Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
NRJ TV LA LICENSE CO, LLC |
Robert Andrews 722 S. DENTON TAP ROAD SUITE 130 COPPELL, TX 75019 United States |
+1 (972) 947-3391 | bob@nrjventures.com | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Peter Douglas VP Engineering NRJ TV VI LLC |
Peter Douglas 3310 Keller Springs Rd Ste 110 Carrollton, TX 75006 United States |
+1 (303) 881-9185 | pdouglas@nrjtv.net |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Station plans to replace the filters, and re-tune the transmitter if possible. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Retune Existing |
Use | Primary (Main) | |
Ownership | Owned | |
Owner | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | Pineapple |
Model | ADT-1000 | |
Year | 2007 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | .35 kW |
Section | Question | Response |
---|---|---|
New IOT Tubes | Number of Tubes (including accessories) needed | N/A |
New Mask Filter | ||
Power | 1.5 kW | |
Other Power | N/A | |
New Exciter | Is a new exciter needed? | No |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Transmitter Tech Expenses |
Travel, per diem, lodging for transmitter tech to be on site |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | No |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 40 | |
Explanation | Site co-ordination and final verifiations. 40 hrs at $100 hr. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
Project management expenses |
Travel, per diem, lodging for on site visits for project management |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | No | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $110,030.00 | $7,100.00 | N/A | $0.00 | N/A |
Total for all systems | $156,175.00 | $48,025.00 | N/A | $5,397.69 | N/A |
Primary Transmitter ADT-1000 | $110,030.00 | $7,100.00 | $0.00 | ||
UHF and VHF - minor banding issues | $105,200.00 | $2,500.00 | N/A | N/A | N/A |
Transmitter Tech Expenses | $1,800.00 | $1,800.00 | Expenses for on-site tech to re-tune transmitter and verify compliance | N/A | N/A |
1.5 kW mask filter | $3,030.00 | $2,800.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $32,700.00 | $29,150.00 | N/A | $5,397.69 | N/A |
Total for all systems | $156,175.00 | $48,025.00 | N/A | $5,397.69 | N/A |
Outside Professional Services | $32,700.00 | $29,150.00 | $5,397.69 | ||
Project management expenses | $1,400.00 | $1,400.00 | On-site expenses for project management | $372.69 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | $125.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | $0.00 | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | $650.00 | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | $2,500.00 | N/A |
Project management of the transition | $6,320.00 | $4,000.00 | N/A | N/A | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | $1,750.00 | N/A |
Actual Information Description | File Name |
---|---|
Project management expenses | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | |
Prepare and or review reimbursement form | |
Project management of the transition | Information not provided. |
Address transition timing and coordination issues w/ other stations and wireless | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $13,445.00 | $11,775.00 | N/A | $0.00 | N/A |
Total for all systems | $156,175.00 | $48,025.00 | N/A | $5,397.69 | N/A |
Other Expenses | $13,445.00 | $11,775.00 | $0.00 | ||
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $450.00 | $450.00 | Contractor to edit announcement. | N/A | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $0.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $156,175.00 | $48,025.00 | $5,397.69 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Robert Andrews Sr VP 04/13/2018 |