Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
WTVH LICENSE LLC Doing Business As: WTVH LICENSE LLC |
Carl S. Lane GRANITE BROADCASTING LLC 2700 Patriot Boulevard, Suite 250 Glenview, IL 60026 United States |
+1 (312) 953-3880 | carllane@granitetv.com | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Paul A. Cicelski , Esq . Lerman Senter PLLC |
2001 L Street NW Suite 400 Washington, DC 20036 United States |
+1 (202) 416-6756 | pcicelski@lermansenter.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | See Exhibit A. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | Sigma | |
Year | 2003 | |
Type | Inductive Output Tube | |
IOT Power Type | Single | |
Power Capacity | 30 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | THU9evo-36 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 55 kW | |
Justification for New Transmitter | Per the manufacturer, the current transmitter cannot be retuned. See Exhibit B. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 300 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 2 inches | |
Length | 800.0 feet | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Heat Exchanger |
Heat Exchanger |
Installation |
Installation |
Additional Equipment |
Additional Equipment |
Additional Site Requirements |
Additional Site Requirements |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 500.0 kW | |
Manufacturer | ||
Model | TFU-30GTH-R O4 | |
Year | 2003 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 274.0 kW | |
Manufacturer | ||
Model | ANT TFU-32JH/VP-R O6 | |
Year | 2017 | |
Justification for New Antenna | Current antenna is a single channel antenna that cannot be used for the post-auction channel. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 6 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Name | Description |
---|---|
Antenna Support Pole |
Antenna Support Pole |
Wedding Cake Mounting Adapter |
Wedding Cake Mounting Adapter |
Redesign and optimization of antenna input |
Redesign and optimization of antenna input |
Additional parts |
Additional parts |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 612 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 19 3/4 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 970 feet per run | |
Justification for New Transmission Line | The existing line could not be used. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | No | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1003682 | |
Coordinates (NAD83) | Latitude (NAD83) | 42° 57' 19.0" N- |
Longitude (NAD83) | 076° 06' 33.0" W- | |
Overall Structure Height | 556.10 feet | |
Support Structure Height | 479.98 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 1359.89 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | WTVH, LLC | |
Date Constructed | 01/30/2004 |
Users |
---|
Amateur Repeat |
Bush electronic |
AMR Metro Amb |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for undocumented/poorly documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Major Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 550 | |
Explanation | Outside consulting engineering, legal work, and accounting services, as well as project management for regional and comprehensive repack execution. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
NEPA Section 106 environmental review | Yes | |
Environmental Assessment | Yes | |
ASR Modification | Yes | |
FAA Consultation (including preparation of FAA Form 7460) | Yes | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | No | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
Sinclair Internal Costs |
Internal Employee Time Costs |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
True-up |
True-up |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $2,178,962.44 | $818,249.94 | N/A | $825,399.54 | N/A |
Total for all systems | $3,908,849.77 | $2,713,617.78 | N/A | $2,103,383.73 | N/A |
Primary Transmitter THU9evo-36 | $2,178,962.44 | $818,249.94 | $825,399.54 | ||
Additional Site Requirements | $91,368.00 | $91,368.00 | N/A | $169,817.60 | The invoice with status Need More Information can be removed. An updated version has been submitted. |
Additional Equipment | $15,926.53 | $15,926.53 | N/A | $15,926.53 | The need more information can be deleted. |
Installation | $186,267.91 | $186,267.91 | N/A | $186,267.91 | The need more information can be removed. |
Heat Exchanger | $1,600.00 | $1,600.00 | N/A | $1,600.00 | N/A |
2" Rigid Conduit and Wiring (Cost per foot) | $20,800.00 | $23,700.00 | See Caryl Electric Co. quote | $23,700.00 | N/A |
Transformer 3 phase/480v - 300 KVA | $36,800.00 | $35,000.00 | N/A | N/A | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $36,300.00 | N/A | N/A | N/A |
UHF - Liquid Cooled Solid State Transmitter 52 - 61 kW | $1,788,000.00 | $428,087.50 | N/A | $428,087.50 | N/A |
Actual Information Description | File Name |
---|---|
Additional Site Requirements | |
Additional Equipment | |
Installation | |
Heat Exchanger | |
2" Rigid Conduit and Wiring (Cost per foot) | |
Transformer 3 phase/480v - 300 KVA | Information not provided. |
Switchgear - industrial 800 amp | Information not provided. |
UHF - Liquid Cooled Solid State Transmitter 52 - 61 kW |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $443,911.59 | $393,031.76 | N/A | $368,193.51 | N/A |
Total for all systems | $3,908,849.77 | $2,713,617.78 | N/A | $2,103,383.73 | N/A |
Primary Antenna ANT TFU-32JH/VP-R O6 | $443,911.59 | $393,031.76 | $368,193.51 | ||
Redesign and optimization of antenna input | $3,709.80 | $3,709.80 | N/A | $3,709.80 | The version of invoice #839003 with status Need More Information can be removed. A revised version has been uploaded. |
Wedding Cake Mounting Adapter | $41,297.86 | $41,297.86 | N/A | $41,297.86 | N/A |
Antenna Support Pole | $85,077.16 | $85,077.16 | N/A | $85,077.16 | N/A |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | $12,300.00 | $37,741.47 | See Dielectric quote | $12,903.22 | N/A |
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized | $289,500.00 | $208,183.90 | See Response to August 4 Inquiry. | $208,183.90 | N/A |
Additional parts | $5,296.77 | $5,296.77 | N/A | $5,296.77 | N/A |
Sweep test of existing antenna | $6,730.00 | $11,724.80 | Two sweep tests were necessary. | $11,724.80 | N/A |
Actual Information Description | File Name |
---|---|
Redesign and optimization of antenna input | |
Wedding Cake Mounting Adapter | |
Antenna Support Pole | |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | |
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized | |
Additional parts | |
Sweep test of existing antenna |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $195,940.00 | $150,160.33 | N/A | $150,160.33 | N/A |
Total for all systems | $3,908,849.77 | $2,713,617.78 | N/A | $2,103,383.73 | N/A |
Primary Transmission Line | $195,940.00 | $150,160.33 | $150,160.33 | ||
Rigid Transmission Line - copper, 6 1/8" | $195,940.00 | $150,160.33 | N/A | $150,160.33 | Invoice #839003 with status Need More Information can be removed. A revised version has been uploaded. |
Actual Information Description | File Name |
---|---|
Rigid Transmission Line - copper, 6 1/8" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $657,800.00 | $935,929.80 | N/A | $643,729.80 | N/A |
Total for all systems | $3,908,849.77 | $2,713,617.78 | N/A | $2,103,383.73 | N/A |
Primary Tower TOWER | $657,800.00 | $935,929.80 | $643,729.80 | ||
Major tower reinforcement/modifications | $421,000.00 | $400,000.00 | N/A | $107,800.00 | N/A |
Tall Tower (greater than 500') | $210,500.00 | $504,201.00 | See FDH quote. | $504,201.00 | N/A |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study | $26,300.00 | $31,728.80 | See FDH quotes. | $31,728.80 | N/A |
Actual Information Description | File Name |
---|---|
Major tower reinforcement/modifications | |
Tall Tower (greater than 500') | |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $233,661.68 | $218,221.89 | N/A | $140,419.48 | N/A |
Total for all systems | $3,908,849.77 | $2,713,617.78 | N/A | $2,103,383.73 | N/A |
Outside Professional Services | $233,661.68 | $218,221.89 | $140,419.48 | ||
ASR modification (prepare FCC Form 854) | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | $10,520.00 | $10,000.00 | N/A | N/A | N/A |
NEPA Section 106 environmental review, if needed | $6,310.00 | $6,000.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $7,360.00 | $0.00 | N/A | N/A | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $4,210.00 | $0.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $0.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $221.92 | N/A | $221.92 | N/A |
Prepare request for Special Temporary Authorization | $4,100.00 | $3,000.00 | N/A | $1,567.50 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | $712.50 | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $8,988.75 | Please see Carl T. Jones invoices. | $8,988.75 | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $16,346.25 | See Carl T. Jones invoices. | $16,346.25 | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $3,200.00 | Updated cost of estimated amount per FCC requirement. | $3,117.59 | N/A |
Sinclair Internal Costs | $871.68 | $871.68 | N/A | $871.68 | X |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $80,000.00 | N/A | $27,000.00 | N/A |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
Project management of the transition | $86,900.00 | $81,593.29 | Please see SRG and Lerman Senter invoices. | $81,593.29 | x |
Actual Information Description | File Name |
---|---|
ASR modification (prepare FCC Form 854) | Information not provided. |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | Information not provided. |
NEPA Section 106 environmental review, if needed | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | Information not provided. |
Attorney Fees - Negotiation of lease and other matters for shared locations | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
Prepare request for Special Temporary Authorization | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Perform engineering study for new channel assignment and antenna development | |
Address transition timing and coordination issues w/ other stations and wireless | Information not provided. |
Prepare and or review reimbursement form | |
Sinclair Internal Costs | |
Comprehensive coverage verification via field study, if needed | |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | Information not provided. |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $198,574.06 | $198,024.06 | N/A | ($24,518.93) | N/A |
Total for all systems | $3,908,849.77 | $2,713,617.78 | N/A | $2,103,383.73 | N/A |
Other Expenses | $198,574.06 | $198,024.06 | ($24,518.93) | ||
MVPD Notification of Channel Change | $5,000.00 | $5,000.00 | See Exhibit J. | N/A | N/A |
Develop and air announcement of upcoming channel change | $75,000.00 | $75,000.00 | See Response to August 4 Inquiry. | N/A | N/A |
Equipment Storage | $29,526.68 | $29,526.68 | See Exhibit J. | $29,526.68 | N/A |
Equipment Delivery and Handling Charges | $18,931.38 | $18,931.38 | See Exhibit J. | $18,931.38 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $28,566.00 | $28,566.00 | See Response to August 4 Inquiry. | $10,632.98 | N/A |
Non-zoning permits | $10,000.00 | $10,000.00 | See Exhibit J. | N/A | N/A |
Local Zoning | $20,000.00 | $20,000.00 | See Exhibit J. | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | $5,900.00 | N/A |
True-up | $0.00 | $0.00 | N/A | ($89,509.97) | N/A |
Actual Information Description | File Name |
---|---|
MVPD Notification of Channel Change | Information not provided. |
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Storage | |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | |
Non-zoning permits | Information not provided. |
Local Zoning | Information not provided. |
DTV Medical Facility Notification | |
True-up |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $3,908,849.77 | $2,713,617.78 | $2,103,383.73 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | Yes |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lawrence Wills Vice President 12/15/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lawrence Wills Vice President 12/15/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lawrence Wills Vice President 12/15/2022 |