Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
FIRST UNITED, INC. Doing Business As: FIRST UNITED, INC. |
Joseph Stroud PO Box 5257 Oak Brook OAK BROOK, IL 60522 United States |
+1 (708) 633-0001 | josephstroud@me.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Samuel Hariton Widelity |
4031 University Drive Ste. 100 Fairfax, VA 22030 United States |
+1 (339) 222-8107 | sam.hariton@widelity.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | Facilities listed above are co-located on Willis Tower west antenna structures with WEDE-CD. WEDE-CD transitions to new channel through antenna replacement, retune of existing transmitter, and installation of new mask filter. Existing line remains. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Retune Existing |
Use | Primary (Main) | |
Ownership | Owned | |
Owner | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | Harris |
Model | UAX-500A7 | |
Year | 2013 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 0.5 kW |
Section | Question | Response |
---|---|---|
New IOT Tubes | Number of Tubes (including accessories) needed | N/A |
New Mask Filter | ||
Power | 1.5 kW | |
Other Power | N/A | |
New Exciter | Is a new exciter needed? | No |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Other | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | Single Channel Panel Array | |
ERP: | 4.3 kW | |
Manufacturer | ||
Model | 9552312 | |
Year | 2004 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Other | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | Single Channel Panel Array | |
ERP: | 2.84 kW | |
Manufacturer | ||
Model | TUA-C2-2/4-1 Kit | |
Year | 2017 | |
Justification for New Antenna | Existing antenna exhibits undesirable VSWR at repack channel, and does not replicate existing pattern. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Name | Description |
---|---|
Antenna delivery to Willis Tower |
Delivery of antenna from installer facility to Willis Tower, and rooftop staging. |
Antenna reassembly on Willis Rooftop |
Assembly of antenna on Willis Tower rooftop. |
Antenna handling and storage |
Receiving, handling, and storage of antenna at installer facility. |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Utilize Existing |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | Andrew |
Type | Flexible Air | |
Diameter | 1 5/8 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 250 feet per run |
Name | Description |
---|---|
Transmission line routing change |
Labor for minor adjustment in transmission line routing due to required antenna replacement. |
Transmission line routing change material |
Connector kit an mounting hardware for relocation of existing transmission line due to antenna change. |
Primary Transmission Line - Other Expenses - Dehydrator |
Primary Transmission Line - Other Expenses - Dehydrator |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | Located on Building | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1032959 | |
Coordinates (NAD83) | Latitude (NAD83) | 41° 52' 44.1" N- |
Longitude (NAD83) | 087° 38' 10.2" W- | |
Overall Structure Height | 1729.97 feet | |
Support Structure Height | 1435.35 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 595.14 feet | |
Structure Type | BTWR - Building with Tower | |
Tower Owner | 233 Broadcast, LLC | |
Date Constructed | 01/01/2002 |
Facility ID | Call Sign | Service |
---|---|---|
9613 | WBBM-FM | FM |
72115 | WGN-TV | DTV |
9617 | WBBM-TV | DTV |
28621 | WJMK | FM |
71428 | WCIU-TV | DTV |
47905 | WMAQ-TV | DTV |
22211 | WFLD | DTV |
168662 | WMEU-CD | DTV |
71425 | WWME-CD | DTV |
70119 | WSNS-TV | DTV |
10802 | WTTW | DTV |
10801 | WFMT | FM |
48772 | WPWR-TV | DTV |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Minor Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Located on Building |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 595 | |
Explanation | WEDE-CD does not have sufficient resource capacity and expertise in house to handle all of the reimbursement filing, expense tracking, vendor coordination, progress reporting, budget creation, budget review, budget tracking, daisy-chain monitoring, et al. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | Yes | |
Additional Field Engineering Service | Yes | |
Number of Days | 2 | |
Justification | These field engineering costs were necessary to complete the installation of the new primary antenna during the repack. |
Name | Description |
---|---|
Required Willis Tower RF Safety Coordination |
Required RF safety coordination during antenna change. |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $108,230.00 | $52,800.00 | N/A | $0.00 | N/A |
Total for all systems | $1,003,411.30 | $642,296.40 | N/A | $256,391.86 | N/A |
Primary Transmitter UAX-500A7 | $108,230.00 | $52,800.00 | $0.00 | ||
UHF and VHF - minor banding issues | $105,200.00 | $50,000.00 | N/A | N/A | N/A |
1.5 kW mask filter | $3,030.00 | $2,800.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $50,530.00 | $48,900.00 | N/A | $17,687.26 | N/A |
Total for all systems | $1,003,411.30 | $642,296.40 | N/A | $256,391.86 | N/A |
Primary Antenna TUA-C2-2/4-1 Kit | $50,530.00 | $48,900.00 | $17,687.26 | ||
Antenna reassembly on Willis Rooftop | $5,000.00 | $5,000.00 | Reassembly of antenna on rooftop in preparation for installation. | N/A | N/A |
Antenna delivery to Willis Tower | $10,000.00 | $10,000.00 | Delivery of antenna from installation contractor facility to Willis Tower. Includes shipping to Willis Tower from contractor yard, unloading antenna at dock, and transport to rooftop of building. After hours work due to size and elevators. | $4,125.50 | N/A |
Antenna handling and storage | $2,500.00 | $2,500.00 | Receiving and handling of antenna at installation contractor facility. Includes material storage fees. | N/A | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | $6,400.00 | N/A |
UHF - Lower Power Side Mount, Class A One Station antenna -- basic | $26,300.00 | $25,000.00 | N/A | $7,161.76 | N/A |
Actual Information Description | File Name |
---|---|
Antenna reassembly on Willis Rooftop | Information not provided. |
Antenna delivery to Willis Tower | |
Antenna handling and storage | Information not provided. |
Sweep test of existing antenna | |
UHF - Lower Power Side Mount, Class A One Station antenna -- basic |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $7,741.30 | $7,741.30 | N/A | $1,891.30 | N/A |
Total for all systems | $1,003,411.30 | $642,296.40 | N/A | $256,391.86 | N/A |
Primary Transmission Line | $7,741.30 | $7,741.30 | $1,891.30 | ||
Primary Transmission Line - Other Expenses - Dehydrator | $1,741.30 | $1,741.30 | Please see WEDE-CD Primary Transmission Line Dehydrator Budget Revision Justification Letter | $1,741.30 | N/A |
Transmission line routing change material | $2,000.00 | $2,000.00 | Cable refit kits and connectors,and other hardware for transmission line relocation due to new antenna installation. | N/A | N/A |
Transmission line routing change | $4,000.00 | $4,000.00 | Labor for rerouting of existing transmission line due to antenna change. | $150.00 | N/A |
Actual Information Description | File Name |
---|---|
Primary Transmission Line - Other Expenses - Dehydrator | |
Transmission line routing change material | Information not provided. |
Transmission line routing change |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $591,600.00 | $260,465.35 | N/A | $110,465.35 | N/A |
Total for all systems | $1,003,411.30 | $642,296.40 | N/A | $256,391.86 | N/A |
Primary Tower BTWR | $591,600.00 | $260,465.35 | $110,465.35 | ||
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $95,402.85 | Please see Estimated Cost Justification WEDE-CD-410-Existing Primary Tower - Tower Rigging, Complex Tower V0 | $95,402.85 | N/A |
Structural engineering tower load study for well documented tower | $12,600.00 | $15,062.50 | Please See Estimated Cost Justification WEDE-CD-410-Existing Primary Tower - Tower Load Study, Documented Tower v0 | $15,062.50 | N/A |
Minor tower reinforcement/modifications | $158,000.00 | $150,000.00 | Cost expected to include design and fabrication of modified antenna mounting brackets for west bridge location. | N/A | N/A |
Actual Information Description | File Name |
---|---|
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | |
Structural engineering tower load study for well documented tower | |
Minor tower reinforcement/modifications | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $160,120.00 | $187,794.75 | N/A | $116,147.95 | N/A |
Total for all systems | $1,003,411.30 | $642,296.40 | N/A | $256,391.86 | N/A |
Outside Professional Services | $160,120.00 | $187,794.75 | $116,147.95 | ||
Attorney Fees - Negotiation of lease and other matters for shared locations | $4,210.00 | $24,869.25 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $24,869.25 | N/A |
Required Willis Tower RF Safety Coordination | $9,440.00 | $9,440.00 | Cost assumes four nights of work, plus related expenses, per diem, and mileage. | N/A | N/A |
Additional Field Engineering Service, 2 Days | $2,750.00 | $2,750.00 | Please see WEDE-CD Additional Field Engineering Service Budget Revision Justification Letter | $2,750.00 | N/A |
RF Exposure Measurements | $21,050.00 | $12,500.00 | Required RFR survey of Willis Tower rooftops following antenna change. | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $3,680.00 | $3,142.00 | Please see WEDE Attorney - STA Revision Justification Cover Letter. The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $3,142.00 | see submitted invoices |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $16,668.50 | Per Estimated Cost Justification WEDE-CD-550-Attorney - Construction Permit Application v0 | $16,054.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | $706.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | $4,112.50 | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | $282.50 | N/A |
Project management of the transition | $94,010.00 | $99,675.00 | Per Widelity Strategic Support Quote | $64,231.70 | N/A |
Actual Information Description | File Name |
---|---|
Attorney Fees - Negotiation of lease and other matters for shared locations | |
Required Willis Tower RF Safety Coordination | Information not provided. |
Additional Field Engineering Service, 2 Days | |
RF Exposure Measurements | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | |
Address transition timing and coordination issues w/ other stations and wireless | Information not provided. |
Prepare and or review reimbursement form | |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $85,190.00 | $84,595.00 | N/A | $10,200.00 | N/A |
Total for all systems | $1,003,411.30 | $642,296.40 | N/A | $256,391.86 | N/A |
Other Expenses | $85,190.00 | $84,595.00 | $10,200.00 | ||
MVPD Notification of Channel Change | $5,000.00 | $5,000.00 | N/A | $3,000.00 | N/A |
Develop and air announcement of upcoming channel change | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $30,000.00 | $30,000.00 | Based on delivery and staging of equipment, and subsequent transfer to Willis Tower from installation contractor. | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $30,000.00 | $30,000.00 | Removal of old antenna and associated material from Willis Tower. | $2,000.00 | N/A |
Non-zoning permits | $2,000.00 | $2,000.00 | City of Chicago permitting | N/A | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $200.00 | Please see attached combined document for Cooley Invoice 2115254. | $200.00 | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,070.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | $5,000.00 | N/A |
Actual Information Description | File Name |
---|---|
MVPD Notification of Channel Change | |
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Delivery and Handling Charges | Information not provided. |
Disposal Costs (for equipment and other waste, net of any salvage value) | |
Non-zoning permits | Information not provided. |
FCC Filing Fees - Special Temporary Authorization request | |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
FCC Filing Fees - Form 2100 minor change CP application | Information not provided. |
DTV Medical Facility Notification |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $1,003,411.30 | $642,296.40 | $256,391.86 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Joseph Stroud President 07/22/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Joseph Stroud President 07/22/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Joseph Stroud President 07/22/2022 |