Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
MOHAVE COUNTY BOARD OF SUPERVISORS Applicant Doing Business As: MOHAVE COUNTY BOARD OF SUPERVISORS |
Barbara Spoonhour PO BOX 7000 KINGMAN, AZ 86402 United States |
+1 (928) 753-0729 | spoonb@mohave.gov | Other |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
The Preparer is same as the reimbursement contact. |
|
|
|
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | Transition complete required based on T-Mobile/FCC Repackaging |
Question | Response |
---|---|
Sharee Station Facility ID | 43413 |
Call Sign | K28PO-D |
Type | |
Licensee Name | MOHAVE COUNTY BOARD OF SUPERVISORS |
Status | LICENSED |
DTS | No |
Community of License | LAKE HAVASU CITY, AZ |
Pre-auction RF Channel | 28 |
Post-auction RF Channel | |
Neilsen DMA | |
Network Affiliation |
Question | Response |
---|---|
Sharee Station Facility ID | 43402 |
Call Sign | K24NG-D |
Type | |
Licensee Name | MOHAVE COUNTY BOARD OF SUPERVISORS |
Status | LICENSED |
DTS | No |
Community of License | LAKE HAVASU CITY, AZ |
Pre-auction RF Channel | 24 |
Post-auction RF Channel | |
Neilsen DMA | |
Network Affiliation |
Question | Response |
---|---|
Sharee Station Facility ID | 43371 |
Call Sign | K22NK-D |
Type | |
Licensee Name | MOHAVE COUNTY BOARD OF SUPERVISORS |
Status | LICENSED |
DTS | No |
Community of License | LAKE HAVASU CITY, AZ |
Pre-auction RF Channel | 22 |
Post-auction RF Channel | |
Neilsen DMA | |
Network Affiliation |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | PA-140 UHF | |
Year | 2019 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 140 W |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | TRN-5X-1-U-C | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 140 W | |
Justification for New Transmitter | To facilitate T-Mobile/FCC Repackaging |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | Yes | |
Size | 1 inches | |
Length | 26.0 feet | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Top Mount | |
Antenna position in stack | Top | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels | 4 | |
Design power capacity in use | 25.0 % | |
Lower Limit | 542.00 MHz | |
Upper Limit | 548.00 MHz | |
ERP: | 200.0 W | |
Manufacturer | ||
Model | 4DR-4S | |
Year | 2019 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Top Mount | |
Antenna position in stack | Top | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels/Bays | 4 | |
Lower Limit | 542.00 MHz | |
Upper Limit | 548.00 MHz | |
Design power capacity in use | 25.0 % | |
ERP: | 100.0 W | |
Manufacturer | ||
Model | 4DR-4S | |
Year | 2019 | |
Justification for New Antenna | Existing antenna system cannot be modified or re-tuned. Requires specific build to match frequency. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | No |
Power Dividers | Does the panel antenna require power dividers? | Yes |
Number of Power Dividers | 1 | |
Cable Harness | Does the panel antenna require cable harness? | No |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | No |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | No | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Name | Description |
---|---|
Construction |
Actual |
Staff expenses |
6 hours at 63.90 |
Technical staff expense |
2 hours at 40.00 |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $15,625.00 | $11,710.80 | N/A | $11,710.80 | N/A |
Total for all systems | $38,151.93 | $25,209.82 | N/A | $25,209.82 | N/A |
Primary Transmitter TRN-5X-1-U-C | $15,625.00 | $11,710.80 | $11,710.80 | ||
1" Rigid Conduit and Wiring | $1,875.00 | $1,875.00 | The actual cost was higher than the original estimated cost. | $1,875.00 | The actual cost for rewiring was higher than the original estimate. |
UHF - Air Cooled Solid State Transmitter 50.001 - 150 Watts | $13,750.00 | $9,835.80 | Actual | $9,835.80 | Uploaded corrected invoice and memo to answer FCC questions. 3/18/22: Uploaded corrected invoice and memo. |
Actual Information Description | File Name |
---|---|
1" Rigid Conduit and Wiring | |
UHF - Air Cooled Solid State Transmitter 50.001 - 150 Watts |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $8,300.00 | $5,654.51 | N/A | $5,654.51 | N/A |
Total for all systems | $38,151.93 | $25,209.82 | N/A | $25,209.82 | N/A |
Primary Antenna 4DR-4S | $8,300.00 | $5,654.51 | $5,654.51 | ||
UHF Broadband panel antenna (per panel), horizontally-polarized | $7,000.00 | $4,871.46 | The original estimate did not include the sales tax that was erroneously missing from WECOM Invoice 150491. The estimate also did not include the purchase of band pas filters. | $4,871.46 | 03/17/22: Updated invoices 70 and 150491 for antenna and jumper purchase only. |
Power Dividers (each, for panel antenna system, if not included in antenna cost) | $1,300.00 | $783.05 | Actual costs. This is the cost for the power divider and the sales tax that was erroneously excluded (invoice 70) from invoice 150491. | $783.05 | 03/17/22: Uploaded invoices 70 and 150491 for purchase and sales tax of divider. 3/18/22: Uploaded additional information for invoices 70 and 150491. 05/09/22: Uploaded memo for invoice 150491. |
Actual Information Description | File Name |
---|---|
UHF Broadband panel antenna (per panel), horizontally-polarized | |
Power Dividers (each, for panel antenna system, if not included in antenna cost) |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $9,557.50 | $3,175.08 | N/A | $3,175.08 | N/A |
Total for all systems | $38,151.93 | $25,209.82 | N/A | $25,209.82 | N/A |
Outside Professional Services | $9,557.50 | $3,175.08 | $3,175.08 | ||
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $890.36 | The actual costs were higher than the estimated amount. | $890.36 | The actual costs were higher than the original estimate. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $0.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $2,284.72 | Actual | $2,284.72 | The estimated amount and the actuals are the same. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $0.00 | N/A | N/A | N/A |
Perform engineering study for displacement application | $1,800.00 | $0.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for displacement application | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $4,669.43 | $4,669.43 | N/A | $4,669.43 | N/A |
Total for all systems | $38,151.93 | $25,209.82 | N/A | $25,209.82 | N/A |
Other Expenses | $4,669.43 | $4,669.43 | $4,669.43 | ||
Technical staff expense | $60.43 | $60.43 | Actual | $60.43 | Estimated cost changed to actual cost per Myrna's email. |
Staff expenses | $529.00 | $529.00 | The actual staff time cost was higher than the original estimate. | $529.00 | Corrected invoice and memo uploaded. |
Construction | $4,080.00 | $4,080.00 | Actual | $4,080.00 | N/A |
Actual Information Description | File Name |
---|---|
Technical staff expense | |
Staff expenses | |
Construction |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $38,151.93 | $25,209.82 | $25,209.82 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | Yes |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Barbara Jo Spoonhour Administrative Services Director 08/22/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Barbara Jo Spoonhour Administrative Services Director 08/22/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Barbara J Spoonhour Administrative Services Director 08/22/2022 |