FCC Form 399: Reimbursement Request

Approved by OMB 3060-1178
Go to the Federal Communications Commission homepage at www.fcc.gov

(REFERENCE COPY - Not for submission) FCC Form 399: Reimbursement Request

Facility ID:
31570
Service:
DTV
Call Sign:
WPAN
Channel:
21 (UHF)
File Number:
0000028768
FRN:
0019006501
Date Submitted:
02/02/2021

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

B&C COMMUNICATIONS, LLC

Doing Business As: B&C COMMUNICATIONS, LLC

William Smith, Manager

155 MIDDLE PLANTATION LANE

GULF BREEZE, FL 32561

United States

+1 (716) 310-3711 BILLSMEDIA@GMAIL.COM Limited Liability Company

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

Tony L. zumMallen

President

QCommunications, LLC

Tony zumMallen

705B SE Melody LN

Lees Summit, MO 64063

United States

+1 (816) 729-1177 tony@qcomm.tv

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan See attached Transition Plan Exhibit.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model NV8604e
Year 2008
Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power Capacity 3.6 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? No
Manufacturer
Model ULXTE-20
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 12.9 kW
Justification for New Transmitter 3-9-2020-CH21- ERP of 620kW see attached- 3-9-power budget showing -TPO -11.82kW. The ULXTE-20- 12.9kW is the min available transmitter. OLD power budget for Ch. 31-was 84 kw ERP which required 7 kw.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) Yes
Switchgear (industrial 800 amp) Yes
Transformer (480V) Yes
Power 150 kVA
Rigid Conduit and Wiring Yes
Size 2 inches
Length 200.0 feet
Other Electrical Service No
Description N/A
HVAC Service Does the replacement transmitter require HVAC Service? Yes
Type Heating and Cooling
Size 10 tons
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Electrical

Install 200 amp panel, conduit, surge protector, etc.

Transmitter Site Preparation

Site prep for installation of the main transmitter and RF components not part of Gates SOW.

Site Survey

Site Survey - required to perform the engineering and design of new equipment at new ch21 site

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? No
Existing Antenna Manufacturer and Type Class Full Power
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Other
Number of Stations Supported N/A
Number of Panels N/A
Design power capacity in use N/A
Lower Limit N/A
Upper Limit N/A
Other Antenna Type Broadband Slot
ERP: 33.5 kW
Manufacturer
Model CS-2030-5771-14
Year 2008

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? No
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? No
New Antenna Manufacturer and Types Class Full Power
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Slot
Number of Stations Supported 1
Number of Panels/Bays 24
Lower Limit 512.00 MHz
Upper Limit 518.00 MHz
Design power capacity in use 90.0 %
Other Antenna Type N/A
ERP: 620.0 kW
Manufacturer
Model ALP24M3-HSBx-21
Year 2020
Justification for New Antenna ch 21 requires new antenna model form ch 31 see the attached 3-9-WPAN_ERI-ALP24m3 -power budget file

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna?
Type
Number of channels supported N/A
Frequencies of channels supported N/A
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? N/A
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? Broadband
Feed Line Size 6 1/8 inches inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna? Yes
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Freight

Freight for antenna and transmission line

Sales Tax

Sales tax for Antenna and transmission line

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing transmission line shared with another station or stations? No
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer
Type Flexible Foam
Diameter 1 5/8 inches
Other Diameter N/A
Segment Length N/A
Other Segment Length N/A
Number of parallel runs 1
Length 790 feet per run

Primary Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? No
Type Rigid
Diameter 6 1/8 inches
Other Diameter N/A
Segment Length 19 1/2 inches
Other Segment Length N/A
Number of parallel runs 1
Length 1270 feet per run
Justification for New Transmission Line ch21 requires new line at new site. see the attached power budget for line details. 3-9-WPAN_ERI-ALP24M3-HSBx-21_TPO20200226 and quote WPAN ERI 20200218-051RevA ALP24 wMACX675 Line Installed

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Vertical spring hanger

Vertical spring hangers that support transmission line.

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Add Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Description of Use N/A
Ownership Owned
Is this tower consider Complex? No
Is this tower currently shared with any other stations? No
One or more FM, AM or TV radio broadcaster(s) N/A
Others Types of Users N/A
Is tower documented for structural analysis? Yes
Is tower compliant with Rev G? No
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1054512
Coordinates (NAD83) Latitude (NAD83) 30° 42' 21.0" N-
Longitude (NAD83) 087° 24' 12.0" W-
Overall Structure Height 1414.02 feet
Support Structure Height 1328.72 feet
Ground Elevation Above Mean Sea Level (AMSL) 134.51 feet
Structure Type TOWER - Free Standing or Guyed Structure
Tower Owner B&C Communications, LLC
Date Constructed 01/01/1997


Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for documented tower
Tower Reinforcements Please select whether tower reinforcements are needed: Serious Reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower N/A
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Name Description

Reinforcing Analysis and Design

Includes analysis and design of required tower reinforcements/modifications based on the previous ERI study

Engineering Services - Land survey

3 separate visits to site to determine existing conditions, land survey, underground utilities, stake new tower centerline, new tower "as built" of base

RF Installation

RF Installation

Angle Brackets

Angle support brackets to reattach line to tower.

Additional Reinforcement Materials

Additional reinforcement materials and labor to install

Tower Lighting

Tower Lighting due to height change. See letter attached to INV WPAN-37457F

Tag Path Clearing

Tag Path clearing - 500 to 600 feet to 50 feet tag path

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 900
Explanation Scope and significance of project require outside management services to augment existing internal personnel to assist turnkey management of and ensure timely and safe execution of channel relocation.
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 4
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 4
NEPA Section 106 environmental review No
Environmental Assessment No
ASR Modification Yes
FAA Consultation (including preparation of FAA Form 7460) Yes
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements No
Additional Field Engineering Service Yes
Number of Days 10
Justification the new ch21 site requires additional field engineering prior to and during the repack system installation due to the unknown nature of the new sites existing building and other tenants facilities to ensure proper engineering and designs are imposed

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Name Description

Consulting and Permit costs

Consulting Services for tower permitting for Repack.

General Legal

General Legal services related to Repack activities

Geotechnical Survey and Report

Geotech survey, report, and associated borings.

Vendor travel expenses

Reimbursable Vendor Travel expenses for working in the field on behalf of the station for the Repack project

General Consulting Engineering Services

Includes CP amendment, signal strength coverage map, change in tower height issues, general CP application

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning No
Non-zoning permits No
BLM or NFS Coordination No
FCC Construction Permit Minor Change Yes
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? No
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? Yes
Does this relocation require MVPD Notification of a Channel Change? Yes

Other Expenses

Back to Top

Other Expenses Not Listed

Name Description

Clear brush

Clear trees and brush to accommodate guy wire installation

Disconnect and decommission existing transmission and RF components

Disconnect transmitter and RF components from existing configuration to make way for new facilities.

Impedance Transformer

Additional parts - impedance transformer.

Portapotty

Portapotty for installation activities

Site Security

Site security to provide protection overnight for indoor and outdoor equipment during installation activities at an unmanned site.

Newspaper Legal Ads

Legal advertising for notice of channel change

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $671,666.00 $619,522.60 N/A $516,472.60 N/A
Total for all systems $3,007,939.07 $3,512,509.34 N/A $3,105,448.31 N/A
Primary Transmitter ULXTE-20 $671,666.00 $619,522.60 $516,472.60
Transmitter Site Preparation $5,700.00 $5,700.00 Site prep for installation of the main transmitter and RF components not part of Gates SOW. N/A N/A
Electrical $13,616.00 $13,616.00 Per Gulf Coast Electrical Contractors: install 200 am commercial panel with all breakers required to feed new tx, pump module and heat exchanger. Install conduit, surge protector. Remove unused conduit/wiring. Replace disconnecting eq on HVAC $13,616.00 N/A
10 Ton system $60,500.00 $27,725.00 Purchase and installation of (2) 5-ton American St 20 SEER variable speed heat pum, air handlers, with associated duct runs, controllers, switches, permits per attached Climatech quote $27,725.00 N/A
2" Rigid Conduit and Wiring (Cost per foot) $5,200.00 $5,200.00 N/A N/A N/A
Switchgear - industrial 800 amp $38,200.00 $38,200.00 N/A N/A N/A
Service entrance 3 phase/800 amp/208 volt $14,400.00 $14,400.00 N/A N/A N/A
Transformer 3 phase/480v - 150 KVA $25,550.00 $25,550.00 N/A N/A N/A
Site Survey $14,000.00 $14,000.00 Site survey and report are required to be performed before the new transmitter and components installation plan can be finalized. N/A N/A
UHF - Liquid Cooled Solid State Transmitter 8.2 - 13 kW $494,500.00 $475,131.60 N/A $475,131.60 N/A

Components

Actual Information Description File Name
Transmitter Site Preparation Information not provided.
Electrical

Component Description:
Electrical work - Gulf Coast Electrical - INV 2020-154
Amount:
$13,616.00
10 Ton system

Component Description:
HVAC system for WPAN - INV 3305
Amount:
$27,725.00
2" Rigid Conduit and Wiring (Cost per foot) Information not provided.
Switchgear - industrial 800 amp Information not provided.
Service entrance 3 phase/800 amp/208 volt Information not provided.
Transformer 3 phase/480v - 150 KVA Information not provided.
Site Survey Information not provided.
UHF - Liquid Cooled Solid State Transmitter 8.2 - 13 kW

Component Description:
Freight for RF components - Gates INV US0339845
Amount:
$340.69

Component Description:
Third and final invoice for transmitter. Includes sales tax & Freight. Gates INV US0339470
Amount:
$176,398.57

Component Description:
Final Tx invoice - Gates - US0339620
Amount:
$8,395.50

Component Description:
2nd invoice for transmitter. GatesAir JW30004736-2
Amount:
$144,998.42

Component Description:
Gates Air - 1st transmitter invoice # JW30004736-1 - Q-86562
Amount:
$144,998.42

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $148,022.57 $147,692.57 N/A $110,692.57 N/A
Total for all systems $3,007,939.07 $3,512,509.34 N/A $3,105,448.31 N/A
Primary Antenna ALP24M3-HSBx-21 $148,022.57 $147,692.57 $110,692.57
Elbow complex, broadband, at antenna input, per 6 1/8. feedline (if needed) $13,700.00 $13,700.00 N/A N/A N/A
UHF - High Power, Side Mount, basic slot antenna, 24 bay,, 620 kW input, directional,, horizontally polarized $70,978.61 $70,978.61 per attached proposal - 3-9- WPAN ERI 20200218-051RevA ALP24 wMACX675 Line Installed $70,978.61 N/A
Freight $5,593.46 $5,593.46 Freight for antenna and tx line per ERI invoice WPAN-56638 $5,593.46 N/A
Sales Tax $27,870.50 $27,870.50 Sales tax for antenna and tx line - ERI Proposal 20200218-051 Rev C - Charged on INV WPAN-56638 $27,870.50 N/A
Side mount brackets for high power antennas (if not included in antenna base cost) $23,150.00 $23,150.00 N/A N/A N/A
Sweep test of existing antenna $6,730.00 $6,400.00 N/A $6,250.00 N/A

Components

Actual Information Description File Name
Elbow complex, broadband, at antenna input, per 6 1/8. feedline (if needed) Information not provided.
UHF - High Power, Side Mount, basic slot antenna, 24 bay,, 620 kW input, directional,, horizontally polarized

Component Description:
Antenna portion of invoice - WPAN - ERI - INV WPAN-64000A
Amount:
$35,489.30

Component Description:
WPAN-ERI ANTENNA LINE 001
Amount:
$35,489.31
Freight

Component Description:
Freight for antenna and tx line - ERI INV WPAN-56638
Amount:
$5,593.46
Sales Tax

Component Description:
Sales tax for antenna and transmission line - ERI - WPAN-56638
Amount:
$27,870.50
Side mount brackets for high power antennas (if not included in antenna base cost) Information not provided.
Sweep test of existing antenna

Component Description:
Remaining amount for sweep - ERI INV WPAN-56638
Amount:
$625.00

Component Description:
WPAN - ERI - Sweep - INV WPAN-64000A
Amount:
$2,500.00

Component Description:
WPAN - SWEEP TEST LINE 028 - INV WPAN-64000
Amount:
$3,125.00

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $257,919.61 $200,879.61 N/A $174,684.41 N/A
Total for all systems $3,007,939.07 $3,512,509.34 N/A $3,105,448.31 N/A
Primary Transmission Line $257,919.61 $200,879.61 $174,684.41
Vertical spring hanger $1,379.61 $1,379.61 Vertical spring hangers to support the transmission line. Per actual costs - ERI invoice 56550 $1,379.61 N/A
Rigid Transmission Line - copper, 6 1/8" $256,540.00 $199,500.00 per attacehd proposal - 3-9-WPAN ERI 20200218-051RevA ALP24 wMACX675 Line Installed plus estimated freight $173,304.80 N/A

Components

Actual Information Description File Name
Vertical spring hanger

Component Description:
Vertical Spring hangers for tx line - ERI - INV 56550
Amount:
$1,379.61
Rigid Transmission Line - copper, 6 1/8"

Component Description:
Transmission line not needed - ERI - WPAN-56638
Amount:
($1,861.50)

Component Description:
WPAN - ERI - Transmission line & dryer - INV WPAN-64000A
Amount:
$87,583.15

Component Description:
WPAN - TX LINE AND DRYER - LINES 002-026 INV WPAN-64000
Amount:
$87,583.15

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,491,543.72 $2,144,932.29 N/A $2,052,577.28 N/A
Total for all systems $3,007,939.07 $3,512,509.34 N/A $3,105,448.31 N/A
Primary Tower TOWER $1,491,543.72 $2,144,932.29 $2,052,577.28
Serious tower reinforcement/modifications $1,052,000.00 $1,607,338.57 per ERI Proposal 20200213-002, line item 002 - TV Services. see attached WPAN-399-Tower mod summary-Final 3-9-2020 includes foundation repair Includes sales tax on INV WPAN-37457E $1,607,338.57 N/A
RF Installation $1,868.59 $1,868.59 PER ERI Order 37457P - INV 56731 $1,868.59 N/A
Additional Reinforcement Materials $10,486.80 $10,486.80 Additional reinforcement materials from ERI Order # 37457O - includes labor to install and FL sales tax $10,486.80 N/A
Structural engineering tower load study for well documented tower $12,600.00 $29,975.00 Two TAs needed to determine refurbished versus replaced. The 2nd TA was able to determine the tower can be refurbished if shortened and all tenents removed and with substantial reinforcements of tower and foundation work. see ERI 20200213-002 $29,975.00 N/A
Angle Brackets $12,695.00 $12,695.00 Per ERI change order 37457D.1 attached to invoice WPAN-56218 $12,695.00 N/A
Reinforcing Analysis and Design $5,250.00 $5,250.00 Per actual costs charged on ERI invoice #54843 $5,250.00 N/A
Tag Path Clearing $18,705.00 $18,705.00 Tag Path Clearing: 500 - 600 feet to 50 feet tag path. PER ERI Inv 56573 $18,705.00 N/A
Engineering Services - Land survey $29,280.00 $29,280.00 Per proposal from Electronics Research, Inc #20200103-684 for $29280.00. N/A N/A
Tower Lighting $138,158.33 $138,158.33 Tower lighting - includes sales tax. Per ERI invoice WPAN-37457F and WPAN-56505 (freight) $138,158.33 The total are actual costs and are the same as the estimated costs: $138,158.33
Tall Tower (greater than 500') $210,500.00 $291,175.00 per ERI Proposal 20200218-05, line item 029 - TV Services. see attached $228,099.99 N/A

Components

Actual Information Description File Name
Serious tower reinforcement/modifications

Component Description:
Freight for tower material - ERI - WPAN-56896
Amount:
$5,436.82

Component Description:
WPAN- ERI - TOWER REFURBISHMENT LINE 001,002,003 MATERIAL, FOUNDATION INV WPAN-54000
Amount:
$776,129.50

Component Description:
Weather Days - tower work - ERI INV 56335
Amount:
$13,000.00

Component Description:
Concrete testing at tower - ERI - INV 56872
Amount:
$239.15

Component Description:
WPAN Tower Work: ERI reinforcement, foundation, tv install - INV WPAN-54000A
Amount:
$681,534.60

Component Description:
tower work plus sales tax - ERI - INV WPAN-37457E
Amount:
$130,998.50
RF Installation

Component Description:
RF Installation - ERI - INV 56731
Amount:
$1,868.59
Additional Reinforcement Materials

Component Description:
Additional reinforcement mat & labor - ERI - INV 56730
Amount:
$10,486.80
Structural engineering tower load study for well documented tower

Component Description:
2nd invoice Tower reinforcing analysis & design. ERI invoice WPAN-37457C-1
Amount:
$3,250.00

Component Description:
1st invoice engineering climbing inspection of tower - ERI INV WPAN-3000
Amount:
$11,737.50

Component Description:
2nd invoice engineering tower climbing inspection - ERI WPAN-54187
Amount:
$11,737.50

Component Description:
Tower: Reinforcing analysis and design. ERI INV WPAN-37457C
Amount:
$3,250.00
Angle Brackets

Component Description:
Angle support brackets - ERI - INV WPAN-56218
Amount:
$12,695.00
Reinforcing Analysis and Design

Component Description:
ERI - reinforcing analysis and design - INV 54843
Amount:
$5,250.00
Tag Path Clearing

Component Description:
Tag path clearing - ERI INV 56573
Amount:
$18,705.00
Engineering Services - Land survey Information not provided.
Tower Lighting

Component Description:
freight for tower lights - ERI - INV WPAN-56505
Amount:
$1,462.23

Component Description:
Tower light change due to height. WPAN - ERI - INV WPAN-37457F
Amount:
$136,696.10
Tall Tower (greater than 500')

Component Description:
Weather days - ERI - INV 56889
Amount:
$11,050.00

Component Description:
Weather day during antenna install - ERI - INV 56608
Amount:
$2,600.00

Component Description:
Antenna removal done by others - per CO 37457D - ERI - INV WPAN-56638
Amount:
($55,407.50)

Component Description:
Installation of line & antenna - WPAN - ERI - INV WPAN-64000A
Amount:
$116,470.00

Component Description:
Weather days during antenna install - ERI - INV 56704
Amount:
$7,800.00

Component Description:
WPAN - ERI INSTALLATION OF LINE AND ANTENNA - LINE 029 - INV WPAN-64000 - ROUNDED DOWN 1 PENNY
Amount:
$145,587.49

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $362,098.52 $326,893.62 N/A $208,267.07 N/A
Total for all systems $3,007,939.07 $3,512,509.34 N/A $3,105,448.31 N/A
Outside Professional Services $362,098.52 $326,893.62 $208,267.07
General Consulting Engineering Services $13,800.00 $13,800.00 Consulting Engineering - several issues, including tower height changes, CP application amendment, signal strength coverage, FAA consulting, CP extension, Tolling waiver, CP review. Lohnes and Culver invoices $13,110.00 N/A
Vendor travel expenses $14,000.00 $14,000.00 estimated vendor travel for the project N/A N/A
Geotechnical Survey and Report $9,500.00 $9,500.00 Per ERI Proposals 2019717-126 and 20190913-739 attached to invoice 54838 $9,500.00 N/A
Consulting and Permit costs $12,743.52 $12,743.52 Consulting and permitting costs for WPAN tower site $12,743.52 N/A
Additional Field Engineering Service, 10 Days $22,500.00 $22,500.00 estimated amount for 10 days of field engineering N/A N/A
Comprehensive coverage verification via field study, if needed $84,200.00 $42,000.00 N/A N/A N/A
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase $2,105.00 $2,000.00 N/A $210.00 N/A
ASR modification (prepare FCC Form 854) $2,105.00 $2,105.00 N/A $690.00 N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $14,720.00 $14,720.00 N/A N/A N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $4,210.00 $4,000.00 N/A $1,140.00 N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $2,250.00 N/A $0.00 N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $5,000.00 N/A $4,860.00 N/A
Prepare request for Special Temporary Authorization $8,200.00 $8,200.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A $0.00 N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $3,000.00 N/A $2,975.00 N/A
Project management of the transition $142,200.00 $150,140.10 per actual invoices from QCommunications and Widelity. $147,103.55 N/A
General Legal $6,835.00 $6,835.00 General Legal services related to Repack $6,835.00 Per actual invoice costs
Prepare and or review reimbursement form $2,630.00 $3,100.00 Estimated Cost Justification WPAN-590-Prepare and_or Review Reimbursement Form v4 $3,100.00 Only asking for reimbursement of the $2500, but duplicate entry because adding required cover letter (can't delete or amend prior submission).
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A $0.00 N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $7,000.00 N/A $6,000.00 N/A

Components

Actual Information Description File Name
General Consulting Engineering Services

Component Description:
Various consulting engineering - Lohnes & Culver - INV 202010-1590-01-31570
Amount:
$2,910.00

Component Description:
CP application amendment and signal strength coverage map - Lohnes & Culver INV 201904-1590-01-31570
Amount:
$2,390.00

Component Description:
Structural issues of tower; prepare eng statement for 399 - Lohnes & Culver - INV 202003-1590-01-31570
Amount:
$4,870.00

Component Description:
FAA consulting, FAA notification - Lohnes & Culver - INV 202009-1590-01-31570
Amount:
$2,190.00

Component Description:
Lohnes - eng consultant - prepare final power budget - INV 202010-1590-02-31570
Amount:
$750.00
Vendor travel expenses Information not provided.
Geotechnical Survey and Report

Component Description:
ERI prop 20190717-129 and 20190913-739. Geotech survey and associated borings. INV 54838
Amount:
$9,500.00
Consulting and Permit costs

Component Description:
Permitting and consulting services for WPAN Tower site - AFF - INV 2020243
Amount:
$12,743.52
Additional Field Engineering Service, 10 Days Information not provided.
Comprehensive coverage verification via field study, if needed Information not provided.
FAA consultant, including cost of preparing FAA Form 7460 (Notice of Proposed Construction), if needed for height increase

Component Description:
Legal invoice for Ch. 31 FAA filing work (replaces prior invoices submitted).
Amount:
$210.00
ASR modification (prepare FCC Form 854)

Component Description:
Prepare 854-MD - Lohnes & Culver - INV 202009-1590-01-31570
Amount:
$690.00
Attorney Fees - Prepare and File request for Special Temporary Authorization Information not provided.
Attorney Fees - Negotiation of lease and other matters for shared locations

Component Description:
WPAN-550-Attorney - Negotiate Lease and Other Matters
Amount:
$210.00

Component Description:
Legal Services
Amount:
$660.00

Component Description:
Calls with client and conference call with Widelity re: repack reimbursement issues
Amount:
$270.00
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application

Component Description:
Legal invoice for Ch. 31 construction permit application work (replaces prior invoices submitted).
Amount:
$4,860.00
Prepare request for Special Temporary Authorization Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application

Component Description:
FCC Form 2100 Construction Permit Application
Amount:
$1,735.00

Component Description:
CP Application Modification
Amount:
$1,240.00
Project management of the transition

Component Description:
Tech and field PM March 2020 -
Amount:
$17,143.00

Component Description:
Dec 2020 399 PM Hours - QC21-712
Amount:
$481.90

Component Description:
399 processing PM - QC20-484
Amount:
$1,508.90

Component Description:
Tech and field PM April 2020
Amount:
$10,175.20

Component Description:
Tech and Field Proj mgmt Jan 2020
Amount:
$24,000.20

Component Description:
Provide Project Management to station for repack - QComm INV QC20-272
Amount:
$1,698.50

Component Description:
Technical and field PM Aug 2019 QC20-370
Amount:
$7,094.20

Component Description:
Field and Tech Proj mgmt - June 2020
Amount:
$14,046.20

Component Description:
8-3-20 QComm - PM hours for June 2020 - QC20-354
Amount:
$466.10

Component Description:
Project Management - paperwork July 2020 - INV QC20-432
Amount:
$742.60

Component Description:
Nov 2020 399 PM hours - QComm - QC20-611
Amount:
$1,406.20

Component Description:
Technical and Field project management - July 2019 -
Amount:
$2,196.20

Component Description:
Tech & field proj mgmt July 2020
Amount:
$10,886.20

Component Description:
Technical and field proj mgmt Oct 2019
Amount:
$1,027.00

Component Description:
399 "paperwork" processing - PM - August 2020 - QC20-483
Amount:
$2,575.40

Component Description:
Field and Tech proj mgmt - Feb 2020
Amount:
$18,154.20

Component Description:
Tech & field Proj mgmt Dec 2019
Amount:
$4,345.00

Component Description:
Widelity April project management - INV B&C-WPAN-037. NOTE: INVOICE NUMBER IS B&C-WPAN-037. "And" was substituted for "&" in the invoice number.
Amount:
$2,233.35

Component Description:
Technical and field proj mgmt - Nov 2019
Amount:
$2,133.00

Component Description:
Tech and Field proj mgmt September 2019
Amount:
$6,399.00

Component Description:
Technical and field proj mgmt - May 2020
Amount:
$14,172.60

Component Description:
May 2020 PM Hours - QComm - INV QC20-330
Amount:
$450.30

Component Description:
October 2020 Paperwork PM - QComm - INV QC20-504
Amount:
$3,768.30
General Legal

Component Description:
Current amount due only. Legal Services - Jeffrey Timmons - INV 02763
Amount:
$780.00

Component Description:
General legal 10/3 thru 12/5/20 - Timmons - INV 2822
Amount:
$300.00

Component Description:
WPAN - Timmons - GEn Legal Aug - Oct 2020 - INV 2792
Amount:
$390.00

Component Description:
Gen Legal 1/1/19 - 3/16/19 - Timmons - INV 02543
Amount:
$30.00

Component Description:
Legal services 10/2/20 thru 10/15/20 - Timmons - INV 2810
Amount:
$1,145.00

Component Description:
Current amount due only. Legal Services - Jeffrey Timmons - INV 2741
Amount:
$3,270.00

Component Description:
Medical notifications - legal - Timmons INV 2823
Amount:
$90.00

Component Description:
Legal - medical notifications - Timmons - INV 2793
Amount:
$830.00
Prepare and or review reimbursement form

Component Description:
Upload invoice to Widelity site
Amount:
$60.00

Component Description:
Legal Services
Amount:
$180.00

Component Description:
Legal Services
Amount:
$90.00

Component Description:
Legal invoice for cost estimates/reimbursements work. Request reimburse $2500 approved in allotment, vendor wrote off/credit for $1250 per retainer; adds cover letter to previously submission.
Amount:
$2,500.00

Component Description:
Legal Services
Amount:
$150.00

Component Description:
Legal invoice for cost estimates/reimbursements work. Request reimburse $2500 approved in allotment, vendor wrote off/credit for $1250 per retainer.
Amount:
$2,500.00

Component Description:
Legal Services
Amount:
$30.00

Component Description:
Legal Services
Amount:
$120.00
Address transition timing and coordination issues w/ other stations and wireless Information not provided.
Perform engineering study for new channel assignment and antenna development

Component Description:
New Channel Assignment & Antenna Development
Amount:
$2,400.00

Component Description:
Alternate Channel Analysis
Amount:
$3,600.00

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $76,688.65 $72,588.65 N/A $42,754.38 N/A
Total for all systems $3,007,939.07 $3,512,509.34 N/A $3,105,448.31 N/A
Other Expenses $76,688.65 $72,588.65 $42,754.38
Newspaper Legal Ads $209.88 $209.88 Newspaper legal ad regarding channel change and resume broadcast date. NW Daily News - 34426797 $209.88 N/A
Site Security $21,600.00 $21,600.00 Overnight site security to protect indoor and outdoor equipment during installation activities at an unmanned site. $21,600.00 N/A
Portapotty $1,750.00 $1,750.00 Actual costs per XTreme Plumbing & Septic Invoices $1,750.00 N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $5,000.00 $5,000.00 N/A $4,255.73 N/A
MVPD Notification of Channel Change $1,000.00 $1,000.00 Prepare and send notices to MVPDs. $0.00 N/A
Clear brush $9,650.00 $9,650.00 Clear trees and brush from guy paths per ERI invoice 56411 $9,650.00 N/A
Disconnect and decommission existing transmission and RF components $14,000.00 $14,000.00 estimated amount to disconnect and decommission tx and rf components N/A N/A
Impedance Transformer $1,538.77 $1,538.77 Impedance transformer per ERI invoice 56408 - additional parts. $1,538.77 N/A
Develop and air announcement of upcoming channel change $250.00 $250.00 Voice talent to tape announcement. $0.00 N/A
Equipment Delivery and Handling Charges $8,500.00 $8,500.00 N/A N/A N/A
DTV Medical Facility Notification $11,550.00 $7,500.00 N/A $3,750.00 N/A
FCC Filing Fees - Special Temporary Authorization request $195.00 $195.00 N/A N/A N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $325.00 N/A $0.00 N/A
FCC Filing Fees - Form 2100 minor change CP application $1,110.00 $1,070.00 N/A $0.00 N/A

Components

Actual Information Description File Name
Newspaper Legal Ads

Component Description:
Newspaper Ad - NW FL Daily News - 34426797
Amount:
$209.88
Site Security

Component Description:
Site security from 8/4/20 to 8/10/20.
Amount:
$3,780.00

Component Description:
10/7/20 Revised - Site security week 4 - Severance - INV 1290
Amount:
$3,780.00

Component Description:
Security services for 8/18/20 through 8/24/20.
Amount:
$3,780.00

Component Description:
Revised date - Security services for 8/11/20 through 8/17/20.
Amount:
$3,780.00

Component Description:
Revised 10/7/20 Site Security - week 5 - Severance INV 1293
Amount:
$3,780.00

Component Description:
Week #6 - final site security invoice- Severance - INV 1295
Amount:
$2,700.00
Portapotty

Component Description:
Portapotty 9/7/20 thru 10/6/20 - Xtreme INV I2051
Amount:
$325.00

Component Description:
Portapotty for one month with 2 cleanings/week. INV 1032150767743
Amount:
$150.00

Component Description:
portapotty services Nov 5 - Dec 4, 2020 - Xtreme - INV I1585
Amount:
$400.00

Component Description:
portapotty services 12-5-20 thru 1-4-2021 - Xtreme - INV I2348
Amount:
$325.00

Component Description:
Portapotty services Oct 5 - Nov 4, 2020
Amount:
$400.00

Component Description:
Portapotty for September 2020
Amount:
$150.00
Disposal Costs (for equipment and other waste, net of any salvage value)

Component Description:
Dumpster - ERI - INV 56354
Amount:
$980.15

Component Description:
Dumpster fees - ERI - INV 56709
Amount:
$2,074.11

Component Description:
Dumpster Fees - ERI - INV 56636
Amount:
$1,201.47
MVPD Notification of Channel Change Information not provided.
Clear brush

Component Description:
Clear trees & brush from guy paths - ERI - INV 56411
Amount:
$9,650.00
Disconnect and decommission existing transmission and RF components Information not provided.
Impedance Transformer

Component Description:
Impedance transformer - ERI - INV 56408
Amount:
$1,538.77
Develop and air announcement of upcoming channel change Information not provided.
Equipment Delivery and Handling Charges Information not provided.
DTV Medical Facility Notification

Component Description:
Medical Notifications - WPAN - RF Notifications - INV 1488
Amount:
$3,750.00
FCC Filing Fees - Special Temporary Authorization request Information not provided.
FCC Filing Fees - Form 2100 license to cover application Information not provided.
FCC Filing Fees - Form 2100 minor change CP application Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $3,007,939.07 $3,512,509.34 $3,105,448.31

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. Yes
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

William Smith

President


02/02/2021

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

William Smith

President


02/02/2021

Attachments

Back to Top