Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
CBS OPERATIONS INC. Doing Business As: CBS OPERATIONS INC. |
Daniel G. Ryson 1725 DeSales St. NW Suite 501 Washington, DC 20036 United States |
+1 (202) 457-4505 | dryson@cbs.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Daniel G Ryson Associate Director of Spectrum Management CBS |
Daniel G. Ryson 1725 DeSales Street NW Suite 501 Washington, DC 20036 United States |
+1 (202) 457-4074 | dryson@cbs.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | See attached statement. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Retune Existing |
Use | Primary (Main) | |
Ownership | Owned | |
Owner | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | GatesAir |
Model | UAXT-1 | |
Year | 2015 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 0.9 kW |
Section | Question | Response |
---|---|---|
New IOT Tubes | Number of Tubes (including accessories) needed | N/A |
New Mask Filter | ||
Power | Other | |
Other Power | 0 kW | |
New Exciter | Is a new exciter needed? | No |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Re-tune transmitter and mask filter |
Re-tune transmitter and mask filter by manufacturer. |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase | |
Manufacturer | ||
Model | ULXTE-6 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 4.32 kW | |
Justification for New Transmitter | Required to allow the station to remain on the air during the re-tuning of its main transmitter and replacement of its antenna. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | Yes | |
Size | 2 inches | |
Length | 100.0 feet | |
Other Electrical Service | Yes | |
Description | Various Electrical work. See Attachment 11. | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 250.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A | |
Inside RF System | Is an additional interior RF system required to support this interim transmitter? | Yes |
Name | Description |
---|---|
Equipment Racks |
Equipment Racks. See Attachment 12. |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 7.8 kW | |
Manufacturer | ||
Model | B8UA | |
Year | 2000 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Class A |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | TLP-12A/VP-R | |
Year | 2019 | |
Justification for New Antenna | Present antenna cannot be re-tuned. See Attachment 3. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Type | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 7.0 kW | |
Manufacturer | ||
Model | TLP-8M | |
Year | 2019 | |
Justification for New Antenna | Interim antenna required during transition to allow station to remain on the air during channel change. See Attachment 3 |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Utilize Existing |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | Andrew |
Type | Flexible Foam | |
Diameter | 7/8 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 180 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Type | Rigid | |
Diameter | 3 1/8 inches | |
Segment Length | 20' | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 980 feet per run | |
Justification for New Transmission Line | New interim site. No existing line. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Auxiliary (Backup) | |
Description of Use | Interim Antenna | |
Ownership | Leased | |
Is this tower consider Complex? | Candelabra | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1253064 | |
Coordinates (NAD83) | Latitude (NAD83) | 39° 53' 39.2" N- |
Longitude (NAD83) | 086° 12' 20.5" W- | |
Overall Structure Height | 1009.83 feet | |
Support Structure Height | 849.73 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 829.06 feet | |
Structure Type | GTOWER - Guyed Structure Used for Communication Purposes | |
Tower Owner | American Tower, LLC | |
Date Constructed | 07/24/2006 |
Facility ID | Call Sign | Service |
---|---|---|
69115 | WICR | FM |
7908 | WDTI | DTV |
37102 | WHMB-TV | DTV |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for tower with candelabra |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Minor Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Candelabra |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Site Coordination Meeting |
Site coordination meetings with tower owner, broadcasters, and vendors. See Attachment 4. |
Tower Rent |
Tower rent for duration of repack period. See Attachment 4. |
Permits |
Preparation and submission of forms for electrical, building and other permits. See Attachment 4. |
Tower Permit Packages |
Tower, ground, and building construction drawing package required for local permits. Please see Attachment 4 |
Tower Project Management |
Construction project management for tower work. Please see Attachment 4. |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | Located on Building | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
ASR Number | ||
Coordinates (NAD83) | Latitude (NAD83) | 39° 46' 11.1" N- |
Longitude (NAD83) | 086° 09' 25.9" W- | |
Overall Structure Height | 830.00 feet | |
Support Structure Height | 630.00 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 717.00 feet | |
Structure Type | BANT - Building with an Antenna | |
Tower Owner | Hertz Investment Group | |
Date Constructed | 01/01/1990 |
Facility ID | Call Sign | Service |
---|---|---|
59590 | WFBQ | FM |
59589 | WOLT | FM |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | No study needed |
Tower Reinforcements | Please select whether tower reinforcements are needed: | No reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Located on Building |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 100 | |
Explanation | Staff not available. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | No |
For Auxiliary Facility | N/A | |
For Main Facility | N/A | |
Prepare and file Form FCC License to Cover Application | No | |
For Auxiliary Facility | N/A | |
For Main Facility | N/A | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | No | |
Address transition timing and coordination issues w/ other stations and wireless providers | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | Yes | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | No | |
Does this relocation require MVPD Notification of a Channel Change? | No |
Name | Description |
---|---|
Studio Transmitter Link |
Data and programming terminal equipment required to convey digitized television programming to interim site. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $385,709.96 | $284,051.56 | N/A | $58,616.22 | N/A |
Total for all systems | $1,729,726.96 | $918,445.10 | N/A | $258,882.75 | N/A |
Interim Transmitter ULXTE-6 | $268,588.44 | $260,988.44 | $58,616.22 | ||
Other -- Building Addition Size: 250.0 | $55,676.94 | $55,676.94 | See Attachments 9 (Lockwood Design) and 10 (Assisted Integrated Systems). | $47,276.94 | N/A |
Equipment Racks | $4,093.66 | $4,093.66 | Equipment Racks required for ancillary hardware at interim site. See Attachment 12. | $0.00 | N/A |
UHF inside RF system including switching | $147,500.00 | $140,000.00 | N/A | N/A | N/A |
Other Electrical Service: Various Electrical work. See Attachment 11. | $24,700.00 | $24,700.00 | Various electrical work at interim site. See Attachment 11. | N/A | N/A |
2" Rigid Conduit and Wiring (Cost per foot) | $2,600.00 | $2,500.00 | N/A | N/A | N/A |
UHF - Liquid Cooled Solid State Transmitter 4.32 kW | $34,017.84 | $34,017.84 | See Attachment 19 and 22. This cost is for a comparable 20 watt transmitter, including mask filter, RF accessories, electrical, installation and proof. | $11,339.28 | N/A |
Primary Transmitter UAXT-1 | $117,121.52 | $23,063.12 | $0.00 | ||
Re-tune transmitter and mask filter | $11,921.52 | $11,921.52 | See Attachment 1 | N/A | N/A |
Other 0 kW mask filter | $0.00 | $0.00 | Existing mask filter can be retuned. | N/A | N/A |
UHF and VHF - minor banding issues | $105,200.00 | $11,141.60 | See Attachment 1. | N/A | N/A |
Actual Information Description | File Name |
---|---|
Other -- Building Addition Size: 250.0 | |
Equipment Racks | Information not provided. |
UHF inside RF system including switching | Information not provided. |
Other Electrical Service: Various Electrical work. See Attachment 11. | Information not provided. |
2" Rigid Conduit and Wiring (Cost per foot) | Information not provided. |
UHF - Liquid Cooled Solid State Transmitter 4.32 kW | |
Re-tune transmitter and mask filter | Information not provided. |
Other 0 kW mask filter | Information not provided. |
UHF and VHF - minor banding issues | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $52,977.00 | $39,234.00 | N/A | $26,225.50 | N/A |
Total for all systems | $1,729,726.96 | $918,445.10 | N/A | $258,882.75 | N/A |
Interim Antenna TLP-8M | $33,030.00 | $19,617.00 | $16,417.00 | ||
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | $3,200.00 | N/A |
UHF - Lower Power Side Mount, Class A One Station antenna -- basic | $26,300.00 | $13,217.00 | See Attachment 5 Items 1 and 2. Includes side-mount brackets. | $13,217.00 | N/A |
Primary Antenna TLP-12A/VP-R | $19,947.00 | $19,617.00 | $9,808.50 | ||
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | $3,200.00 | N/A |
UHF - Lower Power, Top Mount, Class A, basic slot antenna, 15 kW input, elliptically or circularly polarized | $13,217.00 | $13,217.00 | Reimbursement cost based on a hypothetical Dielectric TLP-8M and bracketes. See Attachments 5, 7, and 19. | $6,608.50 | N/A |
Actual Information Description | File Name |
---|---|
Sweep test of existing antenna | |
UHF - Lower Power Side Mount, Class A One Station antenna -- basic | |
Sweep test of existing antenna | |
UHF - Lower Power, Top Mount, Class A, basic slot antenna, 15 kW input, elliptically or circularly polarized |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $101,920.00 | $24,087.54 | N/A | $24,087.54 | N/A |
Total for all systems | $1,729,726.96 | $918,445.10 | N/A | $258,882.75 | N/A |
Interim Transmission Line | $101,920.00 | $24,087.54 | $24,087.54 | ||
Rigid Transmission Line - copper, 3 1/8" | $101,920.00 | $24,087.54 | We are proposing 3 1/8-inch rigid transmission line but only seeking reimbursement for 1 5/8-inch air dielectric line. See Attachment 8, lines 3-18. | $24,087.54 | N/A |
Primary Transmission Line | $0.00 | $0.00 | $0.00 |
Actual Information Description | File Name |
---|---|
Rigid Transmission Line - copper, 3 1/8" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,099,730.00 | $504,497.00 | N/A | $143,480.00 | N/A |
Total for all systems | $1,729,726.96 | $918,445.10 | N/A | $258,882.75 | N/A |
Primary Tower BANT | $421,000.00 | $200,000.00 | $0.00 | ||
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $200,000.00 | 50% of Widelity Cost Catalog Estimate | $0.00 | N/A |
Auxiliary Tower GTOWER | $678,730.00 | $304,497.00 | $143,480.00 | ||
Tower Project Management | $9,480.00 | $9,480.00 | Construction project management. See Attachment 4. (Estimated cost was adjusted 31 Oct 2019 to match value in Attachment 4.) | $9,480.00 | N/A |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $200,000.00 | 50% of Widelity Cost Catalog Estimate. See also Attachment 13. | $134,000.00 | N/A |
Minor tower reinforcement/modifications | $158,000.00 | $10,000.00 | It is expected that additional loads imposed on the tower by the new repack antennas will cause the tower to fail. The structural failure is expected to be in the minor category. See Attachment 4. | N/A | N/A |
Structural engineering tower load study for a documented tower with candelabra | $20,000.00 | $14,767.00 | Tower mapping and structural engineering for a tower with a candelabra. | N/A | N/A |
Site Coordination Meeting | $2,500.00 | $2,500.00 | Site coordination meeting with tower owner, other broadcasters, contractors, and vendors at interim tower site. See Attachment 4. | N/A | N/A |
Tower Rent | $57,600.00 | $57,600.00 | Required for operation on interim tower. See Attachment 4. | N/A | N/A |
Permits | $750.00 | $750.00 | Prepare and submit forms for electrical, building and other permits necessary for local approvals. See Attachment 4. | N/A | N/A |
Tower Permit Packages | $9,400.00 | $9,400.00 | Construction drawings for tower, building, and ground required for local permits. See Attachment 4. | N/A | N/A |
Actual Information Description | File Name |
---|---|
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | Information not provided. |
Tower Project Management | |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | |
Minor tower reinforcement/modifications | Information not provided. |
Structural engineering tower load study for a documented tower with candelabra | Information not provided. |
Site Coordination Meeting | Information not provided. |
Tower Rent | Information not provided. |
Permits | Information not provided. |
Tower Permit Packages | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $57,310.00 | $44,050.00 | N/A | $575.00 | N/A |
Total for all systems | $1,729,726.96 | $918,445.10 | N/A | $258,882.75 | N/A |
Outside Professional Services | $57,310.00 | $44,050.00 | $575.00 | ||
RF Exposure Measurements | $21,050.00 | $10,000.00 | N/A | N/A | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $4,210.00 | $4,000.00 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application | $2,105.00 | $2,050.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | $575.00 | N/A |
Project management of the transition | $15,800.00 | $15,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
RF Exposure Measurements | Information not provided. |
Attorney Fees - Negotiation of lease and other matters for shared locations | Information not provided. |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | |
Project management of the transition | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $32,080.00 | $22,525.00 | N/A | $5,898.49 | N/A |
Total for all systems | $1,729,726.96 | $918,445.10 | N/A | $258,882.75 | N/A |
Other Expenses | $32,080.00 | $22,525.00 | $5,898.49 | ||
DTV Medical Facility Notification | $11,550.00 | $2,000.00 | N/A | $2,000.00 | N/A |
Studio Transmitter Link | $10,000.00 | $10,000.00 | Data and programming terminal equipment. Required to convey digitized television programming to interim site. | N/A | N/A |
Equipment Delivery and Handling Charges | $5,000.00 | $5,000.00 | N/A | $3,698.49 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $200.00 | Filing Fees have increased. | $200.00 | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
DTV Medical Facility Notification | |
Studio Transmitter Link | Information not provided. |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
FCC Filing Fees - Special Temporary Authorization request | |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $1,729,726.96 | $918,445.10 | $258,882.75 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Andrew J Siegel Assistant Secretary 10/31/2019 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Andrew J Siegel Assistant Secretary 10/31/2019 |