Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
FOX TELEVISION STATIONS, LLC |
Joseph M. Di Scipio 400 N. CAPITOL STREET, NW SUITE 890 WASHINGTON, DC 20001 United States |
+1 (202) 824-6522 | JDISCIPIO@21CF.COM | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Dennis Wallace Managing Partner Meintel, Sgrignoli & Wallace, LLC |
Dennis Wallace 1282 Smallwood Drive Suite 372 Waldorf, MD 20603 United States |
+1 (202) 251-7589 | Dennis.Wallace@mswdtv.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | WFLD plans to install interim facilities in cooperation with other stations at Willis Tower, replace existing antennna, transmission line, and Transmitter. Complex site on top of Willis Tower. The building is still working on transition plan for the site. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | CD2200P3 | |
Year | 1999 | |
Type | Inductive Output Tube | |
IOT Power Type | Three | |
Power Capacity | 75 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | Paragon | |
Transmitter Type | Inductive Output Tube | |
IOT Power Type | Three | |
Power capacity | 75 kW | |
Justification for New Transmitter | New transmitter required as existing unit is obsolete and no longer supported by manufacturer. Existing transmitter is rated 75KW. New TPO cannot be determined at this time. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 300 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 3 inches | |
Length | 400.0 feet | |
Other Electrical Service | Yes | |
Description | IOT Transmitter Electrical Installation Costs Willis Tower | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 50 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 1000.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Plumbing Demolition |
Disconnect Piping for transmitter (Great Lakes) |
Water Glycol System |
Building Chilled Water System Connection. (ZonaTherm) |
Remove Existing Main Transmitter |
Remove existing main transmitter from Willis Tower |
ThermoFlo Leibert system |
ThermoFlo Leibert Installation |
Remote Control Wiring |
Wire up existing remote control to new transmitter |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase | |
Manufacturer | ||
Model | THU9EVO-40 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 60 kW | |
Justification for New Transmitter | Interim transmitter will be required to operate interim facilities while building is changing out antennas and other stations make changes. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | Yes | |
Power | 500 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 3 inches | |
Length | 300.0 feet | |
Other Electrical Service | Yes | |
Description | Interim Transmitter Electrical Installation - Willis Tower | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 50 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 1000.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A | |
Inside RF System | Is an additional interior RF system required to support this interim transmitter? | Yes |
Name | Description |
---|---|
Willis Tower Fees |
Fees to Willis Tower for Interim Transmitter Installation & Operation |
Remove existing equipment |
Removal of existing equipment in interim transmitter area |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Auxiliary (Backup) | |
Description of Use | Licensed Aux Antenna | |
Ownership | Leased | |
Owner | Willis Tower | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | Yes | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Bottom | |
Polarization | Circular | |
Type | Broadband Panel | |
Number of Stations Supported | 2 | |
Number of Panels | 24 | |
Design power capacity in use | 100.0 % | |
Lower Limit | 572.00 MHz | |
Upper Limit | 578.00 MHz | |
Other Antenna Type | N/A | |
ERP: | 475.0 kW | |
Manufacturer | ||
Model | PHP24C | |
Year | 1999 |
Facility ID | Call Sign |
---|---|
47905 | WMAQ-TV |
22211 | WFLD |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Auxiliary (Backup) |
Description of Use | Aux Antenna | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Ownership | Leased | |
Owner | Willis Tower | |
Is antenna shared? | Yes | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Bottom | |
Polarization | Elliptical | |
Type | Broadband Panel | |
Number of Stations Supported | 2 | |
Number of Panels/Bays | 24 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 600.00 MHz | |
Design power capacity in use | 100.0 % | |
Other Antenna Type | N/A | |
ERP: | 475.0 kW | |
Manufacturer | ||
Model | TBD | |
Year | 2018 | |
Justification for New Antenna | Replacement of Aux Antenna as needed to move antennas on top of building. Final Aux antenna configuration yet to be determined. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 2 | |
Frequencies of channels supported | RF channel | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | Yes | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Broadband | |
Feed Line Size | 6 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | Yes |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
RF Channel Number |
---|
29 |
24 |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Middle | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 1000.0 kW | |
Manufacturer | ||
Model | ATW14H3H-ETC2-31H | |
Year | 1999 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Top | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 859.0 kW | |
Manufacturer | ||
Model | To Be Determined | |
Year | 2018 | |
Justification for New Antenna | New antenna required for new channel. Slot antenna. Final antenna configuration has not been determined yet. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 7 3/16 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | Yes |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Name | Description |
---|---|
West Tower Stack Project |
Willis Tower West Tower Stack Project per Willis Spreadsheet. |
Combiner Room Costs |
Willis Tower Combiner Room Modification Cost Estimate. Per Willis Tower Spreadsheet. |
Southwest Pole Decommissioning |
Willis Tower Decommissioning of SW Pole. per Willis Tower Spreadsheet. |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Auxiliary (Backup) | |
Description of Use | Licensed Aux | |
Ownership | Leased | |
Owner | Willis Tower | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | Yes | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 2 | |
Length | 400 feet per run |
Facility ID | Call Sign |
---|---|
47905 | WMAQ-TV |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Auxiliary (Backup) |
Description of Use | Licensed Aux | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 19 3/4 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 2 | |
Length | 400 feet per run | |
Justification for New Transmission Line | Replacement of Aux Antenna Transmission Line. The new Aux Combiner will be in a new location within the building and will require new transmission line. |
Name | Description |
---|---|
Transmission Line Layout |
Develop Transmission line layout and installation drawings for Aux Antenna. |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 8 3/16 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 400 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 7 3/16 inches | |
Other Diameter | N/A | |
Segment Length | 19 3/4 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 300 feet per run | |
Justification for New Transmission Line | Current Transmission line does not extend to the top of the west tower and it routed to the top of the SW Pole Outrigger. The New Antenna location requires new transmission line. However, applicant will re-use as much as possible of the existing line. |
Name | Description |
---|---|
Transmission Line Layout Installation Drawings |
Develop and play transmission line layout and installation drawings. See attached Quote. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | Located on Building | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1032959 | |
Coordinates (NAD83) | Latitude (NAD83) | 41° 52' 44.1" N- |
Longitude (NAD83) | 087° 38' 10.2" W- | |
Overall Structure Height | 1729.97 feet | |
Support Structure Height | 1435.35 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 595.14 feet | |
Structure Type | BTWR - Building with Tower | |
Tower Owner | 233 Broadcast, LLC | |
Date Constructed | 01/01/2002 |
Facility ID | Call Sign | Service |
---|---|---|
71283 | WCFS-FM | FM |
73226 | WLS-TV | DTV |
60539 | WXFT-DT | DTV |
72115 | WGN-TV | DTV |
10802 | WTTW | DTV |
6377 | WTMX | FM |
10801 | WFMT | FM |
51165 | WGCI-FM | FM |
74178 | WKSC-FM | FM |
22211 | WFLD | DTV |
70042 | WLIT-FM | FM |
48772 | WPWR-TV | DTV |
71425 | WWME-CD | DTV |
28621 | WJMK | FM |
12498 | WGBO-DT | DTV |
47905 | WMAQ-TV | DTV |
9617 | WBBM-TV | DTV |
32334 | WJYS | DTV |
9613 | WBBM-FM | FM |
73228 | WLS-FM | FM |
53971 | WEBG | FM |
10981 | WCPX-TV | DTV |
Users |
---|
Willis Tower |
Microwave |
Two Way |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for tower with candelabra |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Serious Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Located on Building |
Helicopter Services Required | Are helicopter services required? | Yes |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 1500 | |
Explanation | Outside Project Management to coordinate with Willis Tower, Antenna, Helicopter, Rigging, and Transmitter Replacements. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | Yes | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | Yes | |
Number of Days | 45 | |
Justification | On Site RF Engineering to supervise equipment installation, performance measurements, and compliance with project requirements. |
Name | Description |
---|---|
Prepare and File FCC Progress Reports |
Prepare and File FCC Progress Reports |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
Illinois and Chicago Sales Tax |
Estimated Sales tax on equipment. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $5,321,530.00 | $5,880,667.00 | N/A | $0.00 | N/A |
Total for all systems | $12,425,532.00 | $11,363,156.00 | N/A | $0.00 | N/A |
Interim Transmitter THU9EVO-40 | $2,554,860.00 | $2,447,560.00 | $0.00 | ||
Remove existing equipment | $92,860.00 | $92,860.00 | Remove existing equipment from interim transmitter space. Willis Tower Building. Does not include disposal of equipment. See attached quote. | N/A | N/A |
Willis Tower Fees | $0.00 | $0.00 | Willis Tower Fees for Interim transmitter installation | N/A | N/A |
Transformer 3 phase/480v - 500 KVA | $48,400.00 | $46,000.00 | Catalog | N/A | N/A |
Other -- Building Addition Size: 1000.0 | $150,000.00 | $150,000.00 | Building Space Modifications for Interim Transmitter Space at Willis Tower Building. | N/A | N/A |
UHF inside RF system including switching | $147,500.00 | $140,000.00 | Catalog | N/A | N/A |
50 Ton system | $172,500.00 | $164,000.00 | Catalog HVAC/Mechanical Mods - Willis Tower Space | N/A | N/A |
UHF - Liquid Cooled Solid State Transmitter 52 - 61 kW | $1,788,000.00 | $1,700,000.00 | Interim Transmitter | N/A | N/A |
3" Rigid Conduit and Wiring (Cost per foot) | $15,600.00 | $14,700.00 | Catalog | N/A | N/A |
Other Electrical Service: Interim Transmitter Electrical Installation - Willis Tower | $140,000.00 | $140,000.00 | Interim Transmitter Electrical Installation Willis Tower Building | N/A | N/A |
Primary Transmitter Paragon | $2,766,670.00 | $3,433,107.00 | $0.00 | ||
ThermoFlo Leibert system | $360,000.00 | $360,000.00 | ThermoFlo Quote Attached. Leibert Units Installation at Willis Tower | N/A | N/A |
Water Glycol System | $75,750.00 | $75,750.00 | ZonaTherm Quote attached. Water/Glycol System | N/A | N/A |
Plumbing Demolition | $13,220.00 | $13,220.00 | Plumbing Demolition. Pipefitter Scope. Quote Attached. | N/A | N/A |
Remote Control Wiring | $3,600.00 | $3,600.00 | Wire up existing remote control to new transmitter. See attached vendor quote. | N/A | N/A |
Three IOT system (75 kW) | $1,415,000.00 | $2,094,837.00 | Comark Quote 3 tube Paragon Transmitter is attached. | N/A | N/A |
Remove Existing Main Transmitter | $180,000.00 | $180,000.00 | Quote to remove existing equipment. Beam Supplies, HE Glycol, Etc. Down Elevator. Rigging, Labor Overtime on Weekends/Nights. See attached quote. Does not include disposal. | N/A | N/A |
Other -- Building Addition Size: 1000.0 | $250,000.00 | $250,000.00 | Modifications to building space for new transmitter. Willis Tower Building. | N/A | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $36,300.00 | Catalog | N/A | N/A |
Transformer 3 phase/480v - 300 KVA | $36,800.00 | $35,000.00 | Catalog | N/A | N/A |
3" Rigid Conduit and Wiring (Cost per foot) | $20,800.00 | $19,600.00 | Catalog | N/A | N/A |
Other Electrical Service: IOT Transmitter Electrical Installation Costs Willis Tower | $200,800.00 | $200,800.00 | Electrical Installation for new transmitter. Willis Tower Building. See Okeh Electric Quote attached. | N/A | N/A |
50 Ton system | $172,500.00 | $164,000.00 | Modifications to HVAC/Mechanical Systems Willis Tower Building | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $3,890,037.00 | $3,597,774.00 | N/A | $0.00 | N/A |
Total for all systems | $12,425,532.00 | $11,363,156.00 | N/A | $0.00 | N/A |
Primary Antenna To Be Determined | $2,862,997.00 | $2,967,207.00 | $0.00 | ||
Elbow complex, single channel, at antenna input, per 7 3/16. feedline (if needed) | $13,900.00 | $13,200.00 | Catalog Costs. | N/A | N/A |
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) | $5,260.00 | $5,000.00 | Catalog Cost. | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | Catalog Cost. | N/A | N/A |
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized | $289,500.00 | $395,000.00 | Custom Three Station Stack Antenna designed for Willis Tower Building West Pylon. Final Antenna Configuration is not known at this time. This antenna will require special structural design. | N/A | N/A |
Southwest Pole Decommissioning | $1,110,500.00 | $1,110,500.00 | Willis Tower Spreadsheet. WFLD Allocated costs of project per Willis Tower Engineering Statement attached. | N/A | N/A |
Combiner Room Costs | $12,857.00 | $12,857.00 | Willis Tower Spreadsheet. Costs for modification of combiner room per Willis Tower Engineering Statement attached. | N/A | N/A |
West Tower Stack Project | $1,424,250.00 | $1,424,250.00 | Willis Tower Triple Destack and Double Stack per attached spreadsheet from Willis Tower and attached Willis Tower Engineering Statement. | N/A | N/A |
Auxiliary Antenna TBD | $1,027,040.00 | $630,567.00 | $0.00 | ||
UHF - High Power Top Mount (200-1000 kW), Two Station broadband panel antenna, elliptically or circularly polarized | $768,000.00 | $0.00 | Catalog | N/A | N/A |
New combiner, cost per channel (without antenna) | $84,200.00 | $464,167.00 | Willis Tower Aux Combiner / East Tower per Willis Tower Spreadsheet. See attached Willis Tower Engineering Statement. | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | Catalog Costs. | N/A | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $22,000.00 | Catalog Costs. | N/A | N/A |
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) | $5,260.00 | $5,000.00 | Catalog Costs. | N/A | N/A |
Elbow complex, broadband, at antenna input, per 6 1/8. feedline (if needed) | $13,700.00 | $13,000.00 | Catalog | N/A | N/A |
Combiner output splitting/switching for dual feed lines, if applicable | $126,000.00 | $120,000.00 | Catalog | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $308,600.00 | $450,000.00 | N/A | $0.00 | N/A |
Total for all systems | $12,425,532.00 | $11,363,156.00 | N/A | $0.00 | N/A |
Primary Transmission Line | $122,000.00 | $250,000.00 | $0.00 | ||
Transmission Line Layout Installation Drawings | $35,000.00 | $35,000.00 | Develop transmission line layout and installation drawings. See attached vendor quote. | N/A | N/A |
Rigid Transmission Line - copper, 7 3/16" | $87,000.00 | $215,000.00 | Custom Transmission line fabrication required. Each section will need to be a custom made section length in order to fit within the existing hallways and vertical shafts within Willis Tower. Standard Line section costs is not applicable. | N/A | N/A |
Auxiliary Transmission Line | $186,600.00 | $200,000.00 | $0.00 | ||
Transmission Line Layout | $25,000.00 | $25,000.00 | Develop transmission line layout and installation drawings. See attached vendor quote. | N/A | N/A |
Rigid Transmission Line - copper, 6 1/8" | $161,600.00 | $175,000.00 | Custom transmission line fabrication required. Each line section will need to be custom made based upon CAD drawings in order to fit within the existing hallway and vertical shafts within the Willis Tower Building. Standard line sections will not fit. | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,493,000.00 | $0.00 | N/A | $0.00 | N/A |
Total for all systems | $12,425,532.00 | $11,363,156.00 | N/A | $0.00 | N/A |
Primary Tower BTWR | $1,493,000.00 | $0.00 | $0.00 | ||
Tower Helicopter Lift | $0.00 | $0.00 | See attached Willis Tower Engineering Statement and Spreadsheet. | N/A | N/A |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $0.00 | See attached Willis Tower Spreadsheet and Engineering Statement. | N/A | N/A |
Serious tower reinforcement/modifications | $1,052,000.00 | $0.00 | See attached Willis Tower spreadsheet and engineering statement. | N/A | N/A |
Structural engineering tower load study for a documented tower with candelabra | $20,000.00 | $0.00 | See attached Willis Tower Engineering Statement. | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $521,175.00 | $544,130.00 | N/A | $0.00 | N/A |
Total for all systems | $12,425,532.00 | $11,363,156.00 | N/A | $0.00 | N/A |
Outside Professional Services | $521,175.00 | $544,130.00 | $0.00 | ||
Prepare and File FCC Progress Reports | $34,980.00 | $34,980.00 | Prepare and File FCC Progress Reports. See attached vendor quote. | N/A | N/A |
Additional Field Engineering Service, 45 Days | $95,400.00 | $95,400.00 | See attached vendor quote. On Site RF Engineering for complex project. Supervision of installation and commissioning of new systems. | N/A | N/A |
RF Exposure Measurements | $21,050.00 | $20,000.00 | Catalog | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $80,000.00 | Catalog | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $7,360.00 | $7,000.00 | Catalog | N/A | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $4,210.00 | $35,000.00 | Willis Tower Building Lease Modifications | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | Catalog | N/A | N/A |
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application | $4,210.00 | $4,000.00 | Catalog | N/A | N/A |
Project management of the transition | $237,000.00 | $225,000.00 | Very large scope project management. | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | Catalog | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | Catalog | N/A | N/A |
Prepare request for Special Temporary Authorization | $4,100.00 | $3,000.00 | Catalog | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | Catalog | N/A | N/A |
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application | $2,105.00 | $2,000.00 | Catalog | N/A | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $15,000.00 | Coordination for Chicago Market and Willis Tower Building Testing and Transition End Dates | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | Catalog | N/A | N/A |
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application | $1,580.00 | $1,500.00 | Catalog | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | Catalog | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $891,190.00 | $890,585.00 | N/A | $0.00 | N/A |
Total for all systems | $12,425,532.00 | $11,363,156.00 | N/A | $0.00 | N/A |
Other Expenses | $891,190.00 | $890,585.00 | $0.00 | ||
Equipment Delivery and Handling Charges | $250,000.00 | $250,000.00 | Delivery and Logistics for Equipment to Willis Tower Building. Elevator and Freight Dock Considerations. Special elevator lifts. See attached rate sheet from Willis Tower Building Management. | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $45,000.00 | $45,000.00 | Disposal of Glycol, Transformer Oil, Old Antenna, etc. from Willis Tower Building. | N/A | N/A |
Non-zoning permits | $19,000.00 | $19,000.00 | Building Permits, Electrical, and Mechanicals. Willis Tower Building City of Chicago | N/A | N/A |
Local Zoning | $0.00 | $0.00 | N/A | N/A | N/A |
Illinois and Chicago Sales Tax | $512,500.00 | $512,500.00 | Estimated Chicago and Illinois Sales Tax on Equipment. The sales tax rate in the City of Chicago is 10.25%. Total Estimated Sales Tax on equipment at the 10.25% rate. | N/A | N/A |
MVPD Notification of Channel Change | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $1,500.00 | $1,500.00 | N/A | N/A | N/A |
Equipment Storage | $45,000.00 | $45,000.00 | Equipment Storage off site until needed on site. | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $190.00 | Catalog | N/A | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,070.00 | Catalog | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | Catalog | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $12,425,532.00 | $11,363,156.00 | $0.00 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Joseph M. Di Scipio SVP, Legal and FCC Compliance 09/17/2017 |