Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
MONTEREY COUNTY SUPERINTENDENT OF SCHOOLS Doing Business As: MONTEREY COUNTY OFFICE OF EDUCATION |
Emiliano A. Valdez 901 BLANCO CIRCLE PO BOX 80851 SALINAS, CA 93912 United States |
+1 (831) 755-0300 | evaldez@montereycoe.org | Government Entity |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Samuel Hariton Widelity |
Samuel Hariton 4031 University Dr Suite 100 Fairfax, VA 22030 United States |
+1 (339) 222-8107 | sam.hariton@widelity.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | K31OL-D is planning to purchase like-for-like transmitter and antenna, to reuse its existing transmission line and to install the new equipment on the existing tower. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | SCT 101 UB-C | |
Year | 2009 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 1200 W |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | TRN-5X-U-18-C | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 1.1 kW | |
Justification for New Transmitter | Re-tuning the existing main transmitter is not an option because it is not technically capable of operating on the assigned channel. |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
Primary Transmitter - Other Expenses |
Primary Transmitter - Other Expenses |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | ALP24M2-HS | |
Year | 2009 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | ALP1 2M2-HSOC-31 | |
Year | 2019 | |
Justification for New Antenna | The new antenna is required because the existing antenna model is not capable of being re-tuned. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
Coordinates (NAD83) | Latitude (NAD83) | 36° 32' 17.8" N- |
Longitude (NAD83) | 121° 37' 34.7" W- | |
Overall Structure Height | 154.00 feet | |
Support Structure Height | 150.00 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 3215.00 feet | |
Structure Type | NNTANN - Antenna Tower Array - 1st N = # | |
Tower Owner | K31OL-D | |
Date Constructed | 06/07/1982 |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | No study needed |
Tower Reinforcements | Please select whether tower reinforcements are needed: | No reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 254 | |
Explanation | K31OL-D does not have sufficient resource capacity and expertise in house to handle all of the reimbursement activities necessary to facilitate on-time completion of the station's build. K31OL-D will hire an outside firm to support K31OL-D in these tasks. | |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | Yes | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | Yes |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $102,811.83 | $56,247.08 | N/A | $37,435.25 | N/A |
Total for all systems | $245,863.83 | $164,295.03 | N/A | $98,795.95 | N/A |
Primary Transmitter TRN-5X-U-18-C | $102,811.83 | $56,247.08 | $37,435.25 | ||
Primary Transmitter - Other Expenses | $18,811.83 | $18,811.83 | Please see K31OL-D Primary Transmitter - Other Parts Budget Justification Letter | $0.00 | N/A |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | $84,000.00 | $37,435.25 | Please see attached Anywave Proposal 8007-02-10-17-2018 | $37,435.25 | N/A |
Actual Information Description | File Name |
---|---|
Primary Transmitter - Other Expenses | |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $38,375.00 | $38,375.00 | N/A | $12,040.25 | N/A |
Total for all systems | $245,863.83 | $164,295.03 | N/A | $98,795.95 | N/A |
Primary Antenna ALP1 2M2-HSOC-31 | $38,375.00 | $38,375.00 | $12,040.25 | ||
UHF-Low Power, Side Mount, Slotted Coaxial, 15.0kW input, Horizontal | $32,645.00 | $32,645.00 | See Estimated Cost Justification K31OL-D-210-Primary Antenna - UHF Low Power Side Mount, H-POL V0 | $12,040.25 | N/A |
Sweep test of transmission line and antenna | $5,730.00 | $5,730.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
UHF-Low Power, Side Mount, Slotted Coaxial, 15.0kW input, Horizontal | |
Sweep test of transmission line and antenna | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $56,190.00 | $14,350.00 | N/A | $7,175.00 | N/A |
Total for all systems | $245,863.83 | $164,295.03 | N/A | $98,795.95 | N/A |
Primary Tower NNTANN | $56,190.00 | $14,350.00 | $7,175.00 | ||
Tower Rigging Short Tower (less than 500') | $56,190.00 | $14,350.00 | Estimated Cost Justification K31OL-D-410-Existing Primary Tower - Tower Rigging, Short Tower v0 | $7,175.00 | N/A |
Actual Information Description | File Name |
---|---|
Tower Rigging Short Tower (less than 500') |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $42,082.00 | $53,877.95 | N/A | $42,145.45 | N/A |
Total for all systems | $245,863.83 | $164,295.03 | N/A | $98,795.95 | N/A |
Outside Professional Services | $42,082.00 | $53,877.95 | $42,145.45 | ||
Project management of the transition | $26,797.00 | $31,435.45 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $31,435.45 | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $3,262.50 | $3,262.50 | N/A | $781.50 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | N/A | N/A |
Prepare Form 601 | $755.00 | $0.00 | 5/6 SS Verified Estimate at $0, the category is not needed per MSG4549646 | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | N/A | N/A |
Perform engineering study for displacement application | $1,800.00 | $9,712.50 | Invoices received | $9,712.50 | Invoices received |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,710.00 | N/A | $216.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Project management of the transition | |
Attorney Fees - Negotiation of lease and other matters for shared locations | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare Form 601 | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for displacement application | |
Prepare/ Review 399 reimbursement form | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $6,405.00 | $1,445.00 | N/A | $0.00 | N/A |
Total for all systems | $245,863.83 | $164,295.03 | N/A | $98,795.95 | N/A |
Other Expenses | $6,405.00 | $1,445.00 | $0.00 | ||
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 Major change CP application | $4,960.00 | $0.00 | 5/6 SS Verified Estimate at $0, the category is not needed per MSG4549646 | N/A | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,110.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $245,863.83 | $164,295.03 | $98,795.95 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Emiliano Valdez Director of Media Center 03/07/2022 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Emiliano Valdez Director of Media Center 03/07/2022 |