Facility ID:
35582
Service:
DTV
Call Sign:
WYDO
Channel:
19 (UHF)
File Number:
0000028146
FRN:
0027174721
Date Submitted:
12/07/2021

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

New Bern (WYDO-TV) Licensee, Inc.

Lisa Asher

2000 WEST 41ST STREET

BALTIMORE, MD 21211

United States

+1 (410) 662-9688 LAsher@cunninghambroadcasting.com Corporation

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

Paul A. Cicelski

Lerman Senter PLLC

Paul A. Cicelski

2001 L Street NW

Suite 400

Washington, DC 20036

United States

+1 (202) 416-6756 pcicelski@lermansenter.com

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. Yes
Briefly describe transition plan Install interim channel 19 antenna, line, and transmitter before switchover date. At switchover date, begin operation on channel 19 interim system. Remove channel 47 equipment. Install full power channel 19 equipment and begin operations

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model Diamond
Year 1998
Type Solid State
Solid State Cooling Air Cooled
Solid State Power Capacity 15 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model THU9EVO-16
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 25.5 kW
Justification for New Transmitter Manufacturer states existing transmitter cannot be retuned to new channel.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) Yes
Switchgear (industrial 800 amp) Yes
Transformer (480V) Yes
Power 300 kVA
Rigid Conduit and Wiring Yes
Size 4 inches
Length 50.0 feet
Other Electrical Service No
Description N/A
HVAC Service Does the replacement transmitter require HVAC Service? Yes
Type Cooling Only
Size 20 tons
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Ice Bridge

Ice Bridge

Electrical Installation

Electrical Installation

Additional parts

Additional parts

Transmitter Transmission Line Fabrication

Transmitter Transmission Line Fabrication

Interim Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Interim
Description of Use N/A
Change Type Purchase
Manufacturer
Model UAXTE-8R44
Transmitter Type Solid State
Solid State Cooling Air Cooled
Solid State Power capacity 4.8 kW
Justification for New Transmitter Currently, there is no interim ch. 19 transmitter. We will have to go on air with interim ch. 19 equipment first; then remove the ch. 47 equipment; and install the full power ch. 19 equipment.

Interim Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service Yes
Description Inside building wiring from breaker box to interim transmitter.
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A
Inside RF System Is an additional interior RF system required to support this interim transmitter? Yes

Interim Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? No
Existing Antenna Manufacturer and Type Class Full Power
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Elliptical
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels N/A
Design power capacity in use N/A
Lower Limit N/A
Upper Limit N/A
Other Antenna Type N/A
ERP: 200.0 kW
Manufacturer
Model TFU-16DSB-M/VP
Year 2009

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? No
New Antenna Manufacturer and Types Class Full Power
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Elliptical
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 124.0 kW
Manufacturer
Model TFU-20DSB-M/VP-R
Year 2017
Justification for New Antenna Manufacturer states existing antenna cannot be retuned to new channel.

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna?
Type
Number of channels supported N/A
Frequencies of channels supported N/A
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? N/A
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? Single Channel
Feed Line Size 6 1/8 inches inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna? Yes
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? Yes
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Mounting Brackets

Mounting Brackets

Feed through complex

Feed through complex

Interim Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Interim
Description of Use N/A
Change Type Purchase New
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? No
New Antenna Manufacturer and Type Class Full Power
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Elliptical
Type Broadband Slot
Number of Stations Supported 1
Number of Panels/Bays 8
Lower Limit 470.00 MHz
Upper Limit 698.00 MHz
Design power capacity in use 24.0 %
Other Antenna Type N/A
ERP: 36.0 kW
Manufacturer
Model TFU-16WB/VP-R C160
Year 2017
Justification for New Antenna Currently, there is no interim ch. 19 antenna. We will have to go on air with interim ch. 19 equipment first; then remove the ch. 47 equipment; and install the full power ch. 19 equipment.

Interim Antenna

Back to Top

Other Antenna Costs

Section Question Response
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? B
Feed Line Size 3 1/8 inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for an antenna? Yes
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? Yes
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Interim Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing transmission line shared with another station or stations? Yes
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer
Type Rigid
Diameter 6 1/8 inches
Other Diameter N/A
Segment Length 20 inches
Other Segment Length N/A
Number of parallel runs 1
Length 2000 feet per run

Facility ID's and Call Signs of all stations with whom the transmission line is shared.

Facility ID Call Sign
18334 WCTI-TV

Primary Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? No
Type Rigid
Diameter 6 1/8 inches
Other Diameter N/A
Segment Length 20 inches
Other Segment Length N/A
Number of parallel runs 1
Length 2000 feet per run
Justification for New Transmission Line Existing shared line with WCTI is being replaced with two separate lines. WCTI moves to channel 10 which requires 19.5ft. section line.

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

4-50 Patch Panel

4-50 Patch Panel

Interim Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Interim
Description of Use N/A
Change Type Purchase New
Type Flexible Air
Diameter 3 inches
Segment Length N/A
Other Segment Length
Number of parallel runs 1
Length 500 feet per run
Justification for New Transmission Line Currently, there is no ch. 19 interim transmission line. We plan to go on air with ch. 19 interim equipment first. Then we will remove the ch. 47 equipment and install the full power ch. 19 equipment.

Interim Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Information not provided.

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Description of Use N/A
Ownership Owned
Is this tower consider Complex?
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users No
Is tower documented for structural analysis? No
Is tower compliant with Rev G? No
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1011271
Coordinates (NAD83) Latitude (NAD83) 35° 06' 16.0" N-
Longitude (NAD83) 077° 20' 11.0" W-
Overall Structure Height 1988.82 feet
Support Structure Height 1878.59 feet
Ground Elevation Above Mean Sea Level (AMSL) 45.93 feet
Structure Type TOWER - Free Standing or Guyed Structure
Tower Owner EASTERN NORTH CAROLINA BROADCASTING CORPORATION
Date Constructed 01/01/1981

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
18334 WCTI-TV DTV
36950 WRNS-FM FM
69444 WUNM-TV DTV

Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for undocumented/poorly documented tower
Tower Reinforcements Please select whether tower reinforcements are needed: Serious Reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Other
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Name Description

Construction Project Management

Construction Project Management

Security

Security

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 450
Explanation Not enough experienced station personnel to manage this large of a project
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
NEPA Section 106 environmental review Yes
Environmental Assessment Yes
ASR Modification Yes
FAA Consultation (including preparation of FAA Form 7460) No
Negotiation of Lease and other Matter for Shared Locations No
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements Yes
Additional Field Engineering Service No
Number of Days N/A
Justification N/A

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Name Description

Sinclair Internal Costs

Internal Employee Time Costs

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning Yes
Non-zoning permits No
BLM or NFS Coordination No
FCC Construction Permit Minor Change Yes
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? Yes
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? Yes
Does this relocation require MVPD Notification of a Channel Change? Yes

Other Expenses

Back to Top

Other Expenses Not Listed

Name Description

True-up

True-up

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,566,287.49 $911,887.71 N/A $422,539.76 N/A
Total for all systems $4,187,865.16 $3,279,082.59 N/A $1,213,905.28 N/A
Interim Transmitter UAXTE-8R44 $399,000.00 $322,311.71 $0.00
UHF inside RF system including switching $147,500.00 $140,000.00 N/A N/A N/A
Other Electrical Service: Inside building wiring from breaker box to interim transmitter. $15,000.00 $15,000.00 N/A N/A N/A
UHF - Air Cooled Solid State Transmitter 4 - 6 kW $236,500.00 $167,311.71 N/A N/A N/A
Primary Transmitter THU9EVO-16 $1,167,287.49 $589,576.00 $422,539.76
Additional parts $16,663.00 $16,663.00 N/A $16,663.00 N/A
Electrical Installation $29,173.24 $29,173.24 N/A $11,937.00 Invoice #002816 can be removed. It has been submitted under a different line item as per RFI request.
Ice Bridge $18,681.25 $18,681.25 N/A $18,681.25 N/A
Other -- HVAC Service Type: C Size:20 (Other) $60,000.00 $60,000.00 N/A N/A N/A
4" Rigid Conduit and Wiring (Cost per foot) $5,050.00 $4,800.00 N/A N/A N/A
Transformer 3 phase/480v - 300 KVA $36,800.00 $35,000.00 N/A N/A N/A
Switchgear - industrial 800 amp $38,200.00 $36,300.00 N/A N/A N/A
Service entrance 3 phase/800 amp/208 volt $14,400.00 $13,700.00 N/A N/A N/A
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW $947,000.00 $373,938.51 N/A $373,938.51 N/A
Transmitter Transmission Line Fabrication $1,320.00 $1,320.00 N/A $1,320.00 N/A

Components

Actual Information Description File Name
UHF inside RF system including switching Information not provided.
Other Electrical Service: Inside building wiring from breaker box to interim transmitter. Information not provided.
UHF - Air Cooled Solid State Transmitter 4 - 6 kW Information not provided.
Additional parts

Component Description:
Transmitter related cost. #9500131929
Amount:
$8,666.00

Component Description:
Transmitter related cost. #9500112072
Amount:
$950.00

Component Description:
Transmitter related cost. #9500111842
Amount:
$7,047.00
Electrical Installation

Component Description:
Transmitter electrical cost. #CR-0380-03
Amount:
$11,937.00

Component Description:
Transmitter related cost. #002816
Amount:
$1,320.00

Component Description:
Resubmitted under 4-50 Patch Panel. #002847
Amount:
N/A
Ice Bridge

Component Description:
Ice Bridge cost. #190401
Amount:
$18,681.25
Other -- HVAC Service Type: C Size:20 (Other) Information not provided.
4" Rigid Conduit and Wiring (Cost per foot) Information not provided.
Transformer 3 phase/480v - 300 KVA Information not provided.
Switchgear - industrial 800 amp Information not provided.
Service entrance 3 phase/800 amp/208 volt Information not provided.
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW

Component Description:
Transmitter related cost. #9500096558
Amount:
$18,531.01

Component Description:
Transmitter cost, 25% down. #9500084671
Amount:
$66,276.88

Component Description:
Transmitter related cost. #9500111916
Amount:
$90,300.00

Component Description:
Transmitter cost, 75% balance. #9500096555
Amount:
$198,830.62
Transmitter Transmission Line Fabrication

Component Description:
TX TL fabrication and install. #002816
Amount:
$1,320.00

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $329,529.98 $318,951.58 N/A $205,644.15 N/A
Total for all systems $4,187,865.16 $3,279,082.59 N/A $1,213,905.28 N/A
Interim Antenna TFU-16WB/VP-R C160 $153,200.00 $149,206.40 $99,398.86
Elbow complex, broadband, at antenna input, per 3 1/8. feedline (if needed) $9,340.00 $8,624.00 N/A $6,094.82 N/A
Sweep test of existing antenna $6,730.00 $5,862.40 N/A $5,862.40 N/A
UHF - High Power, Side Mount, basic slot antenna, 8 bay,, 36 kW input, directional,, elliptically or circularly polarized $108,720.00 $108,720.00 N/A $87,441.64 N/A
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) $5,260.00 $4,000.00 N/A N/A N/A
Side mount brackets for high power antennas (if not included in antenna base cost) $23,150.00 $22,000.00 N/A N/A N/A
Primary Antenna TFU-20DSB-M/VP-R $176,329.98 $169,745.18 $106,245.29
Feed through complex $10,744.68 $10,744.68 N/A $10,744.68 N/A
Mounting Brackets $15,045.30 $15,045.30 N/A $15,045.30 N/A
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) $5,260.00 $4,000.00 N/A N/A N/A
Side mount brackets for high power antennas (if not included in antenna base cost) $23,150.00 $11,600.00 N/A $2,987.73 N/A
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) $12,300.00 $12,768.00 Manufacturer's quote $9,810.36 N/A
UHF - Lower Power Side Mount, One Station antenna . medium power (50-200 kW), elliptically or circularly polarized $103,100.00 $98,000.00 N/A $50,070.02 N/A
Sweep test of existing antenna $6,730.00 $17,587.20 See Dielectric quote. $17,587.20 N/A

Components

Actual Information Description File Name
Elbow complex, broadband, at antenna input, per 3 1/8. feedline (if needed)

Component Description:
Total invoice amount reduced by 25.40%. #617012
Amount:
$6,094.82
Sweep test of existing antenna

Component Description:
Antenna related cost reduced by 8.40%. #712010
Amount:
$5,862.40
UHF - High Power, Side Mount, basic slot antenna, 8 bay,, 36 kW input, directional,, elliptically or circularly polarized

Component Description:
The total invoice amount is reduced by 25.40%. #617012
Amount:
$87,441.64
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) Information not provided.
Side mount brackets for high power antennas (if not included in antenna base cost) Information not provided.
Feed through complex

Component Description:
Antenna related cost reduced by 8.40%. #729014
Amount:
$10,744.68
Mounting Brackets

Component Description:
Antenna related cost reduced by 8.40%. #749012
Amount:
$15,045.30
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) Information not provided.
Side mount brackets for high power antennas (if not included in antenna base cost)

Component Description:
Total invoice amount reduced by 25.40%. #657013
Amount:
$2,987.73
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed)

Component Description:
Antenna related cost reduced by 8.40%. #729014
Amount:
$9,810.36
UHF - Lower Power Side Mount, One Station antenna . medium power (50-200 kW), elliptically or circularly polarized

Component Description:
UHF low power side mount cost. #449045
Amount:
$50,070.02
Sweep test of existing antenna

Component Description:
Antenna related cost reduced by 8.40%. #940011
Amount:
$5,862.40

Component Description:
Antenna related cost reduced by 8.40%. #763002
Amount:
$11,724.80

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $449,416.24 $301,924.04 N/A $223,151.19 N/A
Total for all systems $4,187,865.16 $3,279,082.59 N/A $1,213,905.28 N/A
Interim Transmission Line $29,500.00 $24,651.00 $0.00
Flexible Air Transmission Line - dielectric, 3" $29,500.00 $24,651.00 N/A $0.00 N/A
Primary Transmission Line $419,916.24 $277,273.04 $223,151.19
4-50 Patch Panel $15,916.24 $15,916.24 N/A $15,916.24 N/A
Rigid Transmission Line - copper, 6 1/8" $404,000.00 $261,356.80 N/A $207,234.95 N/A

Components

Actual Information Description File Name
Flexible Air Transmission Line - dielectric, 3" Information not provided.
4-50 Patch Panel

Component Description:
Panel cost. #002847
Amount:
$15,916.24
Rigid Transmission Line - copper, 6 1/8"

Component Description:
Transmission line related cost reduced by 8.40%. #929006
Amount:
$1,352.93

Component Description:
Transmission line related cost reduced by 8.40%. #937005
Amount:
$1,352.93

Component Description:
Rigid copper transmission line cost. #476014
Amount:
$183,548.60

Component Description:
Total invoice amount reduced by 8.40%. #693001
Amount:
$11,078.27

Component Description:
Total invoice amount reduced by 25.40%. #682008
Amount:
$855.48

Component Description:
Total invoice amount reduced by 25.40%. #661003
Amount:
$7,558.47

Component Description:
Total invoice amount reduced by 25.40%. #666043
Amount:
$1,488.27

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,524,506.36 $1,450,206.36 N/A $273,196.46 N/A
Total for all systems $4,187,865.16 $3,279,082.59 N/A $1,213,905.28 N/A
Primary Tower TOWER $1,524,506.36 $1,450,206.36 $273,196.46
Construction Project Management $14,292.36 $14,292.36 N/A $10,747.46 Invoices #0110WYDO and #0120WYDO with the status Need More Information can be removed.
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $400,000.00 N/A $243,035.00 N/A
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study $26,300.00 $25,000.00 N/A $8,500.00 N/A
Security $10,914.00 $10,914.00 N/A $10,914.00 N/A
Serious tower reinforcement/modifications $1,052,000.00 $1,000,000.00 N/A N/A N/A

Components

Actual Information Description File Name
Construction Project Management

Component Description:
Construction project management cost. #0212WYDO
Amount:
$2,119.80

Component Description:
Construction project management. #022221WYDO
Amount:
$1,314.40

Component Description:
Construction management cost. #0120WYDO
Amount:
$1,964.25

Component Description:
Construction project management. #022221WYDO
Amount:
$1,318.80

Component Description:
Construction management cost. #0110WYDO
Amount:
$2,898.75

Component Description:
Construction project management cost. #1119
Amount:
$1,252.02

Component Description:
Construction project management. #1231WYDO
Amount:
$1,198.24

Component Description:
Construction project management cost. #0120WYDO
Amount:
$1,967.40

Component Description:
Construction management cost. #0110WYDO
Amount:
$2,891.90
Complex Tower (includes, for example, those with candelabras and/or stacked antennas)

Component Description:
Tower cost. #SIN002100
Amount:
$38,869.00

Component Description:
Broadcast Field Services Down Payment 50%. #SIN000456
Amount:
$82,648.50

Component Description:
Tower cost. #SIN002048
Amount:
$82,648.50

Component Description:
Tower related cost. #E-190548
Amount:
$38,869.00
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study

Component Description:
Tower related cost. #SIN002340
Amount:
$4,500.00

Component Description:
50% upon order. #E-186765
Amount:
$2,000.00

Component Description:
Tower mapping cost. #E186765
Amount:
$2,000.00

Component Description:
Tower mapping cost. #E186782
Amount:
$2,000.00
Security

Component Description:
Security cost. #1014-TT
Amount:
$10,914.00
Serious tower reinforcement/modifications Information not provided.

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $234,560.88 $213,153.69 N/A $107,519.24 N/A
Total for all systems $4,187,865.16 $3,279,082.59 N/A $1,213,905.28 N/A
Outside Professional Services $234,560.88 $213,153.69 $107,519.24
Project management of the transition $71,100.00 $69,256.64 Please see Summit Ridge Group and Lerman Senter invoices. $69,256.64 The second entry should be removed as we've revised invoice date in first entry.
Sinclair Internal Costs $670.88 $670.88 N/A $670.88 x
RF Exposure Measurements $21,050.00 $20,000.00 N/A N/A N/A
Comprehensive coverage verification via field study, if needed $84,200.00 $80,000.00 N/A $27,000.00 N/A
ASR modification (prepare FCC Form 854) $2,105.00 $2,000.00 N/A N/A N/A
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet $10,520.00 $10,000.00 N/A N/A N/A
NEPA Section 106 environmental review, if needed $6,310.00 $6,000.00 N/A N/A N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $3,680.00 $0.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $0.00 N/A N/A N/A
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application $4,210.00 $0.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $99.92 N/A $99.92 N/A
Prepare request for Special Temporary Authorization $2,050.00 $3,896.25 Please see Carl T. Jones invoices. $3,896.25 N/A
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application $1,580.00 $1,500.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A $1,496.25 N/A
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application $2,105.00 $2,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $4,230.00 See Carl T. Jones invoice. $4,230.00 N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $7,000.00 N/A N/A N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A N/A N/A
Prepare and or review reimbursement form $2,630.00 $2,500.00 N/A $869.30 N/A

Components

Actual Information Description File Name
Project management of the transition

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #472985
Amount:
$282.68

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 33 stations. #482412
Amount:
$1,363.25

Component Description:
Legal Service Cost. #477912
Amount:
$1,111.25

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 59 stations. #295
Amount:
$997.50

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #463026
Amount:
$801.57

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #467378
Amount:
$576.96

Component Description:
Legal services cost. #482748
Amount:
$183.75

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 60 stations. #487016
Amount:
$267.75

Component Description:
Legal services cost. #485674
Amount:
$57.50

Component Description:
Legal services cost. #487961
Amount:
$115.00

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 42 stations. #257
Amount:
$1,209.02

Component Description:
Legal services cost. #481961
Amount:
$57.50

Component Description:
Legal Service Cost. #478861
Amount:
$3,445.40

Component Description:
Legal services cost. #487078
Amount:
$50.00

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 46 stations. #485240
Amount:
$541.57

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 52 stations. #153
Amount:
$1,287.27

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 40 stations. #488547
Amount:
$228.12

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 52 stations. #481318
Amount:
$814.01

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1045
Amount:
$185.10

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #477820
Amount:
$320.19

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #480175
Amount:
$377.96

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 31 stations. #189
Amount:
$1,968.06

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #479829
Amount:
$458.99

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 54 stations. #236
Amount:
$1,117.50

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #479285
Amount:
$372.60

Component Description:
$26,919.78 credit to be split across 93 Sinclair stations reimbursed $999.20 for Invoice 461759 (correct reimbursement amount is $709.74). #CM-11-21-2019-461759
Amount:
($289.46)

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1099
Amount:
$266.93

Component Description:
Legal services cost. #476469
Amount:
$740.00

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1161
Amount:
$267.48

Component Description:
Legal Service Cost. #475391
Amount:
$57.50

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1133
Amount:
$307.72

Component Description:
Legal services cost. #476976
Amount:
$6,916.25

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1079
Amount:
$177.14

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1141
Amount:
$406.17

Component Description:
Legal services cost. #474916
Amount:
$108.75

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1156
Amount:
$399.52

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1114
Amount:
$242.25

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 99 stations. #1086
Amount:
$275.35

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 99 stations. #468718
Amount:
$349.51

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #478288
Amount:
$194.86

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #476367
Amount:
$364.80

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #473506
Amount:
$421.40

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 48 stations. #309
Amount:
$1,299.46

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #473885
Amount:
$318.62

Component Description:
Legal services cost. #472231
Amount:
$57.50

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #118
Amount:
$468.97

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #472583
Amount:
$279.89

Component Description:
Legal services cost. #485238
Amount:
$51.75

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #475283
Amount:
$384.08

Component Description:
Legal services cost. #488528
Amount:
$58.75

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 48 stations. #487892
Amount:
$103.07

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #474405
Amount:
$490.56

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #475744
Amount:
$305.99

Component Description:
Legal services cost. #485231
Amount:
$508.75

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #132
Amount:
$589.44

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #474809
Amount:
$395.77

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 31 stations. #482707
Amount:
$1,071.61

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1130
Amount:
$281.49

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1058
Amount:
$187.24

Component Description:
Legal services cost. #475852
Amount:
$957.50

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1055
Amount:
$243.38

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #466690
Amount:
$446.87

Component Description:
Legal services cost. #473500
Amount:
$20.25

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 42 stations. #485630
Amount:
$405.83

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1117
Amount:
$282.68

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #472173
Amount:
$311.78

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1093
Amount:
$265.72

Component Description:
Legal services cost. #478343
Amount:
$153.75

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1078
Amount:
$215.68

Component Description:
Legal services cost. #480825
Amount:
$115.00

Component Description:
Legal Service Cost. #479374
Amount:
$3,783.75

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #107
Amount:
$602.28

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #478780
Amount:
$271.41

Component Description:
Legal services cost. #474487
Amount:
$57.50

Component Description:
Legal services cost. #482405
Amount:
$4,370.00

Component Description:
Legal services cost. #481392
Amount:
$3,086.55

Component Description:
Legal services cost. #484798
Amount:
$546.25

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1123
Amount:
$342.14

Component Description:
Legal services cost. #473491
Amount:
$51.25

Component Description:
Legal Service Cost. #479897
Amount:
$115.00

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1143
Amount:
$436.90

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1098
Amount:
$238.07

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 33 stations. #179
Amount:
$2,234.33

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 46 stations. #247
Amount:
$1,105.31

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1145
Amount:
$369.98

Component Description:
Legal Service Cost. #477400
Amount:
$512.50

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #470923
Amount:
$406.65

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1167
Amount:
$313.41

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #476885
Amount:
$403.34

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1039
Amount:
$30.47

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #471524
Amount:
$322.83

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1141
Amount:
$406.17

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1105
Amount:
$216.88

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #465001
Amount:
$596.30

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #464321
Amount:
$683.07

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1090
Amount:
$176.70

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #463567
Amount:
$566.48

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1069
Amount:
$246.68

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1039
Amount:
$30.47

Component Description:
Legal services cost. #475381
Amount:
$252.50

Component Description:
Legal Service Cost. #8372918
Amount:
$374.85

Component Description:
Outside professional service cost. #121520WYDO
Amount:
$2,049.00

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1051
Amount:
$105.97

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 99 stations. #469573
Amount:
$377.14

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #465173
Amount:
$654.26

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1072
Amount:
$237.64

Component Description:
Legal Service Cost. #483870
Amount:
$1,875.00

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #477305
Amount:
$393.53

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1111
Amount:
$159.58

Component Description:
Legal services cost. #479370
Amount:
$121.50

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #1063
Amount:
$262.29

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #1151
Amount:
$388.07

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #461759
Amount:
$29.98

Component Description:
Legal services cost. #471648
Amount:
$221.25

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations. #107
Amount:
$603.18
Sinclair Internal Costs

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 40 stations. #IL-SBG-09012021-LB
Amount:
$10.96

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$7.96

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 46 stations.
Amount:
$23.56

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$11.39

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 42 stations.
Amount:
$39.39

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 54 stations.
Amount:
$8.64

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 40 stations. #IL-SBG-08012021-SD
Amount:
$24.72

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 42 stations.
Amount:
$10.78

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 54 stations.
Amount:
$23.95

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$1.69

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 48 stations.
Amount:
$24.96

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 52 stations.
Amount:
$9.79

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$33.53

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 33 stations.
Amount:
$40.92

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$11.03

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$7.86

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$9.47

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$8.66

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 40 stations. #IL-SBG-09012021-SD
Amount:
$14.26

Component Description:
Portion of general repack matter internal time card attributable to this station - divided by 100.
Amount:
$66.55

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$6.09

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 60 stations.
Amount:
$23.77

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 33 stations.
Amount:
$15.86

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 60 stations.
Amount:
$4.95

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$25.53

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$17.02

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$16.53

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$32.09

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$26.93

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 31 stations.
Amount:
$4.10

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 46 stations.
Amount:
$1.53

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$15.08

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 52 stations.
Amount:
$41.33

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 31 stations.
Amount:
$52.76

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$23.96

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 100 stations.
Amount:
$5.37
RF Exposure Measurements Information not provided.
Comprehensive coverage verification via field study, if needed

Component Description:
UAS broadcast measurement. #207058
Amount:
$27,000.00
ASR modification (prepare FCC Form 854) Information not provided.
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet Information not provided.
NEPA Section 106 environmental review, if needed Information not provided.
Attorney Fees - Prepare and File request for Special Temporary Authorization Information not provided.
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #461759
Amount:
$99.92
Prepare request for Special Temporary Authorization

Component Description:
Consulting engineering cost. #868-13-0003
Amount:
$2,970.00

Component Description:
Outside professional service cost. #868-13-0004
Amount:
$926.25
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application

Component Description:
Outside professional service cost. #868-13-0005
Amount:
$1,496.25
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application

Component Description:
Outside professional service cost. #868-13-0003
Amount:
$4,230.00
Perform engineering study for new channel assignment and antenna development Information not provided.
Address transition timing and coordination issues w/ other stations and wireless Information not provided.
Prepare and or review reimbursement form

Component Description:
Portion of general repack matter invoice attributable to this station - divided by 98 stations. #461759
Amount:
$869.30

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $83,564.21 $82,959.21 N/A ($18,145.52) N/A
Total for all systems $4,187,865.16 $3,279,082.59 N/A $1,213,905.28 N/A
Other Expenses $83,564.21 $82,959.21 ($18,145.52)
True-up $0.00 $0.00 N/A ($42,693.54) N/A
MVPD Notification of Channel Change $20,000.00 $20,000.00 N/A N/A N/A
Develop and air announcement of upcoming channel change $20,000.00 $20,000.00 N/A N/A N/A
Equipment Storage $7,374.21 $7,374.21 N/A $7,374.21 N/A
Equipment Delivery and Handling Charges $20,000.00 $20,000.00 N/A $14,223.81 N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $2,000.00 $2,000.00 N/A N/A N/A
Local Zoning $1,000.00 $1,000.00 N/A N/A N/A
FCC Filing Fees - Special Temporary Authorization request $195.00 $190.00 N/A N/A N/A
DTV Medical Facility Notification $11,550.00 $11,000.00 N/A $2,950.00 N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $325.00 N/A N/A N/A
FCC Filing Fees - Form 2100 minor change CP application $1,110.00 $1,070.00 N/A N/A N/A

Components

Actual Information Description File Name
True-up

Component Description:
Dielectric True-up. #CM-2021-10-12-WYDO
Amount:
($42,693.54)
MVPD Notification of Channel Change Information not provided.
Develop and air announcement of upcoming channel change Information not provided.
Equipment Storage

Component Description:
Total invoice amount reduced by 25.40%. #682006
Amount:
$6,184.34

Component Description:
Total invoice amount reduced by 25.40%. #682011
Amount:
$1,189.87
Equipment Delivery and Handling Charges

Component Description:
Equipment delivery and handling cost reduced by 8.40%. #938004
Amount:
$3,060.58

Component Description:
Equipment freight cost. #943006
Amount:
$634.33

Component Description:
Equipment delivery and handling cost reduced by 8.40%. #931004
Amount:
$142.63

Component Description:
Total invoice amount reduced by 25.40%. #682006
Amount:
$6,032.52

Component Description:
Equipment delivery and handling cost reduced by 8.40%. #943006
Amount:
$692.50

Component Description:
Total invoice amount reduced by 8.40%. #695030
Amount:
$1,382.81

Component Description:
Total invoice amount reduced by 25.40%. #682011
Amount:
$2,970.94
Disposal Costs (for equipment and other waste, net of any salvage value) Information not provided.
Local Zoning Information not provided.
FCC Filing Fees - Special Temporary Authorization request Information not provided.
DTV Medical Facility Notification

Component Description:
Medical notification cost. #1222
Amount:
$2,950.00
FCC Filing Fees - Form 2100 license to cover application Information not provided.
FCC Filing Fees - Form 2100 minor change CP application Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $4,187,865.16 $3,279,082.59 $1,213,905.28

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. No
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Lisa Asher

Secretary


12/07/2021

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Lisa Asher

Secretary


12/07/2021