Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
GRAY TELEVISION LICENSEE, LLC |
ONE TELEVISION PLAZA PARKERSBURG, WV 26101 United States |
+1 (304) 485-4588 | Robert.Folliard@gray.tv | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Sam Hariton Widelity, Inc. |
Sam Hariton 4031 University Drive Suite 100 Fairfax, VA, VA 22030 United States |
+1 (339) 222-8107 | sam.hariton@widelity.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | WIYE is planning to purchase a new like-for-like transmitter and a new like-for-like antenna. The station will be reusing the existing transmission lines and remaining on the existing tower. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | TDU2-5K00AV S/N 059-0802 | |
Year | 2002 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 4.4 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | UAXTE-6R44 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 3.1 kW | |
Justification for New Transmitter | The new transmitter is necessary because the manufacturer no longer supports this model. Please see the end of life letter from Comark. |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | Yes | |
Power | 150 kVA | |
Rigid Conduit and Wiring | Yes | |
Size | 1.25 inches | |
Length | 30.0 feet | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
Primary Transmitter - Internal Transmission Line Routing and Other Expenses |
Other costs required for operation of new primary transmitter |
Regrade Access Drive |
Due to high traffic and heavy equipment required for repack related work the access road must be reinforced and repaired. The damage caused to the road is a direct result of repack-required work and should therefore be considered reimbursable. |
Primary Transmitter - Ductwork Install and Adjustment |
Primary Transmitter - Ductwork Install and Adjustment |
HVAC Relocation |
Existing HVAC is being reused, but needs to be relocated. |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | AL12-47-PLC | |
Year | 2012 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | TLP12A/VP-R | |
Year | 2019 | |
Justification for New Antenna | The new antenna is necessary because the existing antenna was cut to a single channel and cannot be retuned |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Utilize Existing |
Use | Primary (Main) | |
Ownership | Owned | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | ERI |
Type | Flexible Air | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 420 feet per run |
Name | Description |
---|---|
Flanges, Connectors, ETC. |
Some additional components, such as flanges and connectors, will be required in order to connect the new transmitter and new antenna to the existing line. |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | Yes | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Yes | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1239800 | |
Coordinates (NAD83) | Latitude (NAD83) | 39° 20' 59.8" N- |
Longitude (NAD83) | 081° 33' 55.4" W- | |
Overall Structure Height | 462.92 feet | |
Support Structure Height | 459.97 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 970.13 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Gray Television Group, Inc. | |
Date Constructed | 11/21/2003 |
Facility ID | Call Sign | Service |
---|---|---|
4685 | WTAP-TV | DTV |
125125 | WOVA-LD | LPD |
Users |
---|
Wood County 911 |
US Coast Guard |
Wash. Count 911 |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study need for guyed or free-standing tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Serious Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 254 | |
Explanation | WIYE requires the aid of outside project management services to fulfill the requirements of the repack. WIYE will hire an outside firm to facilitate and support WIYE in these tasks and others to ensure a timely and well managed transition. | |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | Yes | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | Yes | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $211,889.73 | $236,818.17 | N/A | $170,928.91 | N/A |
Total for all systems | $374,076.55 | $404,669.24 | N/A | $295,704.06 | N/A |
Primary Transmitter UAXTE-6R44 | $211,889.73 | $236,818.17 | $170,928.91 | ||
HVAC Relocation | $3,380.58 | $3,380.58 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time. | $0.00 | N/A |
Primary Transmitter - Ductwork Install and Adjustment | $2,840.00 | $2,840.00 | Estimated Cost Justification WIYE-LD-110-Primary Transmitter - Ductwork Install and Adjustment V0 | $2,840.00 | N/A |
Regrade Access Drive | $15,000.00 | $15,000.00 | See JC Bosley Proposal WTAP_GradeAccessDrive-WIYE-BlueKnobRd | N/A | N/A |
Primary Transmitter - Internal Transmission Line Routing and Other Expenses | $5,961.14 | $5,961.14 | Please see Estimated Cost Justification WIYE-LD-110-Primary Transmitter - Internal Transmission Line Routing and Other Expenses v0 | $5,583.13 | N/A |
1.25" Rigid Conduit and Wiring | $14,658.01 | $14,658.01 | The estimated cost has been adjusted to include all invoices submitted for reimbursement at this time | $7,958.16 | N/A |
UHF - Air Cooled Solid State Transmitter 2.501 - 3.999 kW | $106,300.00 | $154,547.64 | see Estimated Cost Justification WIYE-LD-110-Primary Transmitter - UHF Air-Cooled Solid State, 2.5-3.99 kW v0 | $154,547.62 | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $38,200.00 | N/A | N/A | N/A |
Transformer 3 phase/480v - 150 KVA | $25,550.00 | $2,230.80 | see Estimated Cost Justification WIYE-LD-110-Primary Transmitter - Transformer v0 | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
HVAC Relocation | |
Primary Transmitter - Ductwork Install and Adjustment | |
Regrade Access Drive | Information not provided. |
Primary Transmitter - Internal Transmission Line Routing and Other Expenses | |
1.25" Rigid Conduit and Wiring | |
UHF - Air Cooled Solid State Transmitter 2.501 - 3.999 kW | |
Switchgear - industrial 800 amp | Information not provided. |
Transformer 3 phase/480v - 150 KVA |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $42,379.50 | $43,049.50 | N/A | $43,049.50 | N/A |
Total for all systems | $374,076.55 | $404,669.24 | N/A | $295,704.06 | N/A |
Primary Antenna TLP12A/VP-R | $42,379.50 | $43,049.50 | $43,049.50 | ||
UHF-Low Power, Side Mount, Slotted Coaxial, 15.0kW input, Elliptical | $36,649.50 | $36,649.50 | See Estimated Cost Justification WIYE-LD-210-Primary Antenna - UHF Low Power Side Mount, E-POL V1 | $36,649.50 | N/A |
Sweep test of transmission line and antenna | $5,730.00 | $6,400.00 | See Dielectric Quote 513587, line 3. | $6,400.00 | N/A |
Actual Information Description | File Name |
---|---|
UHF-Low Power, Side Mount, Slotted Coaxial, 15.0kW input, Elliptical | |
Sweep test of transmission line and antenna |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $647.70 | $647.70 | N/A | $0.00 | N/A |
Total for all systems | $374,076.55 | $404,669.24 | N/A | $295,704.06 | N/A |
Primary Transmission Line | $647.70 | $647.70 | $0.00 | ||
Flanges, Connectors, ETC. | $647.70 | $647.70 | See GatesAir Quote Q-82978 | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $64,890.00 | $51,300.00 | N/A | $43,000.00 | N/A |
Total for all systems | $374,076.55 | $404,669.24 | N/A | $295,704.06 | N/A |
Primary Tower TOWER | $64,890.00 | $51,300.00 | $43,000.00 | ||
Serious tower reinforcement/modifications | $0.00 | $0.00 | The reinforcements are being paid for by WTAP and therefore WIYE-LD is not seeking reimbursement for them. | N/A | N/A |
Study needed for guyed or free-standing tower | $8,700.00 | $8,300.00 | See Hodge Structural Quote | N/A | N/A |
Tower Rigging Short Tower (less than 500') | $56,190.00 | $43,000.00 | Per GTI America Inc. Quote Q17-06-030c | $43,000.00 | N/A |
Actual Information Description | File Name |
---|---|
Serious tower reinforcement/modifications | Information not provided. |
Study needed for guyed or free-standing tower | Information not provided. |
Tower Rigging Short Tower (less than 500') |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $38,819.50 | $57,403.75 | N/A | $33,704.25 | N/A |
Total for all systems | $374,076.55 | $404,669.24 | N/A | $295,704.06 | N/A |
Outside Professional Services | $38,819.50 | $57,403.75 | $33,704.25 | ||
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | N/A | N/A |
Prepare Form 601 | $755.00 | $755.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | N/A | N/A |
Perform engineering study for displacement application | $1,800.00 | $5,271.25 | Please see Chesapeake RF Consultants, LLC invoices 2615, 2625, 4321A, 4557A, 4833, 4934, 5021 | $3,525.00 | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,710.00 | N/A | N/A | N/A |
Project management of the transition | $26,797.00 | $41,910.00 | See quote from Widelity | $30,179.25 | N/A |
Actual Information Description | File Name |
---|---|
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare Form 601 | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for displacement application | |
Prepare/ Review 399 reimbursement form | Information not provided. |
Project management of the transition |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $15,450.12 | $15,450.12 | N/A | $5,021.40 | N/A |
Total for all systems | $374,076.55 | $404,669.24 | N/A | $295,704.06 | N/A |
Other Expenses | $15,450.12 | $15,450.12 | $5,021.40 | ||
Equipment Storage | $760.00 | $760.00 | See Atlas Trailer Rentals Quote | N/A | N/A |
Equipment Delivery and Handling Charges | $5,021.41 | $5,021.41 | Please see Estimated Cost Justification WIYE-LD-610-Equipment Delivery and Handling v1 | $5,021.40 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $8,223.71 | $8,223.71 | See Wood County WASTE Quote | N/A | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,110.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Equipment Storage | Information not provided. |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
FCC Filing Fees - Form 2100 minor change CP application | Information not provided. |
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $374,076.55 | $404,669.24 | $295,704.06 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Robert Folliard , III . Assistant Secretary 02/16/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Robert Folliard , III . Assistant Secretary 02/16/2021 |