Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
GREENVILLE (KTXD-TV) LICENSEE, INC. Doing Business As: GREENVILLE (KTXD-TV) LICENSEE, INC. |
Lisa Asher 2000 W. 41ST STREET BALTIMORE, MD 21030 United States |
+1 (410) 568-1500 | LAsher@cunninghambroadcasting.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Paul A Cicelski , Esq . Lerman Senter PLLC |
Paul A. Cicelski 2001 L Street, NW WASHINGTON, DC 20036 United States |
+1 (202) 416-6756 | pcicelski@lermansenter.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | Please see attached Transition Plan Narrative. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Retune Existing |
Use | Auxiliary (Backup) | |
Ownership | Owned | |
Owner | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | Harris |
Model | ULX-4700AT | |
Year | 2009 | |
Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 5 kW |
Section | Question | Response |
---|---|---|
New IOT Tubes | Number of Tubes (including accessories) needed | N/A |
New Mask Filter | ||
Power | 7 kW | |
Other Power | N/A | |
New Exciter | Is a new exciter needed? | No |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Use as Interim |
Move and install existing auxiliary transmitter to interim site then move it back and reinstall. |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | CDP3100P1 | |
Year | 2005 | |
Type | Inductive Output Tube | |
IOT Power Type | Single | |
Power Capacity | 21 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | THU9EVO-36 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 55 kW | |
Justification for New Transmitter | Existing transmitter is not supported for retuning. Station plans to file for maximization as stated in the filed application for minor modification to better match existing service area. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | Yes |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 300 kVA | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | Yes | |
Description | Electrical installation for new transmitter. | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 25 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | Yes |
Size | 550.0 square feet | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Horizontal Line Run |
Horizontal Line Run |
Additional Equipment |
Additional Transmitter Parts |
10 Ton System |
10 Ton System |
Suite Civil Work |
Suite preparation includes preparation includes paint, floor epoxy, concrete equipment pad, and demolition work |
Installation |
Installation |
Single Rack Conversion |
Single Rack Conversion |
Ice Shield |
Ice Protection over the mechanical slab and the equipment for new HVAC units, heat exchangers and repack broadcasters equipment to be installed. |
Move generator |
Move existing 300kW generator from the current site to the final site and install. Requires new pad, standalone ice shield and underground electrical. |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Lease New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Owner | American Tower Corporation | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | Yes | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 4 | |
Number of Panels | 36 | |
Design power capacity in use | 92.5 % | |
Lower Limit | 605.00 MHz | |
Upper Limit | 665.00 MHz | |
Other Antenna Type | N/A | |
ERP: | 600.0 kW | |
Manufacturer | ||
Model | PHP36C | |
Year | 2003 |
Facility ID | Call Sign |
---|---|
22201 | KDAF |
49326 | KDTN |
67910 | KDTX-TV |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Lease New | |
Is this a request for upgraded equipment? | Yes | |
Ownership | Leased | |
Owner | American Tower Corporation | |
Is antenna shared? | Yes | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Broadband Panel | |
Number of Stations Supported | 4 | |
Number of Panels/Bays | 48 | |
Lower Limit | 482.00 MHz | |
Upper Limit | 608.00 MHz | |
Design power capacity in use | 65.0 % | |
Other Antenna Type | N/A | |
ERP: | 377.0 kW | |
Manufacturer | ||
Model | TUM-AP-C4-14/48H-2-B | |
Year | 2017 | |
Justification for New Antenna | Please see attached American Tower Corporation Transition Plan |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 5 | |
Frequencies of channels supported | RF channel | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | No | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Broadband | |
Feed Line Size | 7 3/16 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
RF Channel Number |
---|
18 |
19 |
23 |
29 |
21 |
Name | Description |
---|---|
Combiner Installation |
Installation of the combiner; Dual chain combiner system, Single chain of 2 constant impedance waveguide modules, and/or single chain of 2 directional filter modules per Dielectric layout plus a third low power filter for the wideband port. |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Lease New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Owner | ATC | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | Yes | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 8 3/16 inches | |
Other Diameter | N/A | |
Segment Length | Broadband | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 1507 feet per run |
Facility ID | Call Sign |
---|---|
67910 | KDTX-TV |
22201 | KDAF |
49326 | KDTN |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Lease New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 7 3/16 inches | |
Other Diameter | N/A | |
Segment Length | Broadband | |
Other Segment Length | N/A | |
Number of parallel runs | 2 | |
Length | 1650 feet per run | |
Justification for New Transmission Line | Please see attached American Tower Corporation Transition Plan |
Name | Description |
---|---|
Transmission Line Bridge |
New Ice Bridge required to support new transmission lines from all four repack tenants space to tower, estimated to be 200 linear ft. This cost includes the materials, foundations and installation. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | Candelabra | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1055009 | |
Coordinates (NAD83) | Latitude (NAD83) | 32° 35' 22.0" N- |
Longitude (NAD83) | 096° 58' 12.9" W- | |
Overall Structure Height | 1550.83 feet | |
Support Structure Height | 1453.07 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 829.71 feet | |
Structure Type | GTOWER - Guyed Structure Used for Communication Purposes | |
Tower Owner | American Tower, LLC | |
Date Constructed | 11/04/2008 |
Facility ID | Call Sign | Service |
---|---|---|
23084 | KHKS | FM |
26950 | KATA-CD | DTV |
35841 | KUVN-DT | DTV |
47739 | KDMX | FM |
41380 | KLNO | FM |
18114 | KEGL | FM |
11451 | WRR | FM |
6378 | KZPS | FM |
9620 | KDGE | FM |
14524 | KCBI | FM |
59702 | KKDA-FM | FM |
Users |
---|
KVFW-LD |
K31GL-D |
KHPK-LD |
KJJM-LD |
KNAV-LP |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for tower with candelabra |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Serious Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Candelabra |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Ground and Building A and E Permit Drawing Package |
The generation of a construction drawing package for one broadcaster. |
Construction Project management Tower Modifications Reinforcements and Facilities |
60 hours on Modification project management and RF installation project management. |
Tower Permit Drawing Package |
The generation of a construction drawing package for one broadcaster. |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | Candelabra | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1059733 | |
Coordinates (NAD83) | Latitude (NAD83) | 32° 32' 36.0" N- |
Longitude (NAD83) | 096° 57' 33.0" W- | |
Overall Structure Height | 1635.15 feet | |
Support Structure Height | 1523.60 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 813.97 feet | |
Structure Type | GTOWER - Guyed Structure Used for Communication Purposes | |
Tower Owner | American Towers, LLC | |
Date Constructed | 06/18/2000 |
Facility ID | Call Sign | Service |
---|---|---|
60534 | KSTR-DT | DTV |
49326 | KDTN | DTV |
49324 | KERA-TV | DTV |
22201 | KDAF | DTV |
68834 | KPXD-TV | DTV |
1087 | KRLD-FM | FM |
51517 | KTXA | DTV |
17037 | KDFI | DTV |
55768 | KKXT | FM |
28624 | KVIL | FM |
67910 | KDTX-TV | DTV |
23422 | KTVT | DTV |
41380 | KLNO | FM |
49323 | KERA | FM |
23440 | KMVK | FM |
63779 | KJKK | FM |
42359 | KTXD-TV | DTV |
67195 | KLUV | FM |
9627 | KBFB | FM |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | Candelabra |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 450 | |
Explanation | The station will contract for Project Management services to handle the complete project. It does not have personnel available for any of these tasks, nor is the staff trained to provide any of these services. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
NEPA Section 106 environmental review | Yes | |
Environmental Assessment | Yes | |
ASR Modification | Yes | |
FAA Consultation (including preparation of FAA Form 7460) | Yes | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | Yes | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
Migratory Bird Assessment Permitting |
Migratory Bird Assessment Permitting |
RF System Test |
Testing of the combiner to ensure all one (1) frequencies are tuned for optimal patterns. |
Sinclair Internal Costs |
Internal Employee Time Costs |
Site Coordination Meeting |
Site coordination meetings with all broadcasters, contractors and vendors involved with the site deliveries and construction. |
Site Survey |
Site Survey |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
Construction and Electrical Permits |
2% construction cost, excluding the material and equipment for electrical and building permits. |
Site Security |
Site security for installation and storage of Transmission line and materials for 57 days X 12 hours. The materials are a high risk of theft due to the material makeup such as copper, brass and aluminum. |
Tree Clearing |
This cost is for the removal of trees and vegetation to ensure the proper clearance of taglines and laydown areas, required for construction. |
True-up |
True-up |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $3,243,588.39 | $1,087,587.81 | N/A | $809,216.09 | N/A |
Total for all systems | $7,865,286.60 | $2,231,222.22 | N/A | $1,807,870.62 | N/A |
Primary Transmitter THU9EVO-36 | $3,095,178.39 | $944,087.81 | $809,216.09 | ||
Move generator | $3,706.00 | $3,706.00 | See attached Generator Move Quotation. | $3,706.00 | N/A |
Ice Shield | $53,329.92 | $53,329.92 | Please see attached ATC Transition Plan | $53,329.92 | The need more information can be deleted. |
Single Rack Conversion | $2,914.00 | $2,914.00 | N/A | $2,914.00 | N/A |
Installation | $86,313.00 | $86,313.00 | N/A | $86,313.00 | The need more information can be deleted. |
Suite Civil Work | $106,606.00 | $106,606.00 | See American Tower Quote. | $106,606.00 | N/A |
10 Ton System | $36,046.98 | $36,046.98 | N/A | $36,046.98 | The need more information can be deleted. |
Additional Equipment | $9,552.00 | $9,552.00 | N/A | $9,552.00 | N/A |
Horizontal Line Run | $21,012.00 | $21,012.00 | N/A | $21,012.00 | The need more information can be deleted. |
Other -- Building Addition Size: 550.0 | $17,330.80 | $17,330.80 | The building upgrade is required to accommodate the repack equipment. The current building configuration will need to be altered. See attached American Tower Corporation quote. | $17,330.80 | N/A |
25 Ton system | $91,500.00 | $8,250.20 | Please see attached ATC Transition Plan | $8,250.20 | N/A |
Other Electrical Service: Electrical installation for new transmitter. | $105,467.69 | $105,467.69 | Electrical distribution to the new transmitter. Parts and installation. | $105,467.69 | The marsand need more information can be deleted |
Transformer 3 phase/480v - 300 KVA | $36,800.00 | $35,000.00 | N/A | $4,500.00 | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $12,000.00 | N/A | $12,000.00 | N/A |
Service entrance 3 phase/800 amp/208 volt | $14,400.00 | $13,700.00 | N/A | N/A | N/A |
UHF - Liquid Cooled Solid State Transmitter 52 - 61 kW | $1,788,000.00 | $342,187.50 | N/A | $251,515.78 | N/A |
UHF - Liquid Cooled Solid State Transmitter 14.2 - 20 kW | $684,000.00 | $90,671.72 | ***System Notice: Estimate adjusted and locked because line has been superseded.*** | $90,671.72 | N/A |
Auxiliary Transmitter ULX-4700AT | $148,410.00 | $143,500.00 | $0.00 | ||
7 kW mask filter | $6,210.00 | $6,500.00 | See Marsand comparable | $0.00 | N/A |
UHF and VHF - minor banding issues | $105,200.00 | $100,000.00 | Catalog | N/A | N/A |
Use as Interim | $37,000.00 | $37,000.00 | See attached quote for Auxiliary Transmitter - use as interim | N/A | N/A |
Actual Information Description | File Name |
---|---|
Move generator | |
Ice Shield | |
Single Rack Conversion | |
Installation | |
Suite Civil Work | |
10 Ton System | |
Additional Equipment | |
Horizontal Line Run | |
Other -- Building Addition Size: 550.0 | |
25 Ton system | |
Other Electrical Service: Electrical installation for new transmitter. | |
Transformer 3 phase/480v - 300 KVA | |
Switchgear - industrial 800 amp | |
Service entrance 3 phase/800 amp/208 volt | Information not provided. |
UHF - Liquid Cooled Solid State Transmitter 52 - 61 kW | |
UHF - Liquid Cooled Solid State Transmitter 14.2 - 20 kW | |
7 kW mask filter | |
UHF and VHF - minor banding issues | Information not provided. |
Use as Interim | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,208,943.50 | $241,884.38 | N/A | $241,884.38 | N/A |
Total for all systems | $7,865,286.60 | $2,231,222.22 | N/A | $1,807,870.62 | N/A |
Primary Antenna TUM-AP-C4-14/48H-2-B | $1,208,943.50 | $241,884.38 | $241,884.38 | ||
UHF - High Power Top Mount (200-1000 kW), Four Station broadband panel antenna, elliptically or circularly polarized | $1,090,000.00 | $157,847.43 | See American Tower Quote. | $157,847.43 | N/A |
Combiner Installation | $11,163.50 | $11,163.50 | See attached American Tower Corporation quote. | $11,163.50 | N/A |
Elbow complex, broadband, at antenna input, per 7 3/16. feedline (if needed) | $16,850.00 | $9,166.25 | See attached American Tower Corporation quote. | $9,166.25 | N/A |
New combiner, cost per channel (without antenna) | $84,200.00 | $58,707.20 | See attached American Tower Corporation quote | $58,707.20 | N/A |
Sweep test of existing antenna | $6,730.00 | $5,000.00 | See attached American Tower Corporation quote. | $5,000.00 | N/A |
Actual Information Description | File Name |
---|---|
UHF - High Power Top Mount (200-1000 kW), Four Station broadband panel antenna, elliptically or circularly polarized | |
Combiner Installation | |
Elbow complex, broadband, at antenna input, per 7 3/16. feedline (if needed) | |
New combiner, cost per channel (without antenna) | |
Sweep test of existing antenna |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,135,141.50 | $362,335.27 | N/A | $362,335.27 | N/A |
Total for all systems | $7,865,286.60 | $2,231,222.22 | N/A | $1,807,870.62 | N/A |
Primary Transmission Line | $1,135,141.50 | $362,335.27 | $362,335.27 | ||
Transmission Line Bridge | $36,241.50 | $36,241.50 | See attached American Tower Corporation quote. | $36,241.50 | N/A |
Rigid Transmission Line - copper, 7 3/16" broadband | $1,098,900.00 | $326,093.77 | See attached American Tower Corporation quote. | $326,093.77 | N/A |
Actual Information Description | File Name |
---|---|
Transmission Line Bridge | |
Rigid Transmission Line - copper, 7 3/16" broadband |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,931,350.40 | $246,690.70 | N/A | $246,690.70 | N/A |
Total for all systems | $7,865,286.60 | $2,231,222.22 | N/A | $1,807,870.62 | N/A |
Primary Tower GTOWER | $421,000.00 | $0.00 | $0.00 | ||
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $0.00 | This appears to be a duplicate. | N/A | N/A |
Primary Tower GTOWER | $1,510,350.40 | $246,690.70 | $246,690.70 | ||
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | $421,000.00 | $51,502.50 | See attached American Tower Corporation quote. | $51,502.50 | N/A |
Construction Project management Tower Modifications Reinforcements and Facilities | $14,650.40 | $14,650.40 | See attached American Tower Corporation quote. | $14,650.40 | N/A |
Ground and Building A and E Permit Drawing Package | $2,700.00 | $2,700.00 | See attached American Tower Corporation quote. | $2,700.00 | N/A |
Tower Permit Drawing Package | $0.00 | $0.00 | See attached American Tower Corporation quote. | $0.00 | N/A |
Serious tower reinforcement/modifications | $1,052,000.00 | $169,077.80 | See attached American Tower Corporation quote. | $169,077.80 | N/A |
Structural engineering tower load study for a documented tower with candelabra | $20,000.00 | $8,760.00 | See attached American Tower Corporation quote. ($4,960 - mapping / $3,910 - study) | $8,760.00 | N/A |
Actual Information Description | File Name |
---|---|
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | Information not provided. |
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) | |
Construction Project management Tower Modifications Reinforcements and Facilities | |
Ground and Building A and E Permit Drawing Package | |
Tower Permit Drawing Package | |
Serious tower reinforcement/modifications | |
Structural engineering tower load study for a documented tower with candelabra |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $255,958.83 | $202,970.08 | N/A | $99,807.98 | N/A |
Total for all systems | $7,865,286.60 | $2,231,222.22 | N/A | $1,807,870.62 | N/A |
Outside Professional Services | $255,958.83 | $202,970.08 | $99,807.98 | ||
Sinclair Internal Costs | $568.83 | $568.83 | N/A | $568.83 | N/A |
Site Survey | $5,000.00 | $5,000.00 | N/A | $5,000.00 | The need more information can be deleted. |
Site Coordination Meeting | $2,000.00 | $2,000.00 | See attached American Tower Corporation quote. | $2,000.00 | N/A |
RF System Test | $10,000.00 | $10,000.00 | See attached American Tower Corporation quote. | $6,250.00 | N/A |
Migratory Bird Assessment Permitting | $350.00 | $350.00 | See attached American Tower Corporation quote. | N/A | N/A |
RF Exposure Measurements | $21,050.00 | $3,000.00 | See attached American Tower Corporation quote. | N/A | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $80,000.00 | N/A | $27,000.00 | N/A |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
ASR modification (prepare FCC Form 854) | $2,105.00 | $2,000.00 | N/A | N/A | N/A |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | $10,520.00 | $10,000.00 | N/A | N/A | N/A |
NEPA Section 106 environmental review, if needed | $6,310.00 | $1,080.00 | See attached American Tower Corporation quote. | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $7,360.00 | $0.00 | N/A | N/A | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $4,210.00 | $0.00 | N/A | N/A | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $0.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $155.00 | N/A | $155.00 | N/A |
Prepare request for Special Temporary Authorization | $4,100.00 | $3,000.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $2,066.25 | See Carl T. Jones Corporation invoices. | $2,066.25 | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | $0.00 | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $6,250.00 | See American Tower quotes. | $6,250.00 | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,500.00 | N/A | $2,500.00 | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | $2,099.67 | N/A |
Project management of the transition | $71,100.00 | $67,500.00 | N/A | $45,918.23 | N/A |
Actual Information Description | File Name |
---|---|
Sinclair Internal Costs | |
Site Survey | |
Site Coordination Meeting | |
RF System Test | |
Migratory Bird Assessment Permitting | Information not provided. |
RF Exposure Measurements | Information not provided. |
Comprehensive coverage verification via field study, if needed | |
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase | Information not provided. |
ASR modification (prepare FCC Form 854) | Information not provided. |
Environmental Assessment, if triggered by NEPA Section 106 review or for certain structures over 450 feet | Information not provided. |
NEPA Section 106 environmental review, if needed | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | Information not provided. |
Attorney Fees - Negotiation of lease and other matters for shared locations | Information not provided. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Perform engineering study for new channel assignment and antenna development | |
Address transition timing and coordination issues w/ other stations and wireless | |
Prepare and or review reimbursement form | |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $90,303.98 | $89,753.98 | N/A | $47,936.20 | N/A |
Total for all systems | $7,865,286.60 | $2,231,222.22 | N/A | $1,807,870.62 | N/A |
Other Expenses | $90,303.98 | $89,753.98 | $47,936.20 | ||
True-up | $0.00 | $0.00 | N/A | ($4,972.76) | N/A |
Tree Clearing | $1,600.00 | $1,600.00 | See attached American Tower Corporation quote. | $0.00 | N/A |
Site Security | $0.00 | $0.00 | See attached American Tower Corporation quote. | $0.00 | N/A |
Construction and Electrical Permits | $0.00 | $0.00 | See attached American Tower Corporation quote. | $0.00 | N/A |
Develop and air announcement of upcoming channel change | $500.00 | $500.00 | N/A | N/A | N/A |
Equipment Storage | $16,935.00 | $16,935.00 | N/A | $16,935.00 | The marsand need more information can be deleted. |
Equipment Delivery and Handling Charges | $23,092.98 | $23,092.98 | N/A | $23,092.98 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $16,500.00 | $16,500.00 | Pre-auction channel transmitter and interior RF system dismantling, removal and disposal including coolant and oil reclamation. | $5,089.75 | N/A |
Non-zoning permits | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | $4,250.00 | N/A |
Local Zoning | $5,126.00 | $5,126.00 | See attached American Tower Corporation quote. | $3,541.23 | N/A |
MVPD Notification of Channel Change | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
True-up | |
Tree Clearing | |
Site Security | |
Construction and Electrical Permits | |
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Storage | |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | |
Non-zoning permits | Information not provided. |
DTV Medical Facility Notification | |
Local Zoning | |
MVPD Notification of Channel Change | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $7,865,286.60 | $2,231,222.22 | $1,807,870.62 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lisa Asher Secretary 09/21/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Lisa Asher Secretary 09/21/2021 |