Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
LIVING FAITH MINISTRIES, INC. Doing Business As: LIVING FAITH MINISTRIES, INC. |
1867 Abingdon, VA 24209 United States |
+1 (276) 676-3806 | lisa@livingfaithtv.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Timothy Z Sawyer Technical Consultant T Z Sawyer Technical Consultants |
2130 Hutchison Grove Court Suite 100 Falls Church, VA 22043 United States |
+1 (703) 848-2130 | tzsawyer@tzsawyer.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Please refer to attachment titled "WLFB Updated Repack Transition Plan Narrative Exhibit as of July 2019." |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | QXD1 | |
Year | 2001 | |
Type | Inductive Output Tube | |
IOT Power Type | Single | |
Power Capacity | 20 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | ULXTE-40 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 25.3 kW | |
Justification for New Transmitter | Existing xmitter cannot be re-channeled - channel change is 90 MHz shift (from Ch 40 to Ch 25). IOT operation not available, manufacturer no longer in business. See attached letter from manufacturer dated 1-1-2017. Please also see 9-6-19 xmitter exhibit. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | Yes | |
Size | 3 inches | |
Length | 250.0 feet | |
Other Electrical Service | Yes | |
Description | Incoming AC line surge suppression and disconnect switchgear. | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Electrical |
Electrical |
Site Survey |
Basic Site Survey |
RF Accessories |
RF Accessories |
Transmitter Removal |
Removal of old primary transmitter from facility |
Mask Filter System |
Mask Filter System |
Misc RF Components |
Additional RF components required for installation of transmitter - including but not limited to rf couplers and short transmission line lengths. |
Installation and Proof |
Installation and Proof |
Transmitter Site Access Road |
Truck turnaround for access and road prep for safe transport of WLFB repack equipment (CL Dale Proposal Attached) |
Installation RF Mask-Filter |
Installation expense related to the installation and positioning of the RF mask-filter in limited available space. |
Transmitter Building Electrical |
Transmitter Building Electrical |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels | N/A | |
Design power capacity in use | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Other Antenna Type | N/A | |
ERP: | 1000.0 kW | |
Manufacturer | ||
Model | 2100-32 | |
Year | 2001 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 739.0 kW | |
Manufacturer | ||
Model | ATW26H3-HSP230-25H | |
Year | 2019 | |
Justification for New Antenna | CURRENT CHANNEL IS ON CHANNEL 40 NEW CHANNEL IS CHANNEL 25. 90 MHZ FREQUENCY SHIFT. |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency | N/A | |
Do you need a combiner output splitter/switcher for dual feed lines? | N/A | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | Yes |
Broadband or Single Channel? | Single Channel | |
Feed Line Size | 6 1/8 inches inches | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | Yes |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Name | Description |
---|---|
Installation of Ice Shields |
Installation of Ice Shields |
Freight |
Freight |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
Number of Stations Supported | N/A | |
Number of Panels/Bays | N/A | |
Lower Limit | N/A | |
Upper Limit | N/A | |
Design power capacity in use | N/A | |
Other Antenna Type | N/A | |
ERP: | 300.0 kW | |
Manufacturer | ||
Model | ALP16M2-HSP-2S | |
Year | 2019 | |
Justification for New Antenna | Must remove old channel 40 antenna, prior to installation of new channel 25 antenna. Interim antenna allows for operation at a lower elevation on the existing tower. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | Yes |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Name | Description |
---|---|
Tower Rigging to Stabilize Tower during interim antenna transmission line work |
Tower Rigging to Stabilize Tower during interim antenna transmission line work |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 20 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 275 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | 19 1/2 inches | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 300 feet per run | |
Justification for New Transmission Line | RECHANNELED FROM CH 40 TO CH 25, LINE SEGMENT LENGTH REQUIRES 19-1/2 FT. OLD SEGMENT LENGTH IS 20 FT. |
Name | Description |
---|---|
Transmission Line Bridge Option |
Transmission Line Bridge Option (included in ERI New Tower Proposal) |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Type | Flexible Air | |
Diameter | 3 inches | |
Segment Length | N/A | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 324 feet per run | |
Justification for New Transmission Line | Interim use while main transmission line is removed from tower. |
Name | Description |
---|---|
Transmission Line Routing |
RF Interconnect components between transmission line and interim transmitter. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1219321 | |
Coordinates (NAD83) | Latitude (NAD83) | 37° 13' 12.3" N- |
Longitude (NAD83) | 081° 15' 19.0" W- | |
Overall Structure Height | 424.86 feet | |
Support Structure Height | 421.91 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 3837.88 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Living Faith Ministries, Inc. | |
Date Constructed | 09/30/2000 |
Facility ID | Call Sign | Service |
---|---|---|
52864 | WKQB | FM |
Users |
---|
ISP Provider |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Site Security |
Site security required during construction phase. |
RF Engineer Consultant |
Research regarding tower foundations, structural materials, ground penetration radar options |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1219321 | |
Coordinates (NAD83) | Latitude (NAD83) | 37° 13' 12.3" N- |
Longitude (NAD83) | 081° 15' 19.0" W- | |
Overall Structure Height | 424.86 feet | |
Support Structure Height | 421.91 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 3837.88 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Living Faith Ministries, Inc. | |
Date Constructed | 09/30/2000 |
Facility ID | Call Sign | Service |
---|---|---|
52864 | WKQB | FM |
Users |
---|
ISP Provider |
Section | Question | Response |
---|---|---|
Construct New Tower | Use | Primary (Main) |
Description of Use | N/A | |
Is this a request for upgraded equipment? | No | |
Height | 424.00 feet | |
Justification for New Tower | Please see attached exhibit "WLFB New Tower Justification July 2 2019.pdf". Also, please note that the design of the new tower is not yet finalized; as such, the 424 feet AGL height noted above is subject to change. |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Porta-Potty |
Porta-Potty (WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020) |
Tower Site Tree Removal Tower Site to Road |
Clear trees from tower site to road for stacking of old tower (WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020) |
Tower Site Fencing Guy Anchors |
New fence and gates at 3 tower guy anchors; remove old fences and gates (WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020) |
Addison Surveyors |
Survey services at Bluefield Tower Site |
Tower Site Fencing New Fence and Gate |
New fence and gate extending east end beyond new tower (WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020) |
ERI Geotechnical Survey for collection of soil core samples |
ERI Geotechnical Survey for collection of soil core samples (proposal attached) |
Radio Services |
Radio Antenna Install |
Tower Site Tree Removal New Guy Path |
Clear trees on new guy path 40 feed wide NE and South guy locations (WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020) |
Tower Site Fence East and West End Removal |
East and West End removal during project (WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020) |
Waste Disposal |
Large Dumpster for waste disposal (WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020) |
Installation |
Installation Services |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 100 | |
Explanation | Station does not have staff available. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | Yes | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
PROJECT PLANNING |
TX PHYSICAL LAYOUT REVIEW AND TRANSITION PLANNING |
Insurance Costs |
Insurance coverage for repack related equipment installation and transportation |
Additional Repack Legal Services Not Otherwise Specified in Form 399 |
Non-Catalog Legal Services such as review of quarterly transition status reports and other miscellaneous non-catalog legal fees. |
Interim Antenna Considerations |
Interim Antenna Considerations |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | Yes |
Non-zoning permits | Yes | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
Tower Lease and Tenant Correspondence |
Tower Lease and Tenant Correspondence |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,981,667.84 | $993,958.66 | N/A | $899,708.66 | N/A |
Total for all systems | $4,678,361.93 | $3,571,690.60 | N/A | $2,941,576.93 | N/A |
Primary Transmitter ULXTE-40 | $1,981,667.84 | $993,958.66 | $899,708.66 | ||
Transmitter Building Electrical | $31,700.00 | $31,700.00 | N/A | N/A | N/A |
Installation RF Mask-Filter | $3,500.00 | $3,500.00 | N/A | N/A | N/A |
Transmitter Site Access Road | $26,486.34 | $26,486.34 | N/A | $26,486.34 | Additional expenses were incurred as indicated in the attached invoices. |
Installation and Proof | $58,543.75 | $58,543.75 | N/A | $58,543.75 | N/A |
Misc RF Components | $6,000.00 | $6,000.00 | N/A | N/A | N/A |
Transmitter Removal | $4,500.00 | $4,500.00 | N/A | N/A | N/A |
RF Accessories | $64,134.44 | $64,134.44 | N/A | $64,134.44 | N/A |
Electrical | $7,122.72 | $7,122.72 | N/A | $7,122.72 | N/A |
Site Survey | $8,416.62 | $8,416.62 | N/A | $8,416.62 | Additional expenses were incurred as indicated in the attached invoices. |
Other Electrical Service: Incoming AC line surge suppression and disconnect switchgear. | $38,300.00 | $38,300.00 | Additional expenses were incurred as indicated in the attached invoices | $38,300.00 | Additional expenses were incurred as indicated in the attached invoices |
3" Rigid Conduit and Wiring (Cost per foot) | $13,000.00 | $12,250.00 | N/A | N/A | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $36,300.00 | N/A | N/A | N/A |
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW | $947,000.00 | $422,303.03 | Additional expenses were incurred as indicated in the attached invoices. | $422,303.03 | Additional expenses were incurred as indicated in the attached invoices. |
Mask Filter System | $50,763.97 | $50,763.97 | N/A | $50,763.97 | N/A |
UHF - Liquid Cooled Solid State Transmitter 14.2 - 20 kW | $684,000.00 | $223,637.79 | ***System Notice: Estimate adjusted and locked because line has been superseded.*** | $223,637.79 | N/A |
Actual Information Description | File Name |
---|---|
Transmitter Building Electrical | Information not provided. |
Installation RF Mask-Filter | Information not provided. |
Transmitter Site Access Road | |
Installation and Proof | |
Misc RF Components | Information not provided. |
Transmitter Removal | Information not provided. |
RF Accessories | |
Electrical | |
Site Survey | |
Other Electrical Service: Incoming AC line surge suppression and disconnect switchgear. | |
3" Rigid Conduit and Wiring (Cost per foot) | Information not provided. |
Switchgear - industrial 800 amp | Information not provided. |
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW | |
Mask Filter System | |
UHF - Liquid Cooled Solid State Transmitter 14.2 - 20 kW |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $550,167.49 | $539,715.74 | N/A | $257,486.44 | N/A |
Total for all systems | $4,678,361.93 | $3,571,690.60 | N/A | $2,941,576.93 | N/A |
Interim Antenna ALP16M2-HSP-2S | $255,467.00 | $256,130.25 | $44,851.50 | ||
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $23,150.00 | N/A | N/A | N/A |
Tower Rigging to Stabilize Tower during interim antenna transmission line work | $30,827.00 | $30,827.00 | N/A | $15,413.50 | N/A |
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) | $5,260.00 | $5,260.00 | N/A | $2,400.00 | N/A |
Sweep test of existing antenna | $6,730.00 | $7,393.25 | Additional expenses were incurred as indicated in the attached invoices. | $7,393.25 | Additional expenses were incurred as indicated in the attached invoices. |
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized | $189,500.00 | $189,500.00 | N/A | $19,644.75 | N/A |
Primary Antenna ATW26H3-HSP230-25H | $294,700.49 | $283,585.49 | $212,634.94 | ||
Freight | $3,615.00 | $3,615.00 | Additional expenses were incurred as indicated in the attached invoices. | $3,615.00 | Additional expenses were incurred as indicated in the attached invoices. |
Installation of Ice Shields | $18,645.49 | $18,645.49 | Additional expenses were incurred as indicated in the attached invoices | $18,645.49 | Additional expenses were incurred as indicated in the attached invoices |
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) | $5,260.00 | $4,800.00 | N/A | $4,800.00 | N/A |
Side mount brackets for high power antennas (if not included in antenna base cost) | $23,150.00 | $13,575.00 | N/A | $13,575.00 | N/A |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | $12,300.00 | $11,700.00 | N/A | $5,131.45 | N/A |
Sweep test of existing antenna | $6,730.00 | $6,250.00 | N/A | $6,250.00 | N/A |
UHF - High Power, Side Mount, basic slot antenna, 739 kW input, directional,, horizontally polarized | $225,000.00 | $225,000.00 | N/A | $160,618.00 | N/A |
Actual Information Description | File Name |
---|---|
Side mount brackets for high power antennas (if not included in antenna base cost) | Information not provided. |
Tower Rigging to Stabilize Tower during interim antenna transmission line work | |
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) | |
Sweep test of existing antenna | |
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized | |
Freight | |
Installation of Ice Shields | |
Pattern scatter analysis for side mount high/med power antennas (if not included in antenna base cost) | |
Side mount brackets for high power antennas (if not included in antenna base cost) | |
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) | |
Sweep test of existing antenna | |
UHF - High Power, Side Mount, basic slot antenna, 739 kW input, directional,, horizontally polarized |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $100,086.00 | $97,086.00 | N/A | $61,817.81 | N/A |
Total for all systems | $4,678,361.93 | $3,571,690.60 | N/A | $2,941,576.93 | N/A |
Interim Transmission Line | $26,616.00 | $26,616.00 | $9,082.89 | ||
Transmission Line Routing | $7,500.00 | $7,500.00 | N/A | N/A | N/A |
Flexible Air Transmission Line - dielectric, 3" | $19,116.00 | $19,116.00 | N/A | $9,082.89 | N/A |
Primary Transmission Line | $73,470.00 | $70,470.00 | $52,734.92 | ||
Transmission Line Bridge Option | $12,870.00 | $12,870.00 | N/A | $9,477.83 | N/A |
Rigid Transmission Line - copper, 6 1/8" | $60,600.00 | $57,600.00 | N/A | $43,257.09 | N/A |
Actual Information Description | File Name |
---|---|
Transmission Line Routing | Information not provided. |
Flexible Air Transmission Line - dielectric, 3" | |
Transmission Line Bridge Option | |
Rigid Transmission Line - copper, 6 1/8" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,229,317.08 | $1,225,117.08 | N/A | $1,060,380.00 | N/A |
Total for all systems | $4,678,361.93 | $3,571,690.60 | N/A | $2,941,576.93 | N/A |
Primary Tower TOWER | $95,231.25 | $91,031.25 | $73,595.25 | ||
Short Tower (less than 500') | $84,200.00 | $80,000.00 | N/A | $71,064.00 | N/A |
Site Security | $8,500.00 | $8,500.00 | N/A | N/A | N/A |
RF Engineer Consultant | $2,531.25 | $2,531.25 | N/A | $2,531.25 | N/A |
Primary Tower TOWER | $0.00 | $0.00 | $0.00 | ||
Primary Tower | $1,134,085.83 | $1,134,085.83 | $986,784.75 | ||
Short Tower (less than 500') | $84,200.00 | $84,200.00 | N/A | $0.00 | N/A |
New tower | $952,566.83 | $952,566.83 | Additional expenses were incurred as indicated in the attached invoices. | $952,566.83 | Additional expenses were incurred as indicated in the attached invoices. |
Tower Site Fencing Guy Anchors | $8,000.00 | $8,000.00 | WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020. | $6,000.00 | N/A |
ERI Geotechnical Survey for collection of soil core samples | $5,650.00 | $5,650.00 | N/A | $2,825.00 | N/A |
Radio Services | $12,250.00 | $12,250.00 | N/A | N/A | N/A |
Addison Surveyors | $3,900.00 | $3,900.00 | N/A | $3,900.00 | N/A |
Installation | $31,619.00 | $31,619.00 | N/A | N/A | N/A |
Tower Site Fence East and West End Removal | $1,600.00 | $1,600.00 | WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020. | N/A | N/A |
Tower Site Fencing New Fence and Gate | $7,500.00 | $7,500.00 | WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020. | N/A | N/A |
Waste Disposal | $3,500.00 | $3,500.00 | WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020. | N/A | N/A |
Porta-Potty | $2,000.00 | $2,000.00 | WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020. | $192.92 | N/A |
Tower Site Tree Removal New Guy Path | $13,000.00 | $13,000.00 | WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020. Additional expenses were incurred as indicated in the attached invoices. | $13,000.00 | Additional expenses were incurred as indicated in the attached invoices. |
Tower Site Tree Removal Tower Site to Road | $8,300.00 | $8,300.00 | WLFB unable to get proposal/quote from vendor because scope of project will be unknown until spring 2020. Additional expenses were incurred as indicated in the attached invoices. | $8,300.00 | Additional expenses were incurred as indicated in the attached invoices. |
Actual Information Description | File Name |
---|---|
Short Tower (less than 500') | |
Site Security | Information not provided. |
RF Engineer Consultant | |
Short Tower (less than 500') | |
New tower | |
Tower Site Fencing Guy Anchors | |
ERI Geotechnical Survey for collection of soil core samples | |
Radio Services | Information not provided. |
Addison Surveyors | |
Installation | Information not provided. |
Tower Site Fence East and West End Removal | Information not provided. |
Tower Site Fencing New Fence and Gate | Information not provided. |
Waste Disposal | Information not provided. |
Porta-Potty | |
Tower Site Tree Removal New Guy Path | |
Tower Site Tree Removal Tower Site to Road |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $160,615.29 | $468,810.89 | N/A | $450,125.09 | N/A |
Total for all systems | $4,678,361.93 | $3,571,690.60 | N/A | $2,941,576.93 | N/A |
Outside Professional Services | $160,615.29 | $468,810.89 | $450,125.09 | ||
Interim Antenna Considerations | $420.00 | $420.00 | N/A | $420.00 | N/A |
Additional Repack Legal Services Not Otherwise Specified in Form 399 | $72,374.95 | $72,374.95 | Additional expenses were incurred as indicated in the attached invoices | $72,374.95 | Additional expenses were incurred as indicated in the attached invoices. |
Insurance Costs | $17,890.34 | $17,890.34 | N/A | $17,890.34 | N/A |
PROJECT PLANNING | $5,000.00 | $5,000.00 | N/A | $750.00 | N/A |
RF Exposure Measurements | $21,050.00 | $10,000.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $3,680.00 | $5,082.40 | Additional expenses were incurred as indicated in the attached invoices. | $5,082.40 | Additional expenses were incurred as indicated in the attached invoices. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | $1,508.00 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $5,000.00 | N/A | $4,306.20 | N/A |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | $3,000.00 | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | $7,000.00 | N/A |
Prepare and or review reimbursement form | $2,630.00 | $63,013.70 | Additional expenses were incurred as indicated in the attached invoices. | $63,013.70 | Additional expenses were incurred as indicated in the attached invoices. |
Project management of the transition | $15,800.00 | $274,779.50 | Additional expenses were incurred as indicated in the attached invoices. | $274,779.50 | Additional expenses were incurred as indicated in the attached invoices. |
Actual Information Description | File Name |
---|---|
Interim Antenna Considerations | |
Additional Repack Legal Services Not Otherwise Specified in Form 399 | |
Insurance Costs | |
PROJECT PLANNING | |
RF Exposure Measurements | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Perform engineering study for new channel assignment and antenna development | |
Prepare and or review reimbursement form | |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $78,383.23 | $77,778.23 | N/A | $42,834.93 | N/A |
Total for all systems | $4,678,361.93 | $3,571,690.60 | N/A | $2,941,576.93 | N/A |
Other Expenses | $78,383.23 | $77,778.23 | $42,834.93 | ||
Tower Lease and Tenant Correspondence | $1,000.00 | $1,000.00 | N/A | $98.00 | N/A |
MVPD Notification of Channel Change | $1,544.00 | $1,544.00 | Additional expenses were incurred as indicated in the attached invoices. | $1,544.00 | Additional expenses were incurred as indicated in the attached invoices. |
Develop and air announcement of upcoming channel change | $2,500.00 | $2,500.00 | N/A | $1,158.70 | N/A |
Equipment Delivery and Handling Charges | $35,149.23 | $35,149.23 | Additional expenses were incurred as indicated in the attached invoices. | $35,149.23 | Additional expenses were incurred as indicated in the attached invoices. |
Disposal Costs (for equipment and other waste, net of any salvage value) | $20,000.00 | $20,000.00 | N/A | N/A | N/A |
Non-zoning permits | $2,500.00 | $2,500.00 | N/A | $1,020.00 | N/A |
Local Zoning | $2,500.00 | $2,500.00 | N/A | N/A | N/A |
FCC Filing Fees - Special Temporary Authorization request | $195.00 | $190.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,070.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | $3,865.00 | N/A |
Actual Information Description | File Name |
---|---|
Tower Lease and Tenant Correspondence | |
MVPD Notification of Channel Change | |
Develop and air announcement of upcoming channel change | |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
Non-zoning permits | |
Local Zoning | Information not provided. |
FCC Filing Fees - Special Temporary Authorization request | Information not provided. |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
FCC Filing Fees - Form 2100 minor change CP application | Information not provided. |
DTV Medical Facility Notification |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $4,678,361.93 | $3,571,690.60 | $2,941,576.93 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Michael D. Smith President 03/11/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Michael D. Smith President 03/11/2021 |