Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
Nexstar Media Inc. |
Elizabeth Ryder 545 E. John Carpenter Freeway Suite 700 irving, TX 75062 United States |
+1 (972) 373-8800 | eryder@nexstar.tv | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Elizabeth Ryder General Counsel Nexstar Media Inc. |
Elizabeth Ryder 545 E. John Carpenter Freeway Suite 700 Irving, TX 75062 United States |
+1 (972) 373-8800 | eryder@nexstar.tv |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Replace transmitter and antenna using existing line. Acquire interim antenna and line for continued operation during construction and duration of the assigned phase. Map and analyze tower; design and implement modifications if required. See attached. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | LU250ATD | |
Year | 2010 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 0.25 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | TLU9 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | .01 kW | |
Justification for New Transmitter | The manufacturer of the existing transmitter is out of business and no factory support is available for the existing transmitter. See attachment. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | Yes | |
Size | 1 inches | |
Length | 100.0 feet | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Additional Interior RF System |
Small flex coax type N connectors and type N patch panels |
Temporary Transmitter delivery and Installation |
Temp. Transmitter Install using Temporary Tower until New RePack Transmitter is delivered and installed. Please see Microwave Rental LLC Quote # 200727 attached. |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 1.0 kW | |
Manufacturer | ||
Model | TLP-8E | |
Year | 2010 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 2.5 kW | |
Manufacturer | ||
Model | ALP4L0-ESWR-21 | |
Year | 2020 | |
Justification for New Antenna | The existing primary antenna is a single channel slotted coaxial which cannot accommodate the assigned channel. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Type | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 1.0 kW | |
Manufacturer | ||
Model | TBD | |
Year | 2018 | |
Justification for New Antenna | An interim antenna is necessary to keep station on the air during primary antenna replacement and for the duration of the assigned phase. Station will attempt to rent if renting is available at time of acquisition. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Foam | |
Diameter | Other | |
Other Diameter | 2 1/4 inches | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 50 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Flexible Air | |
Diameter | 1 5/8 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 90 feet per run | |
Justification for New Transmission Line | a |
Name | Description |
---|---|
Transmission Line, Hangers, Grounding Kits Etc. |
Transmission Line and ancillary hardware for new antenna. Please see Electronics Research Proposal # 20200731-125 |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Type | Flexible Foam | |
Diameter | 7/8 inches | |
Segment Length | N/A | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 50 feet per run | |
Justification for New Transmission Line | An interim transmission line is necessary for the interim antenna to keep station on the air during primary antenna replacement and for the duration of the assigned phase. Station will attempt to rent if renting is available at time of acquisition. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
ASR Number | ||
Coordinates (NAD83) | Latitude (NAD83) | 42° 12' 05.3" N- |
Longitude (NAD83) | 072° 38' 41.3" W- | |
Overall Structure Height | 75.00 feet | |
Support Structure Height | 75.00 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 1138.00 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Nexstar Broadcasting, Inc. | |
Date Constructed | 01/01/2004 |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for undocumented/poorly documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Minor Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Construct New |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | No |
ASR Number | ||
Coordinates (NAD83) | Latitude (NAD83) | 42° 12' 05.3" N- |
Longitude (NAD83) | 072° 38' 41.3" W- | |
Overall Structure Height | 75.00 feet | |
Support Structure Height | 75.00 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 1138.00 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Nexstar Broadcasting, Inc. | |
Date Constructed | 01/01/2004 |
Section | Question | Response |
---|---|---|
Construct New Tower | Use | Primary (Main) |
Description of Use | N/A | |
Is this a request for upgraded equipment? | No | |
Height | 70.00 feet | |
Justification for New Tower | See attached Analysis Report from Morrison Hershfield stating that modifying the tower structure to meet the loading requirements is not a feasible option or safe for workers. |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Structural Analysis |
Geotech Survey |
Structural Installation of Tower |
Structural Installation of Tower |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 277 | |
Explanation | Schedule and coordinate multiple vendors, complete progress reports, and update Schedule 399. Station does not have available personnel or personnel trained in project management for such complex projects. Internal accounting and Project management. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | Yes | |
Number of Days | 17 | |
Justification | It will be necessary to survey the site, plan the equipment, develop specifications for purchasing, and oversee multiple vendor RF projects. Station does not have available personnel or personnel trained in such services. |
Name | Description |
---|---|
Engineering and Permit Services |
Engineering and Permit Services |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $67,450.00 | $34,250.00 | N/A | $23,250.00 | N/A |
Total for all systems | $843,410.00 | $639,468.45 | N/A | $254,983.35 | N/A |
Primary Transmitter TLU9 | $67,450.00 | $34,250.00 | $23,250.00 | ||
1" Rigid Conduit and Wiring | $1,000.00 | $1,000.00 | N/A | N/A | N/A |
Temporary Transmitter delivery and Installation | $14,000.00 | $14,000.00 | Temp. Transmitter Install using Temporary Tower until New RePack Transmitter is delivered and installed. Please see Microwave Rental LLC Quote # 200727 attached. | $14,000.00 | N/A |
Additional Interior RF System | $5,000.00 | $5,000.00 | Small flex coax type N connectors and type N patch panels | N/A | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $5,000.00 | Sub-panel, breakers and labor to connect to transmitter rack | N/A | N/A |
UHF - Air Cooled Solid State Transmitter .01 kW | $9,250.00 | $9,250.00 | See Rohde & Schwarz quote 133627.0 | $9,250.00 | N/A |
Actual Information Description | File Name |
---|---|
1" Rigid Conduit and Wiring | Information not provided. |
Temporary Transmitter delivery and Installation | |
Additional Interior RF System | Information not provided. |
Switchgear - industrial 800 amp | Information not provided. |
UHF - Air Cooled Solid State Transmitter .01 kW |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $66,060.00 | $45,577.50 | N/A | $7,777.50 | N/A |
Total for all systems | $843,410.00 | $639,468.45 | N/A | $254,983.35 | N/A |
Interim Antenna TBD | $33,030.00 | $31,400.00 | $0.00 | ||
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
UHF - Lower Power Side Mount, Class A One Station antenna -- basic | $26,300.00 | $25,000.00 | N/A | N/A | N/A |
Primary Antenna ALP4L0-ESWR-21 | $33,030.00 | $14,177.50 | $7,777.50 | ||
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
UHF - Lower Power Side Mount, Class A One Station antenna -- basic | $26,300.00 | $7,777.50 | See ERI quote less upgrade cost | $7,777.50 | N/A |
Actual Information Description | File Name |
---|---|
Sweep test of existing antenna | Information not provided. |
UHF - Lower Power Side Mount, Class A One Station antenna -- basic | Information not provided. |
Sweep test of existing antenna | Information not provided. |
UHF - Lower Power Side Mount, Class A One Station antenna -- basic |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $15,823.00 | $18,289.95 | N/A | $12,303.00 | N/A |
Total for all systems | $843,410.00 | $639,468.45 | N/A | $254,983.35 | N/A |
Interim Transmission Line | $550.00 | $500.00 | $0.00 | ||
Flexible Foam Transmission Line - dielectric, 7/8" | $550.00 | $500.00 | N/A | N/A | N/A |
Primary Transmission Line | $15,273.00 | $17,789.95 | $12,303.00 | ||
Flexible Air Transmission Line - dielectric, 1 5/8" | $2,970.00 | $5,486.95 | See Dielectric quote DMS128-2 | $0.00 | N/A |
Transmission Line, Hangers, Grounding Kits Etc. | $12,303.00 | $12,303.00 | Transmission Line and ancillary hardware for new antenna. Please see Electronics Research Proposal # 20200731-125 | $12,303.00 | N/A |
Actual Information Description | File Name |
---|---|
Flexible Foam Transmission Line - dielectric, 7/8" | Information not provided. |
Flexible Air Transmission Line - dielectric, 1 5/8" | |
Transmission Line, Hangers, Grounding Kits Etc. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $498,801.00 | $350,801.00 | N/A | $157,395.50 | N/A |
Total for all systems | $843,410.00 | $639,468.45 | N/A | $254,983.35 | N/A |
Primary Tower TOWER | $158,000.00 | $10,000.00 | $10,000.00 | ||
Minor tower reinforcement/modifications | $158,000.00 | $10,000.00 | ***System Notice: Estimate adjusted and locked because line has been superseded.*** | $10,000.00 | N/A |
Primary Tower TOWER | $0.00 | $0.00 | $0.00 | ||
Primary Tower | $340,801.00 | $340,801.00 | $147,395.50 | ||
New tower | $34,490.00 | $34,490.00 | See ERI proposal 20190407-174 Rev C | $34,490.00 | N/A |
Short Tower (less than 500') | $84,200.00 | $84,200.00 | Waiting on quotes | $4,500.00 | N/A |
Structural Analysis | $14,700.00 | $14,700.00 | See Electronics Research proposal 20190429-380 and Morrison Hershfield proposal 11/6/2018 | $14,700.00 | N/A |
Structural Installation of Tower | $207,411.00 | $207,411.00 | See Electronics Research quote 20200427-537 Rev A | $93,705.50 | N/A |
Actual Information Description | File Name |
---|---|
Minor tower reinforcement/modifications | |
New tower | |
Short Tower (less than 500') | |
Structural Analysis | |
Structural Installation of Tower |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $118,226.00 | $114,050.00 | N/A | $45,288.50 | N/A |
Total for all systems | $843,410.00 | $639,468.45 | N/A | $254,983.35 | N/A |
Outside Professional Services | $118,226.00 | $114,050.00 | $45,288.50 | ||
Engineering and Permit Services | $9,750.00 | $9,750.00 | See Analytical Engineering proposed Scope of Work | $9,750.00 | N/A |
Additional Field Engineering Service, 17 Days | $34,000.00 | $34,000.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $3,680.00 | $3,500.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | $625.00 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | $3,000.00 | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | $7,000.00 | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | $2,500.00 | N/A |
Project management of the transition | $43,766.00 | $41,550.00 | N/A | $22,413.50 | N/A |
Actual Information Description | File Name |
---|---|
Engineering and Permit Services | |
Additional Field Engineering Service, 17 Days | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Perform engineering study for new channel assignment and antenna development | |
Address transition timing and coordination issues w/ other stations and wireless | Information not provided. |
Prepare and or review reimbursement form | |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $77,050.00 | $76,500.00 | N/A | $8,968.85 | N/A |
Total for all systems | $843,410.00 | $639,468.45 | N/A | $254,983.35 | N/A |
Other Expenses | $77,050.00 | $76,500.00 | $8,968.85 | ||
Develop and air announcement of upcoming channel change | $1,500.00 | $1,500.00 | Cost to develop and produce spots and crawls for viewer notification | N/A | N/A |
Equipment Storage | $16,000.00 | $16,000.00 | N/A | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $16,000.00 | $16,000.00 | N/A | N/A | N/A |
Non-zoning permits | $25,000.00 | $25,000.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | $4,172.00 | N/A |
Equipment Delivery and Handling Charges | $5,000.00 | $5,000.00 | See related invoices | $4,796.85 | N/A |
MVPD Notification of Channel Change | $2,000.00 | $2,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Storage | Information not provided. |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
Non-zoning permits | Information not provided. |
DTV Medical Facility Notification | |
Equipment Delivery and Handling Charges | |
MVPD Notification of Channel Change | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $843,410.00 | $639,468.45 | $254,983.35 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | Yes |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Elizabeth Ryder General Counsel 10/08/2021 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Elizabeth Ryder General Counsel 10/08/2021 |