Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
Estrella Television License LLC |
1845 EMPIRE AVENUE BURBANK, CA 91504 United States |
+1 (818) 729-5300 | chrisb@lbimedia.com | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Samuel Hariton Widelity, Inc. |
4031 University Drive Fairfax, VA 22030 United States |
+1 (339) 222-8107 | sam.hariton@widelity.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | The plan is for KETD to replace the existing channel 45 system with a new channel 15 antenna, new 3-1/8" line and new transmitter. KETD will need to use an interim antenna and line in order to facilitate transition. See attached narrative statement. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | UAX-4000AT | |
Year | 2011 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 4.2 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | ULXTE-16 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 10.8 kW | |
Justification for New Transmitter | Retuning requires replacing the mask filter and extensive testing. This cannot be completed in an overnight maintenance and would result in a prolonged outage. An interim transmitter would be needed during this time to ensure continuous broadcast. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | Yes | |
Power | 150 kVA | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | Yes | |
Description | The new main transmitter will require reconfiguration of the electrical service on site. The electrical work cost has been estimated based on verbal guidance from local electrical contractors. | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 10 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
4 Port Switch |
A 4 port switch is necessary to allow switching from the interim antenna to the new main antenna. |
Internal Transmission Line |
Internal Transmission Line |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 100.0 kW | |
Manufacturer | ||
Model | AL12M-45-PM | |
Year | 2011 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 200.0 kW | |
Manufacturer | ||
Model | TFU-12DSB-F/VP | |
Year | 2017 | |
Justification for New Antenna | The existing antenna is not capable of supporting the new channel and will need to be replaced. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Broadband | |
Feed Line Size | 3 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Air | |
Diameter | 3 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 100 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Flexible Air | |
Diameter | 3 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 100 feet per run | |
Justification for New Transmission Line | New primary antenna will be placed at the same height but on opposite side of tower from existing main. This tower is shared so the station's placement is constrained by the tower owner. |
Name | Description |
---|---|
Dehydrator |
R46345 Dehydrator 200C |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | Terrain Constrained | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1023484 | |
Coordinates (NAD83) | Latitude (NAD83) | 39° 40' 17.4" N- |
Longitude (NAD83) | 105° 13' 08.0" W- | |
Overall Structure Height | 273.95 feet | |
Support Structure Height | 271.98 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 7685.60 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Bear Creek Development Corporation | |
Date Constructed | 11/08/1988 |
Facility ID | Call Sign | Service |
---|---|---|
57219 | KCEC | DTV |
14040 | KRMA-TV | DTV |
26929 | KQMT | FM |
35574 | KQKS | FM |
Users |
---|
West Metro Fire |
Police |
City Denver |
Civil Air Ptrl |
County Denver |
Denver Water |
Fire |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for undocumented/poorly documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Minor Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Terrain constrained |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Structural Analysis |
After the mapping is complete, a structural analysis will need to be run. |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 712 | |
Explanation | KETD does not have sufficient resource capacity and expertise in house to handle all of the Project Management related tasks necessary to facility on-time completion of the station's build by the Construction Deadline. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
NEPA Section 106 environmental review | Yes | |
Environmental Assessment | Yes | |
ASR Modification | Yes | |
FAA Consultation (including preparation of FAA Form 7460) | Yes | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | Yes | |
Number of Days | 10 | |
Justification | Supervision and inspection of work completed |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
Equipment Rental |
Equipment Rental |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $771,177.68 | $280,537.29 | N/A | $174,159.67 | N/A |
Total for all systems | $2,034,968.66 | $1,326,278.03 | N/A | $532,456.65 | N/A |
Primary Transmitter ULXTE-16 | $771,177.68 | $280,537.29 | $174,159.67 | ||
Internal Transmission Line | $3,954.95 | $3,954.95 | Dielectric Quote CLE 084 RevB | $0.00 | N/A |
4 Port Switch | $16,000.00 | $16,000.00 | N/A | $0.00 | N/A |
10 Ton system | $38,900.00 | $37,000.00 | N/A | N/A | N/A |
Other Electrical Service: The new main transmitter will require reconfiguration of the electrical service on site. The electrical work cost has been estimated based on verbal guidance from local electrical contractors. | $40,000.00 | $40,000.00 | N/A | $12,896.00 | N/A |
Transformer 3 phase/480v - 150 KVA | $25,550.00 | $24,300.00 | N/A | $1,981.33 | N/A |
UHF - Liquid Cooled Solid State Transmitter 8.2 - 13 kW | $494,500.00 | $7,009.61 | See Estimated Cost Justification KETD-110-1st Primary Transmitter - UHF - Liquid Cooled Solid State Transmitter 10.8 kW v0 | $7,009.61 | N/A |
UHF - Air Cooled Solid State Transmitter 3.6 kW | $152,272.73 | $152,272.73 | ***System Notice: Estimate adjusted and locked because line has been superseded.***Per GatesAir Quote Q-79399 + shipping and taxes | $152,272.73 | N/A |
Actual Information Description | File Name |
---|---|
Internal Transmission Line | Information not provided. |
4 Port Switch | Information not provided. |
10 Ton system | Information not provided. |
Other Electrical Service: The new main transmitter will require reconfiguration of the electrical service on site. The electrical work cost has been estimated based on verbal guidance from local electrical contractors. | |
Transformer 3 phase/480v - 150 KVA | |
UHF - Liquid Cooled Solid State Transmitter 8.2 - 13 kW | |
UHF - Air Cooled Solid State Transmitter 3.6 kW |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $266,220.00 | $75,338.69 | N/A | $53,014.24 | N/A |
Total for all systems | $2,034,968.66 | $1,326,278.03 | N/A | $532,456.65 | N/A |
Primary Antenna TFU-12DSB-F/VP | $266,220.00 | $75,338.69 | $53,014.24 | ||
UHF - Lower Power Side Mount, One station antenna -- 200-500 kW, elliptically or circularly polarized | $227,000.00 | $39,885.00 | Please see attached Dielectric Quote CLE084RevB and Invoice MAN01020. Cost of antenna plus $5,670.00 for freight | $36,744.70 | N/A |
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | $6,400.00 | N/A |
Elbow complex, broadband, at antenna input, per 3 1/8. feedline (if needed) | $9,340.00 | $7,053.69 | Please see Estimated Cost Justification KETD Primary Antenna Elbow Complex and Dehydrator categories v0 | $7,053.69 | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $22,000.00 | N/A | $2,815.85 | N/A |
Actual Information Description | File Name |
---|---|
UHF - Lower Power Side Mount, One station antenna -- 200-500 kW, elliptically or circularly polarized | |
Sweep test of existing antenna | |
Elbow complex, broadband, at antenna input, per 3 1/8. feedline (if needed) | |
Side mount brackets for high power antennas (if not included in antenna base cost) |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $10,227.82 | $12,032.94 | N/A | $12,032.94 | N/A |
Total for all systems | $2,034,968.66 | $1,326,278.03 | N/A | $532,456.65 | N/A |
Primary Transmission Line | $10,227.82 | $12,032.94 | $12,032.94 | ||
Dehydrator | $4,327.82 | $4,327.82 | see Estimated Cost Justification KETD Primary Antenna Elbow Complex and Dehydrator categories v0 | $4,327.82 | N/A |
Flexible Air Transmission Line - dielectric, 3" | $5,900.00 | $7,705.12 | Per Estimated Estimated Cost Justification KETD-310-Primary Transmission Line - 3 Air Dielectric V1 | $7,705.12 | N/A |
Actual Information Description | File Name |
---|---|
Dehydrator | |
Flexible Air Transmission Line - dielectric, 3" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $617,300.00 | $587,000.00 | N/A | $104,114.00 | N/A |
Total for all systems | $2,034,968.66 | $1,326,278.03 | N/A | $532,456.65 | N/A |
Primary Tower TOWER | $617,300.00 | $587,000.00 | $104,114.00 | ||
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $400,000.00 | N/A | $65,490.00 | N/A |
Structural Analysis | $12,000.00 | $12,000.00 | N/A | $4,136.00 | N/A |
Minor tower reinforcement/modifications | $158,000.00 | $150,000.00 | N/A | $34,488.00 | N/A |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study | $26,300.00 | $25,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | |
Structural Analysis | |
Minor tower reinforcement/modifications | |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $282,811.00 | $284,721.95 | N/A | $159,829.65 | N/A |
Total for all systems | $2,034,968.66 | $1,326,278.03 | N/A | $532,456.65 | N/A |
Outside Professional Services | $282,811.00 | $284,721.95 | $159,829.65 | ||
Additional Field Engineering Service, 10 Days | $3,375.00 | $3,375.00 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $3,375.00 | N/A |
RF Exposure Measurements | $21,050.00 | $20,000.00 | N/A | $17,566.50 | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $80,000.00 | N/A | N/A | N/A |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
ASR modification (prepare FCC Form 854) | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | $10,520.00 | $10,000.00 | N/A | N/A | N/A |
NEPA Section 106 environmental review, if needed | $6,310.00 | $6,000.00 | N/A | N/A | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $4,210.00 | $12,475.80 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $12,475.80 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,520.90 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $2,520.90 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | $250.00 | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $15,050.25 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $15,050.25 | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | $351.00 | N/A |
Project management of the transition | $112,496.00 | $106,800.00 | N/A | $104,023.70 | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $7,360.00 | $7,000.00 | N/A | $4,216.50 | N/A |
Prepare request for Special Temporary Authorization | $4,100.00 | $3,000.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Additional Field Engineering Service, 10 Days | |
RF Exposure Measurements | |
Comprehensive coverage verification via field study, if needed | Information not provided. |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | Information not provided. |
ASR modification (prepare FCC Form 854) | Information not provided. |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | Information not provided. |
NEPA Section 106 environmental review, if needed | Information not provided. |
Attorney Fees - Negotiation of lease and other matters for shared locations | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Perform engineering study for new channel assignment and antenna development | |
Address transition timing and coordination issues w/ other stations and wireless | Information not provided. |
Prepare and or review reimbursement form | |
Project management of the transition | |
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $87,232.16 | $86,647.16 | N/A | $29,306.15 | N/A |
Total for all systems | $2,034,968.66 | $1,326,278.03 | N/A | $532,456.65 | N/A |
Other Expenses | $87,232.16 | $86,647.16 | $29,306.15 | ||
Develop and air announcement of upcoming channel change | $15,000.00 | $15,000.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $25,000.00 | $25,000.00 | N/A | $884.65 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $10,000.00 | $10,000.00 | N/A | $1,599.00 | N/A |
Non-zoning permits | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
Local Zoning | $5,000.00 | $5,000.00 | N/A | $3,777.09 | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $200.00 | See Estimated Cost Justification KETD-610-FCC Filing - Special Temporary Authorization v0 | $200.00 | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | See Estimated Cost Justification KETD-610-FCC Filing - License to Cover Application v0 | $335.00 | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | $8,322.00 | N/A |
Equipment Rental | $1,684.00 | $1,684.00 | Please see KETD Equipment Rental Budget Revision Justification Letter | $1,684.00 | N/A |
MVPD Notification of Channel Change | $12,358.16 | $12,358.16 | Please Estimated Cost Justification KETD-610-MVPD Notification v2 | $12,358.16 | Please see submitted invoices. |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,070.00 | N/A | $146.25 | N/A |
Actual Information Description | File Name |
---|---|
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | |
Non-zoning permits | Information not provided. |
Local Zoning | |
FCC Filing Fees - Special Temporary Authorization request | |
FCC Filing Fees - Form 2100 license to cover application | |
DTV Medical Facility Notification | |
Equipment Rental | |
MVPD Notification of Channel Change | |
FCC Filing Fees - Form 2100 minor change CP application |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $2,034,968.66 | $1,326,278.03 | $532,456.65 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Michael Everett Todd Chief Engineer 03/04/2022 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Michael Everett Todd Chief Engineer 03/04/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Michael Everett Todd Chief Engineer 03/04/2022 |