Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
Gray Television Licensee, LLC |
4370 Peachtree Road, NE Atlanta, GA 30319 United States |
+1 (404) 266-3888 | allfcclms@gray.tv | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Samuel Hariton Widelity |
4031 University Drive Suite 100 Fairfax, VA 22030 United States |
+1 (339) 222-8107 | sam.hariton@widelity.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | Due to non-supported translator we purchased a new translator and installation. A new filter comber was required and shared at the site. Some additional support equipment was required to control the new system. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | MXD30U-T79540 | |
Year | 2010 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 24 W |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | UAXTE-50 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 50 W | |
Justification for New Transmitter | translator no longer supported |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
Two sencore receivers |
These are receivers for use with the transmitter |
Surge Suppressor |
Used with transmitter for power protection |
Primary Transmitter - Additional Pieces |
Primary Transmitter - Additional Pieces |
Pre Filter cable Kit |
RF connection between transmitter and bandpass filter |
Post Fliter cable kit |
RF combiner for connection post bandpass filter |
Tax |
Tax on Transmitter |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | No |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Utilize Existing |
Use | Primary (Main) | |
Ownership | Owned | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | Andrews |
Type | Flexible Foam | |
Diameter | 7/8 inches | |
Number of parallel runs | 1 | |
Length | 75 feet per run |
Name | Description |
---|---|
Combiner |
A new combiner was required and is shared with two other translators |
L4A cable assembly |
Jumper cable from transmitter to Combiner |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 100 | |
Explanation | K18NA-D does not have sufficient resource capacity and expertise in house to handle all activities necessary for completion of the station's build by the construction deadline. K18NA-D will hire an outside firm to facilitate a timely transition | |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | No | |
Form 399 assistance or other program management costs | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $16,827.73 | $14,019.73 | N/A | $14,019.73 | N/A |
Total for all systems | $46,716.27 | $44,199.67 | N/A | $34,192.22 | N/A |
Primary Transmitter UAXTE-50 | $16,827.73 | $14,019.73 | $14,019.73 | ||
Surge Suppressor | $1,624.01 | $1,624.01 | N/A | $1,624.01 | N/A |
Post Fliter cable kit | $361.25 | $361.25 | N/A | $361.25 | N/A |
Pre Filter cable Kit | $289.00 | $289.00 | N/A | $289.00 | N/A |
Tax | $1,049.91 | $1,049.91 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $1,049.91 | N/A |
UHF - Air Cooled Solid State Transmitter 5 - 50 Watts | $10,200.00 | $7,392.00 | Please see K18NA-D GatesAir, Inc. Quote Q-77968 | $7,392.00 | N/A |
Two sencore receivers | $3,060.00 | $3,060.00 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $3,060.00 | N/A |
Primary Transmitter - Additional Pieces | $243.56 | $243.56 | Please see GatesAir Quote #Q-77968 & Invoice #US0320539 | $243.56 | N/A |
Actual Information Description | File Name |
---|---|
Surge Suppressor | |
Post Fliter cable kit | |
Pre Filter cable Kit | |
Tax | |
UHF - Air Cooled Solid State Transmitter 5 - 50 Watts | |
Two sencore receivers | |
Primary Transmitter - Additional Pieces |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $3,683.54 | $3,683.54 | N/A | $3,628.59 | N/A |
Total for all systems | $46,716.27 | $44,199.67 | N/A | $34,192.22 | N/A |
Primary Transmission Line | $3,683.54 | $3,683.54 | $3,628.59 | ||
Combiner | $3,628.59 | $3,628.59 | N/A | $3,628.59 | N/A |
L4A cable assembly | $54.95 | $54.95 | N/A | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
Combiner | |
L4A cable assembly | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $24,370.00 | $24,661.40 | N/A | $15,373.90 | N/A |
Total for all systems | $46,716.27 | $44,199.67 | N/A | $34,192.22 | N/A |
Outside Professional Services | $24,370.00 | $24,661.40 | $15,373.90 | ||
Attorney Fees - Negotiation of lease and other matters for shared locations | $3,262.50 | $120.00 | Please see K18NA-D Attorney Other Matters Budget Revision Justification Letter. The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $120.00 | N/A |
Perform engineering study for displacement application | $1,800.00 | $1,800.00 | N/A | $1,000.00 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | $270.00 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | N/A | N/A |
Form 399 assistance or other Program Management costs | $1,000.00 | $1,000.00 | N/A | N/A | N/A |
Project management of the transition | $10,550.00 | $13,983.90 | Please see K18NA-D Project Management Budget Revision Justification Letter. The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $13,983.90 | N/A |
Actual Information Description | File Name |
---|---|
Attorney Fees - Negotiation of lease and other matters for shared locations | |
Perform engineering study for displacement application | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Form 399 assistance or other Program Management costs | Information not provided. |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,835.00 | $1,835.00 | N/A | $1,170.00 | N/A |
Total for all systems | $46,716.27 | $44,199.67 | N/A | $34,192.22 | N/A |
Other Expenses | $1,835.00 | $1,835.00 | $1,170.00 | ||
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | $170.00 | N/A |
Equipment Delivery and Handling Charges | $1,500.00 | $1,500.00 | N/A | $1,000.00 | N/A |
Actual Information Description | File Name |
---|---|
FCC Filing Fees - Form 2100 license to cover application | |
Equipment Delivery and Handling Charges |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $46,716.27 | $44,199.67 | $34,192.22 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Robert Folliard , III . Assistant Secretary 08/17/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Robert Folliard , III . Assistant Secretary 08/17/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Robert Folliard , III . Assistant Secretary 08/17/2022 |