Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
L4 MEDIA GROUP, LLC Doing Business As: L4 MEDIA GROUP, LLC |
PO Box 60606 Suite 2450 Chicago, IL 60606 United States |
+1 (612) 202-4980 | ssaldana@sktytrading.com | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Tim Wolak Director Banded IT Solutions |
2425 Bentshire Dr Jacksonville, FL 32246 United States |
+1 (312) 231-7895 | twolak@bandeditsolutions.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Current transmission system consists of a single transmitter feeding a flexible transmission line which connects to an antenna on the tower. Work includes tower study/rehabilitation to support new antenna, mounting antenna and retuning transmitter. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Retune Existing |
Use | Primary (Main) | |
Ownership | Owned | |
Owner | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | Elettronika |
Model | TXUD1000 | |
Year | 2015 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 1.0 kW |
Section | Question | Response |
---|---|---|
New IOT Tubes | Number of Tubes (including accessories) needed | N/A |
New Mask Filter | ||
Power | 3 kW | |
Other Power | N/A | |
New Exciter | Is a new exciter needed? | No |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | No |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Leased | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1034290 | |
Coordinates (NAD83) | Latitude (NAD83) | 28° 34' 07.8" N- |
Longitude (NAD83) | 081° 13' 53.8" W- | |
Overall Structure Height | 359.90 feet | |
Support Structure Height | 359.90 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 73.16 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Lovelace Tower, Inc. | |
Date Constructed | 03/11/2005 |
Facility ID | Call Sign | Service |
---|---|---|
10549 | WRCF-CD | DTV |
Users |
---|
LPFM |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for undocumented/poorly documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Minor Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 200 | |
Explanation | Applicant has no internal resources capable of overseeing, identifying, purchasing, installing and commissioning this repack project. It will rely solely on outside services to manage all work required. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | Yes |
RF exposure measurements | No | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
MSW reports |
MSW services to prepare files for FCC reporting post repack |
Progress Reporting |
Prepare and file 9 required progress reports on FCC Form 2100, Schedule 387 on a quarterly basis with the FCC. |
ACME RF |
Project Management services, research and project coordination |
Fletcher, Heald and Hildreth |
Attorney for repack services to prepare, file all required FCC forms and coordination of repack efforts. |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | No |
Name | Description |
---|---|
Construction Drawings |
Provide construction drawing set for local building permit |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $109,355.00 | $19,340.00 | N/A | $19,340.00 | N/A |
Total for all systems | $587,240.00 | $356,883.75 | N/A | $124,410.37 | N/A |
Primary Transmitter TXUD1000 | $109,355.00 | $19,340.00 | $19,340.00 | ||
UHF and VHF - minor banding issues | $105,200.00 | $15,000.00 | N/A | $15,000.00 | N/A |
3 kW mask filter | $4,155.00 | $4,340.00 | the predetermined budget did not equal the actual expense | $4,340.00 | N/A |
Actual Information Description | File Name |
---|---|
UHF and VHF - minor banding issues | |
3 kW mask filter |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $268,500.00 | $188,000.00 | N/A | $6,420.00 | N/A |
Total for all systems | $587,240.00 | $356,883.75 | N/A | $124,410.37 | N/A |
Primary Tower TOWER | $268,500.00 | $188,000.00 | $6,420.00 | ||
Minor tower reinforcement/modifications | $158,000.00 | $100,000.00 | N/A | N/A | N/A |
Short Tower (less than 500') | $84,200.00 | $63,000.00 | N/A | N/A | N/A |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study | $26,300.00 | $25,000.00 | N/A | $6,420.00 | N/A |
Actual Information Description | File Name |
---|---|
Minor tower reinforcement/modifications | Information not provided. |
Short Tower (less than 500') | Information not provided. |
Tower mapping for an undocumented/poorly documented tower and preparation of documentation necessary for tower load study |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $177,800.00 | $122,313.75 | N/A | $85,755.37 | N/A |
Total for all systems | $587,240.00 | $356,883.75 | N/A | $124,410.37 | N/A |
Outside Professional Services | $177,800.00 | $122,313.75 | $85,755.37 | ||
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | $3,776.25 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | $2,716.25 | N/A |
Fletcher, Heald and Hildreth | $5,000.00 | $5,000.00 | N/A | $4,596.67 | N/A |
ACME RF | $15,000.00 | $15,000.00 | N/A | $15,000.00 | N/A |
Progress Reporting | $18,000.00 | $18,000.00 | Prepare and file 9 required progress reports on FCC Form 2100, Schedule 387 on a quarterly basis with the FCC. | $1,192.50 | N/A |
MSW reports | $1,650.00 | $1,650.00 | N/A | $1,523.75 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | $582.29 | N/A |
Comprehensive coverage verification via field study, if needed | $84,200.00 | $30,000.00 | N/A | $30,000.00 | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $8,413.75 | additional RF modeling was required due to congestion in the DMA | $8,413.75 | Additional RF modeling was required due to congestion in the DMA |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | N/A | N/A |
Project management of the transition | $31,600.00 | $30,000.00 | N/A | $17,953.91 | N/A |
Actual Information Description | File Name |
---|---|
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Fletcher, Heald and Hildreth | |
ACME RF | |
Progress Reporting | |
MSW reports | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Comprehensive coverage verification via field study, if needed | |
Perform engineering study for new channel assignment and antenna development | |
Prepare and or review reimbursement form | Information not provided. |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $31,585.00 | $27,230.00 | N/A | $12,895.00 | N/A |
Total for all systems | $587,240.00 | $356,883.75 | N/A | $124,410.37 | N/A |
Other Expenses | $31,585.00 | $27,230.00 | $12,895.00 | ||
Disposal Costs (for equipment and other waste, net of any salvage value) | $1,000.00 | $1,000.00 | Applicant will be required to dispose of the current pre-repack antenna and parts that were replaced for transmitter retuning. The exact costs are not known at this time. | N/A | N/A |
Non-zoning permits | $2,000.00 | $2,000.00 | It is currently unknown what the city or county may levy on applicant in terms of a building permit to perform the tower work required. It is felt this estimate should cover the associated costs for any required permits. | N/A | N/A |
Local Zoning | $2,000.00 | $2,000.00 | It is currently unknown what the local zoning authority or city/county may levy on applicant to perform the tower work required. It is felt this estimate should cover the associated costs for any required permits. | $1,000.00 | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | the fcc changed the fee | $0.00 | N/A |
DTV Medical Facility Notification | $11,550.00 | $7,195.00 | N/A | $7,195.00 | BUDGET WAS ESTIMATED BEFORE WE RECEIVED THE ACTUAL QUOTE FROM THE VENDOR |
Develop and air announcement of upcoming channel change | $2,500.00 | $2,500.00 | It is required that the applicant give notification to viewers of the repack channel change. Applicant has limited internal resources to create and produce such notifications and will most likely have to obtain the services from an outside vendor. | N/A | N/A |
Equipment Storage | $2,500.00 | $2,500.00 | Applicant may receive antenna and transmitter parts prior to set installation dates. There is no on-site storage available and applicant may be forced to use outside temporary storage facilities. | N/A | N/A |
Equipment Delivery and Handling Charges | $5,000.00 | $5,000.00 | There will be shipping charges for the antenna and transmitter costs. Precise costs will not be known until the carrier issues an invoice. Currently, applicant does not estimate costs to be more than this estimate. | N/A | N/A |
Construction Drawings | $4,700.00 | $4,700.00 | required for building permit process | $4,700.00 | N/A |
Actual Information Description | File Name |
---|---|
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
Non-zoning permits | Information not provided. |
Local Zoning | |
FCC Filing Fees - Form 2100 license to cover application | |
DTV Medical Facility Notification | |
Develop and air announcement of upcoming channel change | Information not provided. |
Equipment Storage | Information not provided. |
Equipment Delivery and Handling Charges | Information not provided. |
Construction Drawings |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $587,240.00 | $356,883.75 | $124,410.37 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Tim Wolak Director 06/10/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Tim Wolak Director 06/10/2021 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Tim Wolak Director 06/10/2021 |