Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
VENTANA TELEVISION, INC. |
Eric Yonkin 1 HSN Drive St. Petersburg, FL 33729 United States |
+1 (727) 872-7443 | EASnotice@hsn.net | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Ari Q. Fitzgerald Hogan Lovells US LLP |
555 Thirteenth Street, NW Washington, DC 20004 United States |
+1 (202) 637-2257 | ari.fitzgerald@hoganlovells.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Station must receive and install a new transmitter and antenna. A study is necessary for the tower. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | TXUP-2500 | |
Year | 2010 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 0.8 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | EC702HP-BB | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 1.5 kW | |
Justification for New Transmitter | The lower channel required fewer bays to fit antenna aperture and required higher TPO. |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | Yes | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | PSILP16OI-39 | |
Year | 2010 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | SFN-2030-5600-10 E/P | |
Year | 2020 | |
Justification for New Antenna | New antenna lower gain/less bays due to length for lower channel. Requires higher TPO. Previous channel 39 antenna would not work on channel 30. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | No |
Name | Description |
---|---|
Invoice No. 0030125 Tower Systems South, REPLACE 50 ROOF TOP ANTENNA Order No. HN813151339 |
Invoice No. 0030125 Tower Systems South, REPLACE 50 ROOF TOP ANTENNA Order No. HN813151339 |
Invoice No. C2223-A Microtenixx - SFN-2030-5600-10 |
Invoice No. C2223-A Microtenixx - SFN-2030-5600-10 |
Invoice No. C2223-B Micronetixx - SFN-2030-5600-10 |
Invoice No. C2223-B Micronetixx - SFN-2030-5600-10 |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Ownership | Owned | |
Is this tower consider Complex? | Located on Building | |
Is this tower currently shared with any other stations? | No | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
Coordinates (NAD83) | Latitude (NAD83) | 30° 19' 33.8" N- |
Longitude (NAD83) | 081° 39' 32.2" W- | |
Overall Structure Height | 630.00 feet | |
Support Structure Height | 521.00 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 6.00 feet | |
Structure Type | BTWR - Building with Tower | |
Tower Owner | Ventana Television, Inc. | |
Date Constructed | 05/20/2011 |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Tower mapping and report for structural engineer |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Serious Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Located on Building |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
To Be Determined |
Study and necessary modifications remain to be determined. |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | No |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | No |
Prepare engineering section of Form FCC Construction Permit Application | No | |
Prepare engineering section of Form FCC License to Cover Application | No | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | No |
Prepare and file Form FCC License to Cover Application | No | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | Yes | |
Number of Days | 5 | |
Justification | The station requires a comprehensive coverage verification via field study to confirm that the station's post repack coverage is accurate. The station will be contracting a third party that performs field studies with the use of unmanned aerial vehicles. |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $94,000.00 | $94,000.00 | N/A | $55,254.98 | N/A |
Total for all systems | $304,177.20 | $270,602.20 | N/A | $91,187.18 | N/A |
Primary Transmitter EC702HP-BB | $94,000.00 | $94,000.00 | $55,254.98 | ||
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | $84,000.00 | $84,000.00 | N/A | $52,554.98 | N/A |
Transmitter Building Site Survey/Installation | $10,000.00 | $10,000.00 | N/A | $2,700.00 | N/A |
Actual Information Description | File Name |
---|---|
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | |
Transmitter Building Site Survey/Installation |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $60,679.59 | $60,679.59 | N/A | $35,679.59 | N/A |
Total for all systems | $304,177.20 | $270,602.20 | N/A | $91,187.18 | N/A |
Primary Antenna SFN-2030-5600-10 E/P | $60,679.59 | $60,679.59 | $35,679.59 | ||
Invoice No. C2223-B Micronetixx - SFN-2030-5600-10 | $16,235.95 | $16,235.95 | N/A | $16,235.95 | N/A |
Invoice No. C2223-A Microtenixx - SFN-2030-5600-10 | $15,750.00 | $15,750.00 | N/A | $15,750.00 | N/A |
Invoice No. 0030125 Tower Systems South, REPLACE 50 ROOF TOP ANTENNA Order No. HN813151339 | $3,693.64 | $3,693.64 | N/A | $3,693.64 | N/A |
UHF-Low Power, Side Mount, Slotted Coaxial, 15.0kW input, Elliptical | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Invoice No. C2223-B Micronetixx - SFN-2030-5600-10 | |
Invoice No. C2223-A Microtenixx - SFN-2030-5600-10 | |
Invoice No. 0030125 Tower Systems South, REPLACE 50 ROOF TOP ANTENNA Order No. HN813151339 | |
UHF-Low Power, Side Mount, Slotted Coaxial, 15.0kW input, Elliptical | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $71,000.00 | $71,000.00 | N/A | $0.00 | N/A |
Total for all systems | $304,177.20 | $270,602.20 | N/A | $91,187.18 | N/A |
Primary Tower BTWR | $71,000.00 | $71,000.00 | $0.00 | ||
Tower mapping and report for structural engineer | $21,000.00 | $21,000.00 | N/A | N/A | N/A |
Complex Tower (includes, e.g., towers with candelabras and/or stacked antennas) | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
To Be Determined | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Serious tower reinforcement/modifications | $15,000.00 | $15,000.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $77,910.00 | $44,335.00 | N/A | $0.00 | N/A |
Total for all systems | $304,177.20 | $270,602.20 | N/A | $91,187.18 | N/A |
Outside Professional Services | $77,910.00 | $44,335.00 | $0.00 | ||
Additional Field Engineering Service, 5 Days | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
RF Exposure Measurements | $12,100.00 | $6,000.00 | N/A | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $52,600.00 | $25,125.00 | N/A | N/A | N/A |
Form 399 assistance or other Program Management costs | $1,500.00 | $1,500.00 | N/A | N/A | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,710.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $587.61 | $587.61 | N/A | $252.61 | N/A |
Total for all systems | $304,177.20 | $270,602.20 | N/A | $91,187.18 | N/A |
Other Expenses | $587.61 | $587.61 | $252.61 | ||
Equipment Delivery and Handling Charges | $252.61 | $252.61 | N/A | $252.61 | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Equipment Delivery and Handling Charges | |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $304,177.20 | $270,602.20 | $91,187.18 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | Yes |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Eric Yonkin Associate General Counsel, Legal 09/06/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Eric Yonkin Associate General Counsel, Legal 09/06/2022 |