $190.00 N/A N/A N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $325.00 N/A N/A N/A
DTV Medical Facility Notification $11,550.00 $3,750.00 N/A $0.00 N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $7,000.00 $7,000.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $3,652,258.00 $2,867,419.09 $2,021,539.35

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. Yes
Construction of final facilities or all necessary modifications are complete. Yes
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Michael Daly

Secretary


05/18/2020

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Michael Daly

Secretary


05/18/2020

Certification

Back to Top
Section Question Response
Submission of Final Allocation or Accounting Information Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  2. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  3. The above-named entity certifies that all costs identified as "actual costs" herein accurately represent the costs actually paid by the above-named entity, including any discounts, refunds, or rebates.

  4. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  5. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  6. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Michael Daly

Secretary


05/18/2020