Facility ID:
168737
Service:
LPD
Call Sign:
WHNE-LD
Channel:
3 (Low VHF)
File Number:
0000089995
FRN:
0032881088
Eligibility Status:
Eligible
Date Submitted:
08/18/2021

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

TAIT BROADCASTING, LLC

Doing Business As: TAIT BROADCASTING, LLC

JAMES LEBRATO

27251 STATE ROAD 54

SUITE B14-124

WESLEY CHAPEL, FL 33544

United States

+1 (813) 230-1430 JAMESVL54@AOL.COM Limited Liability Company

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

Tony Zummallen

President

QCommunications, LLC

Tony Zummallen

705B SE Melody Lane #314

Lee's Summit, MO 64063

United States

+1 (816) 729-1177 tony@Qcomm.tv

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan Replace the transmitter and antenna per the channel reassignment with reasonable and customary engineering and business practices.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Ownership Owned
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model AT71KO-1
Year 2010
Type Solid State
Solid State Cooling Air Cooled
Solid State Power Capacity 1.1 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? No
Manufacturer
Model VAXTE-4L
Transmitter Type Solid State
Solid State Cooling Air Cooled
Solid State Power capacity 5 kW
Justification for New Transmitter Transitioning from UHF to VHF. New antenna has lower gain.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Other Transmitter Costs
Does the transmitter installation require a Transmitter Building Site Survey/Installation? Yes
Electrical Service Service Entrance (3 phases 800A 208V) Yes
Switchgear (industrial 800 amp) No
Transformer (480V) No
Rigid Conduit and Wiring No
Other Electrical Service No
HVAC Service Does the replacement transmitter require HVAC Service? No
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Transmitter Shipping fee

Shipping fees for new transmitter

Transmitter Taxes

Sales tax for new transmitter

Transmitter Decommissioning

Harvesting and removal of old transmitter

Site Prep

Preparation of site for new transmitter

Transmitter Training

Onsite training for new transmitter

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Ownership Owned
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? Yes
Existing Antenna Manufacturer and Type
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Slotted Coaxial
ERP: 15.0 kW
Manufacturer
Model PSILP16AWR
Year 2014

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Change Type Purchase New
Ownership Owned
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Types
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Other
Other Antenna Type Panel
ERP: 5.0 kW
Manufacturer
Model PSIVLDP2EC-3
Year 2020
Justification for New Antenna Contour of new antenna is smaller than the original antenna.

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? Single Channel
Feed Line Size 1 5/8 inches inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna? Yes
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Antenna Shipping fee

Shipping fees for new antenna

Tower vendor mobilization fees

Transportation fees for rigging vendor

Antenna Sales Tax

Sales tax for new antenna

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? No

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Ownership Leased
Is this tower consider Complex? No
Is this tower currently shared with any other stations? No
Is tower documented for structural analysis? Yes
Is tower compliant with Rev G? Yes
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1003429
Coordinates (NAD83) Latitude (NAD83) 42° 26' 52.5" N-
Longitude (NAD83) 083° 10' 23.1" W-
Overall Structure Height 1086.93 feet
Support Structure Height 1012.13 feet
Ground Elevation Above Mean Sea Level (AMSL) 662.07 feet
Structure Type GTOWER - Guyed Structure Used for Communication Purposes
Tower Owner American Towers LLC
Date Constructed 06/11/1999


Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Tower mapping and report for structural engineer
Tower Reinforcements Please select whether tower reinforcements are needed: No reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower N/A
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Information not provided.

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 350
Explanation Required to assist in the turnkey management of the channel relocation project in order that the existing internal personal can maintain and operate the stations daily operational requirements and plans.
Outside RF consulting Engineering Services Perform engineering study for displacement application Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Prepare Form 601 Yes
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement Yes
Form 399 assistance or other program management costs Yes
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements No
Additional Field Engineering Service No

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Information not provided.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Permit and Filing Costs FCC Construction Permit Major Change Yes
FCC Construction Permit Minor Change Yes
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? Yes
Point to Point Microwave (STL/ICR) Frequency Coordination for Unidirection System No
Frequency Coordination for Bi-Direction System No
New Point to Point Microwave System No

Other Expenses

Back to Top

Other Expenses Not Listed

Information not provided.

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $140,224.18 $132,252.53 N/A $114,252.53 N/A
Total for all systems $509,828.38 $337,653.74 N/A $176,366.73 N/A
Primary Transmitter VAXTE-4L $140,224.18 $132,252.53 $114,252.53
Transmitter Building Site Survey/Installation $10,000.00 $12,628.35 Cost determined from invoices. $12,628.35 N/A
Service entrance 3 phase/800 amp/208 volt $14,400.00 $3,800.00 Cost determined by quote submitted by Talbot corporation on 10-7-2019 $3,800.00 N/A
Site Prep $8,000.00 $8,000.00 Site preparation including receiving and inventory of transmitter and components; prepare site for acceptance of transmitter; pre-assemble cabinets and subassemblies; ensure all installation materials are available for installation crew. N/A N/A
Transmitter Training $3,000.00 $3,000.00 4/2/2020- Working to obtain quote which may be delayed due to coronavirus pandemic. N/A N/A
Transmitter Decommissioning $7,000.00 $7,000.00 Estimated costs of harvesting and removal of old transmitter from site. Revised upon Site Survey. N/A N/A
Transmitter Taxes $6,316.80 $6,316.80 Sales tax for new transmitter. Refer to Inv: US0335124, US0336295 $6,316.80 N/A
Transmitter Shipping fee $2,232.75 $2,232.75 Estimated shipping fees for new transmitter. Actual costs to be determined. $2,232.75 N/A
Low VHF - Air Cooled Solid State Transmitter 5 kW $89,274.63 $89,274.63 Cost determined from invoices submitted. $89,274.63 LMS Correction

Components

Actual Information Description File Name
Transmitter Building Site Survey/Installation

Component Description:
Transmitter installation
Amount:
$12,628.35
Service entrance 3 phase/800 amp/208 volt

Component Description:
Installation of 3 phase electrical feeder for transmitter.
Amount:
$3,800.00
Site Prep Information not provided.
Transmitter Training Information not provided.
Transmitter Decommissioning Information not provided.
Transmitter Taxes

Component Description:
Sales Tax for 2kW Tx, adjusted. See quote and invoice.
Amount:
$6,316.80
Transmitter Shipping fee

Component Description:
Freight cost
Amount:
$2,232.75
Low VHF - Air Cooled Solid State Transmitter 5 kW

Component Description:
LMS correction
Amount:
$45,000.00

Component Description:
LMS correction
Amount:
$2,750.11

Component Description:
Delete this.
Amount:
N/A

Component Description:
LMS correction
Amount:
$41,524.52

Component Description:
Cost of Transmitter
Amount:
$41,524.52

Component Description:
Delete this.
Amount:
N/A

Component Description:
Cost of Transmitter
Amount:
$45,000.00

Component Description:
Delete This.
Amount:
N/A

Component Description:
Delete this.
Amount:
N/A

Component Description:
Delete This.
Amount:
N/A

Component Description:
Requesting Partial payment for transmitter cost.
Amount:
$2,750.11

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $46,054.00 $46,054.00 N/A $24,899.00 N/A
Total for all systems $509,828.38 $337,653.74 N/A $176,366.73 N/A
Primary Antenna PSIVLDP2EC-3 $46,054.00 $46,054.00 $24,899.00
Low VHF-Low Power, Side Mount, Other, 5.0kW input, Horizontal $24,737.00 $24,737.00 Antenna required for FCC repack $22,737.00 N/A
$0.00 $0.00 N/A N/A N/A
Elbow complex, single channel, 1 5/8” input (if needed) $6,900.00 $6,900.00 4/2/2020- Working to obtain quote which may be delayed due to coronavirus pandemic. N/A N/A
Sweep test of transmission line and antenna $5,730.00 $5,730.00 N/A N/A N/A
Antenna Shipping fee $2,462.00 $2,462.00 Estimated shipping fee for new antenna. Actual costs to be determined. See attached invoice from PSI uploaded on 5.7.20 $2,162.00 N/A
Side Mount antenna brackets $4,625.00 $4,625.00 N/A N/A N/A
Antenna Sales Tax $1,000.00 $1,000.00 Estimated sales tax for new antenna. Actual costs to be determined. N/A N/A
Tower vendor mobilization fees $600.00 $600.00 Per attached JT Tower Service quote. N/A N/A

Components

Actual Information Description File Name
Low VHF-Low Power, Side Mount, Other, 5.0kW input, Horizontal

Component Description:
Antenna for FCC LPTV repack
Amount:
$24,737.00

Component Description:
Credit Memo
Amount:
($2,000.00)
Information not provided.
Elbow complex, single channel, 1 5/8” input (if needed) Information not provided.
Sweep test of transmission line and antenna Information not provided.
Antenna Shipping fee

Component Description:
Actual cost of shipping for antenna
Amount:
$2,162.00
Side Mount antenna brackets Information not provided.
Antenna Sales Tax Information not provided.
Tower vendor mobilization fees Information not provided.

Cost Information

Back to Top

Transmission Line

Information not provided.

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $178,750.00 $4,950.00 N/A $4,950.00 N/A
Total for all systems $509,828.38 $337,653.74 N/A $176,366.73 N/A
Primary Tower GTOWER $178,750.00 $4,950.00 $4,950.00
Tower mapping and report for structural engineer $21,000.00 $750.00 Per attached ATC PE Letter quote. $750.00 N/A
Tower Rigging Tall Tower (greater than 500') $157,750.00 $4,200.00 N/A $4,200.00 N/A

Components

Actual Information Description File Name
Tower mapping and report for structural engineer

Component Description:
Structural analysis
Amount:
$750.00
Tower Rigging Tall Tower (greater than 500')

Component Description:
Antenna installation.
Amount:
$4,200.00

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $135,590.20 $145,187.21 N/A $32,265.20 N/A
Total for all systems $509,828.38 $337,653.74 N/A $176,366.73 N/A
Outside Professional Services $135,590.20 $145,187.21 $32,265.20
Form 399 assistance or other Program Management costs $27,265.20 $27,265.20 Cost determined by invoices. $27,265.20 N/A
Prepare Form 601 $755.00 $755.00 N/A N/A N/A
Project management of the transition $36,925.00 $53,900.00 Required to assist in the turnkey management of the channel relocation project in order that the existing internal personal can maintain and operate the stations daily operational requirements and plans. N/A N/A
Prepare/ Review 399 reimbursement form $1,710.00 $2,500.00 Per attached QCommunications quote. $2,500.00 N/A
Perform engineering study for displacement application $1,800.00 $2,500.00 Per attached invoice 1094 and 1218 from Greg Best Consulting Inc. Multiple evaluations of Detroit Market and displacement evaluations for UHF and VHF channels. Creation of all exhibits and other documentation for displacement application. $2,500.00 N/A
Prepare request for Special Temporary Authorization $1,280.00 $1,280.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $2,102.50 $2,102.50 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,052.50 $1,052.50 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $3,025.00 $3,025.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $1,577.50 $1,577.50 N/A N/A N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $3,262.50 $3,262.50 N/A N/A N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $2,235.00 $2,235.00 N/A N/A N/A
Comprehensive coverage verification via field study, if needed $52,600.00 $43,732.01 Per-attached quote number: QComm_Airborne_Division_Quote_LP_FCV_WHNE_01.12.21 (Signed) $0.00 N/A

Components

Actual Information Description File Name
Form 399 assistance or other Program Management costs

Component Description:
Project Management
Amount:
$585.20

Component Description:
Paperwork PM
Amount:
$2,448.60

Component Description:
Paperwork PM
Amount:
$1,493.80

Component Description:
Form 299 Assistance and PM costs
Amount:
$2,941.40

Component Description:
Paperwork PM
Amount:
$1,447.60

Component Description:
Paperwork PM
Amount:
$1,239.70

Component Description:
Project Management of Repack
Amount:
$3,218.60

Component Description:
PM Paperwork
Amount:
$739.20

Component Description:
PM Paperwork
Amount:
$985.60

Component Description:
PM Paperwork
Amount:
$924.00

Component Description:
PM Paperwork
Amount:
$246.40

Component Description:
Paperwork PM
Amount:
$1,262.80

Component Description:
PM Paperwork
Amount:
$877.80

Component Description:
PM Paperwork
Amount:
$231.00

Component Description:
Prepare and Process Form 399
Amount:
$500.00

Component Description:
Paperwork PM
Amount:
$1,848.00

Component Description:
Paperwork PM
Amount:
$3,696.00

Component Description:
Paperwork PM
Amount:
$2,579.50
Prepare Form 601 Information not provided.
Project management of the transition Information not provided.
Prepare/ Review 399 reimbursement form

Component Description:
Form 399 Submission
Amount:
$2,500.00
Perform engineering study for displacement application

Component Description:
Engineering Consulting services.
Amount:
$1,975.00

Component Description:
Displacement application. Work preformed by Greg Best
Amount:
$525.00

Component Description:
N/A
Amount:
N/A
Prepare request for Special Temporary Authorization Information not provided.
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application Information not provided.
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Negotiation of lease and other matters for shared locations Information not provided.
Attorney Fees - Prepare and File request for Special Temporary Authorization Information not provided.
Comprehensive coverage verification via field study, if needed Information not provided.

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $9,210.00 $9,210.00 N/A $0.00 N/A
Total for all systems $509,828.38 $337,653.74 N/A $176,366.73 N/A
Other Expenses $9,210.00 $9,210.00 $0.00
FCC Filing Fees - Form 2100 minor change CP application $1,110.00 $1,110.00 N/A N/A N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $335.00 N/A N/A N/A
FCC Filing Fees - Form 2100 Major change CP application $4,960.00 $4,960.00 N/A N/A N/A
FCC Filing Fees - Special Temporary Authorization request $305.00 $305.00 N/A N/A N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $1,000.00 $1,000.00 4-6 yard disposal bin on site to capture all waste from on site system integration and tower vendors. N/A N/A
Equipment Delivery and Handling Charges $1,000.00 $1,000.00 Transport, forklift rental and handling fees from staging area to transmitter site. N/A N/A
Equipment Storage $500.00 $500.00 Expecting multiple staggered equipment deliveries from different vendors and need to store and stage new equipment prior to installation date. N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $509,828.38 $337,653.74 $176,366.73

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. No
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Robert Naismith

MEMBER


08/18/2021

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Robert Naismith

MEMBER