Go to the Federal Communications Commission homepage at www.fcc.gov

FCC Form 399: Reimbursement Request

Approved by OMB 3060-1178
Go to the Federal Communications Commission homepage at www.fcc.gov

(REFERENCE COPY - Not for submission) FCC Form 399: Reimbursement Request

Facility ID:
62219
Service:
DTV
Call Sign:
WYDC
Channel:
30 (UHF)
File Number:
0000027884
FRN:
0031173065
Date Submitted:
03/21/2022

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

CTNY License LLC

2750 Luberon Lane

Cumming, GA 30041

United States

+1 (678) 777-8659 bfielder@youralaskalink.com Limited Liability Company

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

The Preparer is same as the reimbursement contact.

 

 

 

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan Changing channels per FCC repack plan from 48 to 30 Replacing transmitter. Need for new temporary antenna/line to stay on air during shared antenna transition (diff. phase). Tower needs reinforcement.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Auxiliary Transmitter

Back to Top

Add Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Auxiliary (Backup)
Description of Use Auxiliary
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model 840A
Year 2005
Type Solid State
Solid State Cooling Air Cooled
Solid State Power Capacity 1.4 kW

Auxiliary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Auxiliary (Backup)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model TMU9evo-6
Transmitter Type Solid State
Solid State Cooling Air Cooled
Solid State Power capacity 6 kW
Justification for New Transmitter Existing transmitter cannot be retuned from channel 48 to channel 30

Auxiliary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring Yes
Size 3 inches
Length 20.0 feet
Other Electrical Service No
Description N/A
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Auxiliary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model 840B
Year 2004
Type Solid State
Solid State Cooling Air Cooled
Solid State Power Capacity 3 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model THU9evo-3
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 4.9 kW
Justification for New Transmitter Currently in wrong band and not retunable

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) Yes
Power 150 kVA
Rigid Conduit and Wiring Yes
Size 3 inches
Length 90.0 feet
Other Electrical Service Yes
Description Tower Electrical Connections.
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Lease New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Leased
Owner WSKA
Site N/A
Is the existing antenna shared with another station or stations? Yes
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? Yes
Existing Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Panel
Number of Stations Supported 3
Number of Panels 28
Design power capacity in use 31.0 %
Lower Limit 535.00 MHz
Upper Limit 700.00 MHz
Other Antenna Type N/A
ERP: 7.0 kW
Manufacturer
Model TUA-C4SP-8 28M-1-T
Year 2006

Facility ID's and Call Signs of all stations with whom the antenna is shared.

Facility ID Call Sign
78908 WSKA
71508 WENY-TV

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Lease New
Is this a request for upgraded equipment? Yes
Ownership Leased
Owner wska
Is antenna shared? Yes
Is antenna directional? No
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Types Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Slot
Number of Stations Supported 3
Number of Panels/Bays 16
Lower Limit 470.00 MHz
Upper Limit 698.00 MHz
Design power capacity in use 80.0 %
Other Antenna Type N/A
ERP: 150.0 kW
Manufacturer
Model TFU-8WB-1-R C160
Year 2006
Justification for New Antenna To handle timing differences resulting from phase difference among tenants sharing the antenna.

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? Yes
Type New
Number of channels supported 3
Frequencies of channels supported Upper and lower frequency
Frequency 535.0 MHz - 690.0 MHz
Do you need a combiner output splitter/switcher for dual feed lines? No
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? Broadband
Feed Line Size 4 1/16 inches inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna?
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? Yes
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Interim Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Interim
Description of Use N/A
Change Type Purchase New
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? No
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Type Class Full Power
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Circular
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 100.0 kW
Manufacturer
Model TLP-BB-24B/VP-R
Year 2017
Justification for New Antenna Temporary antenna for use during transition. 3 antenna partners all have to change channels and current antenna is directional, limiting new channels. Transition phases are not the same. This will be built prior to first transition phase for seamlessness.

Interim Antenna

Back to Top

Other Antenna Costs

Section Question Response
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? B
Feed Line Size 4 1/16 inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for an antenna? Yes
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? Yes
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Interim Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Interim Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Interim
Description of Use N/A
Change Type Purchase New
Type Rigid
Diameter 4 1/16 inches
Segment Length 20'
Other Segment Length
Number of parallel runs 1
Length 950 feet per run
Justification for New Transmission Line interim line

Interim Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Information not provided.

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Description of Use N/A
Ownership Leased
Is this tower consider Complex? No
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users No
Is tower documented for structural analysis? Yes
Is tower compliant with Rev G? No
Existing Tower Structure Registration Do you have a tower registration number? No
ASR Number
Coordinates (NAD83) Latitude (NAD83) 42° 08' 31.2" N-
Longitude (NAD83) 077° 04' 38.8" W-
Overall Structure Height 800.52 feet
Support Structure Height 800.52 feet
Ground Elevation Above Mean Sea Level (AMSL) 1679.77 feet
Structure Type TOWER - Free Standing or Guyed Structure
Tower Owner GRI Telecom, Inc
Date Constructed 08/27/2006

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
71508 WENY-TV DTV
78908 WSKA DTV

Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for documented tower
Tower Reinforcements Please select whether tower reinforcements are needed: Minor Reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower N/A
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Information not provided.

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 695
Explanation Tower mods, coordinate shared antenna issues & 399 preparation
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
NEPA Section 106 environmental review Yes
Environmental Assessment Yes
ASR Modification Yes
FAA Consultation (including preparation of FAA Form 7460) Yes
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements Yes
Additional Field Engineering Service No
Number of Days N/A
Justification N/A

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Information not provided.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning Yes
Non-zoning permits Yes
BLM or NFS Coordination Yes
FCC Construction Permit Minor Change Yes
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? No
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? No
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? Yes
Does this relocation require MVPD Notification of a Channel Change? Yes

Other Expenses

Back to Top

Other Expenses Not Listed

Information not provided.

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $550,170.00 $311,293.80 N/A $162,522.93 N/A
Total for all systems $1,610,460.00 $1,257,521.23 N/A $751,616.78 N/A
Primary Transmitter THU9evo-3 $312,630.00 $227,944.04 $162,522.93
Other Electrical Service: Tower Electrical Connections. $8,900.00 $8,900.00 Please see John Mills Electric Quote dated 9-10-19 $8,900.00 N/A
3" Rigid Conduit and Wiring (Cost per foot) $4,680.00 $4,410.00 N/A $0.00 N/A
Transformer 3 phase/480v - 150 KVA $25,550.00 $3,312.50 Please see document "WYDC Justification Rohde & Schwarz Documentation" for supporting information. Also of note: LMS will not allow for a 30KVA transformer, so the smallest option available in LMS was selected (150KVA) $3,312.49 N/A
UHF - Liquid Cooled Solid State Transmitter 4.9 . 6.5 kW $273,500.00 $211,321.54 Please see attached Rohde & Schwarz Quote #181827.0 $150,310.44 N/A
Auxiliary Transmitter TMU9evo-6 $237,540.00 $83,349.76 $0.00
3" Rigid Conduit and Wiring (Cost per foot) $1,040.00 $980.00 N/A N/A N/A
UHF - Air Cooled Solid State Transmitter 4 - 6 kW $236,500.00 $82,369.76 Please see attached WYDC CH30 TMU9evo-6 Sales Quote 188852 $0.00 N/A

Components

Actual Information Description File Name
Other Electrical Service: Tower Electrical Connections.

Component Description:
ELECTRICAL WORK FOR TV TOWER UPGRADES
Amount:
$8,900.00
3" Rigid Conduit and Wiring (Cost per foot) Information not provided.
Transformer 3 phase/480v - 150 KVA

Component Description:
WYDC-1st Primary Transmitter - 3 Phase, 480 V, 150 KVA Transformer
Amount:
$828.12

Component Description:
WYDC-110-1st Primary Transmitter - 3 Phase, 480 V, 150 KVA Transformer
Amount:
$2,484.37
UHF - Liquid Cooled Solid State Transmitter 4.9 . 6.5 kW

Component Description:
75% Downpayment Quote 181727.0 WYDC CH30 THU9evo-3 Transmitter System
Amount:
$112,732.83

Component Description:
DP 25% Downpayment R&S Quote #181827.0 Quote 181827.0 WYDC CH30 THU9evo-3 Transmitter System
Amount:
$37,577.61
3" Rigid Conduit and Wiring (Cost per foot) Information not provided.
UHF - Air Cooled Solid State Transmitter 4 - 6 kW

Component Description:
WYDC CH 30 TMU9evo-6 Transmitter system
Amount:
$64,349.52

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $256,330.00 $162,532.43 N/A $44,808.25 N/A
Total for all systems $1,610,460.00 $1,257,521.23 N/A $751,616.78 N/A
Interim Antenna TLP-BB-24B/VP-R $149,190.00 $124,124.18 $6,400.00
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) $5,260.00 $5,000.00 N/A N/A N/A
Side mount brackets for high power antennas (if not included in antenna base cost) $23,150.00 $22,000.00 N/A $0.00 N/A
Elbow complex, broadband, at antenna input, per 4 1/16. feedline (if needed) $10,950.00 $10,400.00 N/A N/A N/A
Sweep test of existing antenna $6,730.00 $6,400.00 N/A $6,400.00 N/A
UHF - Lower Power Side Mount, One Station antenna . medium power (50-200 kW), elliptically or circularly polarized $103,100.00 $80,324.18 Please see the attached Dielectric invoice # MAN01014 $0.00 N/A
Primary Antenna TFU-8WB-1-R C160 $107,140.00 $38,408.25 $38,408.25
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) $5,260.00 $0.00 covered in WSKA app N/A N/A
New combiner, cost per channel (without antenna) $84,200.00 $38,408.25 Please see Estimated Cost Justification WYDC-210-Primary Antenna - New Combiner v0 $38,408.25 N/A
Elbow complex, broadband, at antenna input, per 4 1/16. feedline (if needed) $10,950.00 $0.00 N/A N/A N/A
Sweep test of existing antenna $6,730.00 $0.00 N/A N/A N/A
UHF - High Power Top Mount Three Station antenna horizontally polarized $0.00 $0.00 provided in WSKA app N/A N/A

Components

Actual Information Description File Name
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) Information not provided.
Side mount brackets for high power antennas (if not included in antenna base cost)

Component Description:
Please deny this invoice. This has been replaced with invoice MAN01014-2.
Amount:
N/A
Elbow complex, broadband, at antenna input, per 4 1/16. feedline (if needed) Information not provided.
Sweep test of existing antenna

Component Description:
REPACK SWEEP
Amount:
$6,400.00

Component Description:
Please deny this invoice. This has been replaced with invoice MAN01014-2.
Amount:
N/A
UHF - Lower Power Side Mount, One Station antenna . medium power (50-200 kW), elliptically or circularly polarized

Component Description:
Please deny this invoice. This has been replaced with invoice MAN01014-2.
Amount:
N/A
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) Information not provided.
New combiner, cost per channel (without antenna)

Component Description:
COMBINERS FOR SHARED (BROADBAND PANEL) ANTENNA
Amount:
$35,112.00

Component Description:
OTHER FREIGHT AND SHIPPING
Amount:
$3,296.25
Elbow complex, broadband, at antenna input, per 4 1/16. feedline (if needed) Information not provided.
Sweep test of existing antenna Information not provided.
UHF - High Power Top Mount Three Station antenna horizontally polarized Information not provided.

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $134,900.00 $128,250.00 N/A $88,108.45 N/A
Total for all systems $1,610,460.00 $1,257,521.23 N/A $751,616.78 N/A
Interim Transmission Line $134,900.00 $128,250.00 $88,108.45
Rigid Transmission Line - copper, 4 1/16" $134,900.00 $128,250.00 Please see quote 800130CMZ-2 $88,108.45 N/A

Components

Actual Information Description File Name
Rigid Transmission Line - copper, 4 1/16"

Component Description:
ANTENNA UHF SIDE MOUNT
Amount:
$37,957.72

Component Description:
OTHER FREIGHT AND SHIPPING
Amount:
$3,296.25

Component Description:
RIGID TRANSMISSION LINE - COPPer 4-1/16" EIA - 855 FT
Amount:
$46,665.37

Component Description:
OTHER FREIGHT AND SHIPPING
Amount:
$189.11

Component Description:
Please deny this invoice. This has been replaced with invoice MAN01014-2.
Amount:
N/A

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $381,100.00 $394,250.00 N/A $350,125.00 N/A
Total for all systems $1,610,460.00 $1,257,521.23 N/A $751,616.78 N/A
Primary Tower TOWER $381,100.00 $394,250.00 $350,125.00
Minor tower reinforcement/modifications $158,000.00 $150,000.00 N/A $110,000.00 N/A
Structural engineering tower load study for well documented tower $12,600.00 $12,000.00 N/A $7,875.00 N/A
Tall Tower (greater than 500') $210,500.00 $232,250.00 See Estimated Cost Justification WYDC-410-Existing Primary Tower - Tower Rigging, Tall Tower V0 $232,250.00 N/A

Components

Actual Information Description File Name
Minor tower reinforcement/modifications

Component Description:
6 ft Face Guyed Tower Reinforcing & Antenna & At/L Modification Project
Amount:
$88,000.00

Component Description:
6 ft Face Guyed Tower Reinforcing & Antenna
Amount:
$22,000.00
Structural engineering tower load study for well documented tower

Component Description:
Structural Analysis for load case Specified.
Amount:
$7,875.00
Tall Tower (greater than 500')

Component Description:
WYDC-410-Existing Primary Tower - Tower Rigging, Tall Tower
Amount:
$37,300.00

Component Description:
WYDC-410-Existing Primary Tower - Tower Rigging, Tall Tower
Amount:
$149,200.00

Component Description:
Installed antenna and feed lines leading from shelter to antenna.
Amount:
$37,500.00

Component Description:
6 ft Face Guyed Tower Reinforcing & Antenna & T/L
Amount:
$8,250.00

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $271,020.00 $245,920.00 N/A $105,717.15 N/A
Total for all systems $1,610,460.00 $1,257,521.23 N/A $751,616.78 N/A
Outside Professional Services $271,020.00 $245,920.00 $105,717.15
RF Exposure Measurements $21,050.00 $20,000.00 N/A $7,800.00 N/A
Comprehensive coverage verification via field study, if needed $84,200.00 $80,000.00 N/A N/A N/A
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase $2,105.00 $0.00 N/A N/A N/A
ASR modification (prepare FCC Form 854) $2,105.00 $0.00 N/A N/A N/A
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet $10,520.00 $10,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A $720.00 N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $3,000.00 N/A N/A N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $7,000.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $2,250.00 N/A $420.00 N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $4,210.00 $4,000.00 N/A $840.00 N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $3,680.00 $3,500.00 N/A $120.00 N/A
NEPA Section 106 environmental review, if needed $6,310.00 $6,000.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $5,000.00 N/A $675.00 N/A
Prepare request for Special Temporary Authorization $2,050.00 $1,920.00 The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. $0.00 N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A N/A N/A
Prepare and or review reimbursement form $2,630.00 $2,500.00 N/A $1,125.00 N/A
Project management of the transition $109,810.00 $96,750.00 N/A $94,017.15 N/A

Components

Actual Information Description File Name
RF Exposure Measurements

Component Description:
RF exposure measurements, post repack RF environment profile safety and health assessment and signage
Amount:
$7,800.00
Comprehensive coverage verification via field study, if needed Information not provided.
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase Information not provided.
ASR modification (prepare FCC Form 854) Information not provided.
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application

Component Description:
Preparation of an Application for License to cover maximization construction permit.
Amount:
$720.00
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application Information not provided.
Perform engineering study for new channel assignment and antenna development Information not provided.
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application

Component Description:
WYDC-550-Attorney - License to Cover Application (Main)
Amount:
$420.00
Attorney Fees - Negotiation of lease and other matters for shared locations

Component Description:
Professional Services
Amount:
$60.00

Component Description:
Professional Services
Amount:
$180.00

Component Description:
WYDC-550-Attorney - Negotiation of Lease and Other Matters
Amount:
$150.00

Component Description:
Professional Services
Amount:
$90.00

Component Description:
Professional Services
Amount:
$150.00

Component Description:
Professional Services
Amount:
$210.00
Attorney Fees - Prepare and File request for Special Temporary Authorization

Component Description:
Professional Services
Amount:
$120.00
NEPA Section 106 environmental review, if needed Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application

Component Description:
WYDC-550-Attorney - Construction Permit Application (Main)
Amount:
$615.00

Component Description:
WYDC-550-Attorney - Construction Permit Application (Main)
Amount:
$60.00
Prepare request for Special Temporary Authorization

Component Description:
Performance of technical studies to determine the maximum allowable radiated power level and the associated coverage,
Amount:
$1,920.00
Address transition timing and coordination issues w/ other stations and wireless Information not provided.
Prepare and or review reimbursement form

Component Description:
WYDC-590-Prepare and/or Review Reimbursement Form
Amount:
$60.00

Component Description:
Professional Services
Amount:
$1,065.00
Project management of the transition

Component Description:
Project Management
Amount:
$99.00

Component Description:
Project Management
Amount:
$465.00

Component Description:
Project Management
Amount:
$77.50

Component Description:
Project Management
Amount:
$26.35

Component Description:
Project Management
Amount:
$2,047.90

Component Description:
Project Management
Amount:
$230.95

Component Description:
Project Management
Amount:
$542.50

Component Description:
Project Management
Amount:
$232.50

Component Description:
Project Management
Amount:
$11,211.25

Component Description:
Project Management
Amount:
$220.10

Component Description:
Project Management
Amount:
$1,474.05

Component Description:
Project Management
Amount:
$542.50

Component Description:
Project Management
Amount:
$1,858.55

Component Description:
Project Management
Amount:
$2,988.45

Component Description:
Project Management
Amount:
$3,825.15

Component Description:
Project Management
Amount:
$1,060.20

Component Description:
Project Management
Amount:
$4,681.20

Component Description:
Project Management
Amount:
$3,994.20

Component Description:
Project Management
Amount:
$6,447.70

Component Description:
Project management
Amount:
$127.50

Component Description:
Project Management
Amount:
$3,093.10

Component Description:
Project Management
Amount:
$2,790.55

Component Description:
Project Management
Amount:
$2,204.65

Component Description:
Project Management
Amount:
$7,138.60

Component Description:
Project Management
Amount:
$82.50

Component Description:
Project Management
Amount:
$75.00

Component Description:
Project Management
Amount:
$69.35

Component Description:
Project Management
Amount:
$6,035.20

Component Description:
Project Management
Amount:
$3,616.70

Component Description:
Project Management
Amount:
$3,599.45

Component Description:
Project Management
Amount:
$5,881.25

Component Description:
Project Management
Amount:
$4,756.85

Component Description:
Project Management
Amount:
$1,927.50

Component Description:
Project Management
Amount:
$1,213.55

Component Description:
Project Management
Amount:
$2,700.15

Component Description:
Project Management
Amount:
$1,908.40

Component Description:
Project Management
Amount:
$2,495.15

Component Description:
Project Management
Amount:
$2,276.65

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $16,940.00 $15,275.00 N/A $335.00 N/A
Total for all systems $1,610,460.00 $1,257,521.23 N/A $751,616.78 N/A
Other Expenses $16,940.00 $15,275.00 $335.00
DTV Medical Facility Notification $11,550.00 $11,000.00 N/A N/A N/A
BLM or NFS Coordination $0.00 $0.00 N/A N/A N/A
Non-zoning permits $0.00 $0.00 N/A N/A N/A
FCC Filing Fees - Special Temporary Authorization request $195.00 $190.00 N/A N/A N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $335.00 Please see WYDC Smithwick and Belendiuk Invoice 13299 $335.00 N/A
Local Zoning $0.00 $0.00 N/A N/A N/A
FCC Filing Fees - Form 2100 minor change CP application $1,110.00 $0.00 N/A N/A N/A
Equipment Delivery and Handling Charges $3,500.00 $3,500.00 N/A N/A N/A
Develop and air announcement of upcoming channel change $200.00 $200.00 N/A N/A N/A
MVPD Notification of Channel Change $50.00 $50.00 N/A N/A N/A

Components

Actual Information Description File Name
DTV Medical Facility Notification Information not provided.
BLM or NFS Coordination Information not provided.
Non-zoning permits Information not provided.
FCC Filing Fees - Special Temporary Authorization request Information not provided.
FCC Filing Fees - Form 2100 license to cover application

Component Description:
WYDC-610-FCC Filing Fee - License to Cover Application
Amount:
$335.00
Local Zoning Information not provided.
FCC Filing Fees - Form 2100 minor change CP application Information not provided.
Equipment Delivery and Handling Charges Information not provided.
Develop and air announcement of upcoming channel change Information not provided.
MVPD Notification of Channel Change Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $1,610,460.00 $1,257,521.23 $751,616.78

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. Yes
Construction of final facilities or all necessary modifications are complete. Yes
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. Yes

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

William J Christian

CEO


03/21/2022

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

William J Christian

CEO


03/21/2022

Certification

Back to Top
Section Question Response
Submission of Final Allocation or Accounting Information Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  2. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  3. The above-named entity certifies that all costs identified as "actual costs" herein accurately represent the costs actually paid by the above-named entity, including any discounts, refunds, or rebates.

  4. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  5. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  6. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

William J Christian

ceo


03/21/2022

Attachments

Back to Top