Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
SCRIPPS BROADCASTING HOLDINGS LLC |
David Giles 312 WALNUT STREET 28TH FLOOR CINCINNATI, OH 45202 United States |
+1 (513) 977-3000 | DAVE.GILES@SCRIPPS.COM | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Sam Hariton Widelity |
Sam Hariton 4031 University Dr Suite 100 Fairfax, VA 22030 United States |
+1 (339) 222-8107 | sam.hariton@widelity.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | KZSD is planning to purchase all new equipment, but remain on the same tower. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | SS2000-UT | |
Year | 2004 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 1.27 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | UAXTE-3R37 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 1.8 kW | |
Justification for New Transmitter | Re-tuning the existing main transmitter is not an option because the current transmitter is not frequency agile and does not contain a digital modulator. |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | Yes | |
Description | Breaker Expansion and relocation | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
Primary Transmitter Installation |
Primary Transmitter Installation |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels | 6 | |
Design power capacity in use | 15.9 % | |
Lower Limit | 470.00 MHz | |
Upper Limit | 862.00 MHz | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | 75010210 | |
Year | 2018 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels/Bays | 1 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 862.00 MHz | |
Design power capacity in use | 62.5 % | |
ERP: | 7.3 kW | |
Manufacturer | ||
Model | 75010210 | |
Year | 2018 | |
Justification for New Antenna | New antenna needed to fit the station's contour map given their new transmitter TPO and desired antenna gain. Needed to run in parallel for several weeks during installation and channel coordination. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Power Dividers | Does the panel antenna require power dividers? | No |
Cable Harness | Does the panel antenna require cable harness? | No |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Foam | |
Diameter | Other | |
Other Diameter | 2 1/4 inches | |
Number of parallel runs | 1 | |
Length | 150 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Flexible Foam | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 150 feet per run | |
Justification for New Transmission Line | The station needs to construct the new digital channel 20 facility and operate both the existing and new channels in parallel for several weeks during installation and channel coordination. | |
Interior RF Systems | Does the Installation of the Transmission Line require an additional or replacement Inside RF system including switching, patch panels, and dehydrators? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Yes | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1011527 | |
Coordinates (NAD83) | Latitude (NAD83) | 32° 41' 47.0" N- |
Longitude (NAD83) | 116° 56' 10.0" W- | |
Overall Structure Height | 223.75 feet | |
Support Structure Height | 149.93 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 2562.96 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | KSWB, LLC | |
Date Constructed | 05/16/1984 |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | No study needed |
Tower Reinforcements | Please select whether tower reinforcements are needed: | No reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 254 | |
Explanation | KZSD does not have sufficient resource capacity and expertise in house to handle all of the reimbursement activities necessary to facility on-time completion of the station's build. As such, KZSD will hire an outside firm to support KZSD in these tasks. | |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Prepare Form 601 | Yes | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | Yes |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $120,462.00 | $98,772.89 | N/A | $86,130.89 | N/A |
Total for all systems | $236,776.50 | $184,025.98 | N/A | $132,309.78 | N/A |
Primary Transmitter UAXTE-3R37 | $120,462.00 | $98,772.89 | $86,130.89 | ||
Primary Transmitter Installation | $12,000.00 | $12,000.00 | Please see KZSD-LD Wireless Infrastructure Services proposal dated 10/3/18 | $12,000.00 | N/A |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | $84,000.00 | $62,310.89 | Please see GatesAir Quote #Q-77079 & Invoice #US0320775 | $62,310.89 | N/A |
Other Electrical Service: Breaker Expansion and relocation | $24,462.00 | $24,462.00 | Per Wireless Infrastructure Services quote dated 9/11/18. Because of repack requirements, KZSD is moving from an analog to a digital transmitter, necessitating these electrical expenses. | $11,820.00 | N/A |
Actual Information Description | File Name |
---|---|
Primary Transmitter Installation | |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | |
Other Electrical Service: Breaker Expansion and relocation |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $7,480.00 | $1,570.29 | N/A | $1,570.29 | N/A |
Total for all systems | $236,776.50 | $184,025.98 | N/A | $132,309.78 | N/A |
Primary Antenna 75010210 | $7,480.00 | $1,570.29 | $1,570.29 | ||
Sweep test of transmission line and antenna | $5,730.00 | $800.00 | Please see Sweep Test and Installation Breakdown and Wireless Infrastructure Services KZSD CH 20 system Installation Proposal Rev. 1 | $800.00 | N/A |
UHF Broadband panel antenna (per panel), horizontally-polarized | $1,750.00 | $770.29 | see Estimated Cost Justification KZSD-LD-210-Primary Antenna - UHF Broadband Panel, H-POL v0 | $770.29 | N/A |
Actual Information Description | File Name |
---|---|
Sweep test of transmission line and antenna | |
UHF Broadband panel antenna (per panel), horizontally-polarized |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $3,600.00 | $3,600.00 | N/A | $0.00 | N/A |
Total for all systems | $236,776.50 | $184,025.98 | N/A | $132,309.78 | N/A |
Primary Transmission Line | $3,600.00 | $3,600.00 | $0.00 | ||
Flexible Foam Transmission Line - dielectric, 1 5/8" | $3,600.00 | $3,600.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $56,190.00 | $15,600.00 | N/A | $15,600.00 | N/A |
Total for all systems | $236,776.50 | $184,025.98 | N/A | $132,309.78 | N/A |
Primary Tower TOWER | $56,190.00 | $15,600.00 | $15,600.00 | ||
Tower Rigging Short Tower (less than 500') | $56,190.00 | $15,600.00 | Please see KZSD-LD Wireless Infrastructure Services KZSD CH 20 system Installation Proposal Rev. 1 and Sweep Test and Installation Breakdown | $15,600.00 | N/A |
Actual Information Description | File Name |
---|---|
Tower Rigging Short Tower (less than 500') |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $42,334.50 | $57,877.80 | N/A | $28,638.60 | N/A |
Total for all systems | $236,776.50 | $184,025.98 | N/A | $132,309.78 | N/A |
Outside Professional Services | $42,334.50 | $57,877.80 | $28,638.60 | ||
Attorney Fees - Prepare and File request for Special Temporary Authorization | $2,235.00 | $2,482.80 | Please see KZSD-LD Attorney STA Budget Justification Letter. The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $2,482.80 | N/A |
Prepare Form 601 | $755.00 | $755.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $1,280.00 | $525.00 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $525.00 | N/A |
Perform engineering study for displacement application | $1,800.00 | $2,737.50 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $2,737.50 | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,710.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | $112.50 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | N/A | N/A |
Project management of the transition | $26,797.00 | $41,910.00 | Please see KZSD-LD-LPTV strategic support quote.pdf | $22,780.80 | N/A |
Actual Information Description | File Name |
---|---|
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Prepare Form 601 | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare request for Special Temporary Authorization | |
Perform engineering study for displacement application | |
Prepare/ Review 399 reimbursement form | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $6,710.00 | $6,605.00 | N/A | $370.00 | N/A |
Total for all systems | $236,776.50 | $184,025.98 | N/A | $132,309.78 | N/A |
Other Expenses | $6,710.00 | $6,605.00 | $370.00 | ||
FCC Filing Fees - Special Temporary Authorization request | $305.00 | $200.00 | Please see KZSD-LD FCC Filing Fee ENG STA Revision Justification Cover Letter | $200.00 | N/A |
FCC Filing Fees - Form 2100 Major change CP application | $4,960.00 | $4,960.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | $170.00 | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,110.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
FCC Filing Fees - Special Temporary Authorization request | |
FCC Filing Fees - Form 2100 Major change CP application | Information not provided. |
FCC Filing Fees - Form 2100 license to cover application | |
FCC Filing Fees - Form 2100 minor change CP application | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $236,776.50 | $184,025.98 | $132,309.78 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Sravan Reddy Senior Director, General Accounting 07/19/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Sravan Reddy Senior Director, General Accounting 07/19/2022 |