Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
SINCLAIR LAGRANDE LICENSEE, LLC Doing Business As: SINCLAIR LAGRANDE LICENSEE, LLC |
Harvey Arnold 10706 Beaver Dam Road Cockeysville, MD 21030 United States |
+1 (410) 568-1500 | FCCContacts@sbgtv.com | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Paul A. Cicelski , Esq. . Lerman Senter PLLC |
Paul A. Cicelski, Esq. 2001 L Street NW Suite 400 Washington, DC 20036 United States |
+1 (202) 416-6756 | sinclair399s@summitridgegroup.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Replace transmitter and Mask filter. Join a shared antenna system. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | SS-1 | |
Year | 2012 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 1 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | 8605 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 3.1 kW | |
Justification for New Transmitter | Transmitter is not supported. |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
Microwave Band Pass Filter |
Microwave Band Pass Filter |
Paraflector Feed Assembly |
Paraflector Feed Assembly |
Installation Services |
Installation Services |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | SWMP16OM | |
Year | 2006 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | Yes | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Broadband Panel | |
Number of Stations Supported | 4 | |
Number of Panels/Bays | 32 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 608.00 MHz | |
Design power capacity in use | 100.0 % | |
ERP: | 55.0 kW | |
Manufacturer | ||
Model | TUM-25-O4-8/32H-1-R-T | |
Year | 2019 | |
Justification for New Antenna | Current antenna is frequency specific and went to shared antenna with KOIN, KRCW, and KATU STA facilities. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Power Dividers | Does the panel antenna require power dividers? | No |
Cable Harness | Does the panel antenna require cable harness? | No |
Name | Description |
---|---|
Mask Filter |
Mask Filter |
Additional Equipment |
Additional Equipment |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Foam | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 365 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Segment Length | Broadband | |
Number of parallel runs | 1 | |
Length | 365 feet per run | |
Justification for New Transmission Line | Shared facilities with KOIN, KRCW, and KATU. | |
Interior RF Systems | Does the Installation of the Transmission Line require an additional or replacement Inside RF system including switching, patch panels, and dehydrators? | Yes |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Yes | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1035761 | |
Coordinates (NAD83) | Latitude (NAD83) | 45° 31' 13.0" N- |
Longitude (NAD83) | 122° 44' 41.0" W- | |
Overall Structure Height | 918.62 feet | |
Support Structure Height | 812.00 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 954.38 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Sinclair Portland Licensee, LLC | |
Date Constructed | 08/15/1973 |
Facility ID | Call Sign | Service |
---|---|---|
35380 | KOIN | DTV |
21649 | KATU | DTV |
10192 | KRCW-TV | DTV |
67878 | KEVE-LD | LPD |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | No study needed |
Tower Reinforcements | Please select whether tower reinforcements are needed: | No reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 255 | |
Explanation | Outside consulting engineering, legal work, and accounting services, as well as project management for regional and comprehensive repack execution. | |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Prepare Form 601 | Yes | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $142,866.23 | $142,866.23 | N/A | $36,566.23 | N/A |
Total for all systems | $464,339.96 | $253,596.45 | N/A | $124,865.47 | N/A |
Primary Transmitter 8605 | $142,866.23 | $142,866.23 | $36,566.23 | ||
Installation Services | $35,911.10 | $35,911.10 | N/A | $35,911.10 | N/A |
Paraflector Feed Assembly | $306.03 | $306.03 | N/A | $306.03 | N/A |
Microwave Band Pass Filter | $349.10 | $349.10 | N/A | $349.10 | N/A |
UHF - Air Cooled Solid State Transmitter 2.501 - 3.999 kW | $106,300.00 | $106,300.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Installation Services | |
Paraflector Feed Assembly | |
Microwave Band Pass Filter | |
UHF - Air Cooled Solid State Transmitter 2.501 - 3.999 kW | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $8,795.73 | $8,795.73 | N/A | $3,065.73 | N/A |
Total for all systems | $464,339.96 | $253,596.45 | N/A | $124,865.47 | N/A |
Primary Antenna TUM-25-O4-8/32H-1-R-T | $8,795.73 | $8,795.73 | $3,065.73 | ||
Additional Equipment | $990.03 | $990.03 | N/A | $990.03 | x |
UHF-Low Power, Top Mount, Broadband Panel, 32 bay, 55.0kW input, Elliptical | $0.00 | $0.00 | Shared antenna with 100% cost handled by the KATU repack reimbursement. | $0.00 | N/A |
Mask Filter | $2,075.70 | $2,075.70 | N/A | $2,075.70 | N/A |
Sweep test of transmission line and antenna | $5,730.00 | $5,730.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Additional Equipment | |
UHF-Low Power, Top Mount, Broadband Panel, 32 bay, 55.0kW input, Elliptical | Information not provided. |
Mask Filter | |
Sweep test of transmission line and antenna | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $77,197.50 | $1,885.08 | N/A | $1,885.08 | N/A |
Total for all systems | $464,339.96 | $253,596.45 | N/A | $124,865.47 | N/A |
Primary Transmission Line | $77,197.50 | $1,885.08 | $1,885.08 | ||
Interior RF Systems: Inside RF system including switching, patch panels and dehydrators | $0.00 | $0.00 | Shared combiner with 100% of cost handled by the KATU repack reimbursement. | N/A | N/A |
Rigid Transmission Line - copper, 6 1/8" broadband | $77,197.50 | $1,885.08 | N/A | $1,885.08 | N/A |
Actual Information Description | File Name |
---|---|
Interior RF Systems: Inside RF system including switching, patch panels and dehydrators | Information not provided. |
Rigid Transmission Line - copper, 6 1/8" broadband |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $157,750.00 | $22,368.00 | N/A | $22,368.00 | N/A |
Total for all systems | $464,339.96 | $253,596.45 | N/A | $124,865.47 | N/A |
Primary Tower TOWER | $157,750.00 | $22,368.00 | $22,368.00 | ||
Tower Rigging Tall Tower (greater than 500') | $157,750.00 | $22,368.00 | N/A | $22,368.00 | N/A |
Actual Information Description | File Name |
---|---|
Tower Rigging Tall Tower (greater than 500') |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $45,702.50 | $45,653.41 | N/A | $28,952.43 | N/A |
Total for all systems | $464,339.96 | $253,596.45 | N/A | $124,865.47 | N/A |
Outside Professional Services | $45,702.50 | $45,653.41 | $28,952.43 | ||
Attorney Fees - Prepare and File request for Special Temporary Authorization | $2,235.00 | $2,235.00 | N/A | N/A | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $3,262.50 | $3,262.50 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | N/A | N/A |
Prepare Form 601 | $755.00 | $755.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,425.00 | See invoices. | $1,425.00 | N/A |
Perform engineering study for displacement application | $1,800.00 | $1,800.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | $1,068.75 | N/A |
Prepare request for Special Temporary Authorization | $1,280.00 | $1,280.00 | N/A | N/A | N/A |
Project management of the transition | $26,902.50 | $26,480.91 | N/A | $26,458.68 | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,710.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Attorney Fees - Prepare and File request for Special Temporary Authorization | Information not provided. |
Attorney Fees - Negotiation of lease and other matters for shared locations | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare Form 601 | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Perform engineering study for displacement application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Prepare request for Special Temporary Authorization | Information not provided. |
Project management of the transition | |
Prepare/ Review 399 reimbursement form | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $32,028.00 | $32,028.00 | N/A | $32,028.00 | N/A |
Total for all systems | $464,339.96 | $253,596.45 | N/A | $124,865.47 | N/A |
Other Expenses | $32,028.00 | $32,028.00 | $32,028.00 | ||
Disposal Costs (for equipment and other waste, net of any salvage value) | $32,028.00 | $32,028.00 | N/A | $32,028.00 | N/A |
Actual Information Description | File Name |
---|---|
Disposal Costs (for equipment and other waste, net of any salvage value) |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $464,339.96 | $253,596.45 | $124,865.47 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | Yes |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lucy Rutishauser CFO 02/02/2023 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lucy Rutishauser CFO 02/02/2023 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lucy Rutishauser CFO 02/02/2023 |