Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
KOREAN AMERICAN TV BROADCASTING CORP. Doing Business As: KOREAN AMERICAN TV BROADCASTING CORP. |
SUSAN SIM OH 4675 RIVER GREEN PARKWAY DULUTH, GA 30096 United States |
+1 (770) 497-0076 | susan.oh@telemundoatlanta.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
DAVINA SASHKIN Fletcher, Heald & Hildreth, PLC |
DAVINA S. SASHKIN 1300 N. 17th Street Suite 1100 Arlington, VA 22209 United States |
+1 (703) 812-0400 | sashkin@fhhlaw.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | WKTB-CD is changing channels from 47 to 23 according to the repack phase plan. The station will require a new antenna and must mount higher on the tower, but will be able to re-use the transmitter via retuning. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Retune Existing |
Use | Primary (Main) | |
Ownership | Owned | |
Owner | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | Rohde & Schwartz |
Model | NV8306 | |
Year | 2011 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 1.8 kW |
Section | Question | Response |
---|---|---|
New IOT Tubes | Number of Tubes (including accessories) needed | N/A |
New Mask Filter | ||
Power | 3 kW | |
Other Power | N/A | |
New Exciter | Is a new exciter needed? | No |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this antenna currently shared with any other stations? | No | |
Is this antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 12.5 kW | |
Manufacturer | ||
Model | ALP12L2-HSOC | |
Year | 2010 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 7.7 kW | |
Manufacturer | ||
Model | TLP-12B | |
Year | 2018 | |
Justification for New Antenna | Current antenna is incapable of operating on repacked channel. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Name | Description |
---|---|
Antenna Space Rent |
22 months of antenna space rent |
Antenna Space Reservation |
Antenna space reservation one-time fee |
Dehydrator |
Automatic dehydrator with alarm |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Air | |
Diameter | 1 5/8 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 0 | |
Length | 425 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Type | Flexible Air | |
Diameter | 1 5/8 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 0 | |
Length | 425 feet per run | |
Justification for New Transmission Line | New transmission line is necessary to install new antenna at higher location on tower while current facilities operate. |
Name | Description |
---|---|
Gas Pass Connector Conversion Kit |
See attached Quote from SJ Ramer Associates, Inc. |
Transmission Line Installation Kit |
See attached Quote from SJ Ramer Associates, Inc. |
Two 1 5-8 EIA Female Connectors |
See attached Quote from SJ Ramer Associates, Inc. |
7-8 and 1 5-8 Air Connector |
See attached Quote from SJ Ramer Associates, Inc. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Yes | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1018919 | |
Coordinates (NAD83) | Latitude (NAD83) | 33° 55' 01.3" N- |
Longitude (NAD83) | 084° 12' 05.9" W- | |
Overall Structure Height | 499.99 feet | |
Support Structure Height | 495.07 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 1089.88 feet | |
Structure Type | LTOWER - Lattice Tower | |
Tower Owner | American Towers, LLC. | |
Date Constructed | 01/24/2012 |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Tower Permit Drawing Package |
The generation of a permitting drawing packing for one broadcaster or customer. |
Ground and Building AandE Permit Drawing Package |
The generation of a permitting drawing packing for one broadcaster or customer. |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 95 | |
Explanation | Pre-construction services (including initial antenna placement and RF compatibility review, zoning and permitting requirements review; leasing application services). Management of the timelines and schedules occurring during the repack. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | No | |
For Auxiliary Facility | N/A | |
For Main Facility | N/A | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | No |
For Auxiliary Facility | N/A | |
For Main Facility | N/A | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | No | |
Additional Field Engineering Service | Yes | |
Number of Days | 5 | |
Justification | On-site installation, testing and proofs |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
Progress Reports |
Preparation and filing of quarterly FCC progress reports |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $109,355.00 | $28,950.00 | N/A | $0.00 | N/A |
Total for all systems | $457,492.22 | $288,430.22 | N/A | $0.00 | N/A |
Primary Transmitter NV8306 | $109,355.00 | $28,950.00 | $0.00 | ||
3 kW mask filter | $4,155.00 | $3,950.00 | N/A | N/A | N/A |
UHF and VHF - minor banding issues | $105,200.00 | $25,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $74,530.00 | $71,866.00 | N/A | $0.00 | N/A |
Total for all systems | $457,492.22 | $288,430.22 | N/A | $0.00 | N/A |
Primary Antenna TLP-12B | $74,530.00 | $71,866.00 | $0.00 | ||
Antenna Space Reservation | $32,000.00 | $32,000.00 | One-time fee charged by American Tower to reserve the new antenna space in addition to current antenna space during construction of new channel facilities. See attached American Tower term sheet. | N/A | N/A |
Dehydrator | $1,800.00 | $1,800.00 | N/A | N/A | N/A |
Antenna Space Rent | $7,700.00 | $7,700.00 | N/A | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
UHF - Lower Power Side Mount, Class A One Station antenna -- basic | $26,300.00 | $23,966.00 | See attached SJ Ramer Associates Quote for TLP12B Ch 23 with Standard Mounts | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,727.22 | $11,519.22 | N/A | $0.00 | N/A |
Total for all systems | $457,492.22 | $288,430.22 | N/A | $0.00 | N/A |
Primary Transmission Line | $1,727.22 | $11,519.22 | $0.00 | ||
7-8 and 1 5-8 Air Connector | $44.44 | $44.44 | See attached SJ Ramer Associates quote. | N/A | N/A |
Flexible Air Transmission Line - dielectric, 1 5/8" | $0.00 | $9,792.00 | See attached SJ Ramer Associates quote. New/longer transmission line required for installation of new antenna at height above current antenna (which will remain in operation until end of phase). See also Scope of Work from American Tower Term Sheet. | N/A | N/A |
Two 1 5-8 EIA Female Connectors | $751.82 | $751.82 | See attached SJ Ramer Associates quote. | N/A | N/A |
Transmission Line Installation Kit | $902.71 | $902.71 | See attached SJ Ramer Associates quote. | N/A | N/A |
Gas Pass Connector Conversion Kit | $28.25 | $28.25 | See attached SJ Ramer Associates quote. | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $93,600.00 | $89,400.00 | N/A | $0.00 | N/A |
Total for all systems | $457,492.22 | $288,430.22 | N/A | $0.00 | N/A |
Primary Tower LTOWER | $93,600.00 | $89,400.00 | $0.00 | ||
Ground and Building AandE Permit Drawing Package | $4,700.00 | $4,700.00 | N/A | N/A | N/A |
Short Tower (less than 500') | $84,200.00 | $80,000.00 | N/A | N/A | N/A |
Tower Permit Drawing Package | $4,700.00 | $4,700.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $125,450.00 | $38,830.00 | N/A | $0.00 | N/A |
Total for all systems | $457,492.22 | $288,430.22 | N/A | $0.00 | N/A |
Outside Professional Services | $125,450.00 | $38,830.00 | $0.00 | ||
Additional Field Engineering Service, 5 Days | $8,100.00 | $8,100.00 | N/A | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $5,000.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $3,500.00 | N/A | N/A | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $5,000.00 | Coordination required by American Tower. | N/A | N/A |
Project management of the transition | $15,010.00 | $9,480.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $52,830.00 | $47,865.00 | N/A | $0.00 | N/A |
Total for all systems | $457,492.22 | $288,430.22 | N/A | $0.00 | N/A |
Other Expenses | $52,830.00 | $47,865.00 | $0.00 | ||
Progress Reports | $8,000.00 | $8,000.00 | N/A | N/A | N/A |
Develop and air announcement of upcoming channel change | $12,000.00 | $12,000.00 | N/A | N/A | N/A |
Equipment Storage | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
Local Zoning | $750.00 | $750.00 | N/A | N/A | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $190.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $6,600.00 | N/A | N/A | N/A |
MVPD Notification of Channel Change | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $457,492.22 | $288,430.22 | $0.00 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Susan Sim Oh Managing Partner 08/28/2017 |