Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
GRAY TELEVISION LICENSEE, LLC |
Lucy Brown 4370 PEACHTREE ROAD, NE ATLANTA, GA 30319 United States |
+1 (703) 237-5211 | Robert.Folliard@gray.tv | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Sam Hariton Widelity |
Sam Hariton 4031 University Dr Suite 100 Fairfax, VA 22030 United States |
+1 (339) 222-8107 | sam.hariton@widelity.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | KMNF is planning to purchase an upgraded transmitter, purchase an upgraded antenna, purchase new transmission line, and move to a new tower . |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | Innovator CX | |
Year | 2010 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 1 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | TBD | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 90 W | |
Justification for New Transmitter | KMNF cannot retune the transmitter, as the station is getting newer equipment, moving to a different band, moving to a different site, and obtaining a higher TPO. |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
Other Electrical Costs: Conduit and Wiring |
Other Electrical Costs: Conduit and Wiring |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Leased | |
Owner | CTV of Southern Minnesota | |
Is the existing antenna shared with another station or stations? | Yes | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Other | |
Other Antenna Type | broadband superturnstile | |
ERP: | 1.9 kW | |
Manufacturer | ||
Model | 771-304 | |
Year | 2009 |
Facility ID | Call Sign |
---|---|
13839 | K19LI-D |
125749 | K32GX-D |
13838 | K21DG-D |
13840 | K14KE-D |
13844 | K26CS-D |
13846 | K18NE-D |
167237 | K34JX-D |
28003 | K30FN-D |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Top | |
Polarization | Elliptical | |
Type | Slotted Coaxial | |
ERP: | 3.0 kW | |
Manufacturer | ||
Model | TLS-V4 | |
Year | 2019 | |
Justification for New Antenna | KMNF is requesting upgraded equipment. However, moving to the VHF band requires vertical polarization. These components should be considered reimbursable. KMNF acknowledges that it is increasing its ERP, and that power increase is not reimbursable. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | Yes |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Leased | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Foam | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 1040 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Type | Flexible Foam | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 1100 feet per run | |
Justification for New Transmission Line | KMNF is moving towers and will require a new transmission line. | |
Interior RF Systems | Does the Installation of the Transmission Line require an additional or replacement Inside RF system including switching, patch panels, and dehydrators? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | No | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1025277 | |
Coordinates (NAD83) | Latitude (NAD83) | 43° 56' 12.3" N- |
Longitude (NAD83) | 094° 24' 39.0" W- | |
Overall Structure Height | 1072.82 feet | |
Support Structure Height | 1008.52 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 1051.17 feet | |
Structure Type | GTOWER - Guyed Structure Used for Communication Purposes | |
Tower Owner | Gray Media Group, Inc. | |
Date Constructed | 09/01/1960 |
Facility ID | Call Sign | Service |
---|---|---|
68853 | KEYC-TV | DTV |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Tower mapping and report for structural engineer |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Minor Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 254 | |
Explanation | KMNF does not have sufficient resource capacity and expertise in house to handle all of the reimbursement activities necessary to facilitate on-time completion of the station's build. KMNF will hire an outside firm to support KMNF in these tasks. | |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Prepare Form 601 | Yes | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | Yes |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $11,300.00 | $11,300.00 | N/A | $0.00 | N/A |
Total for all systems | $465,717.76 | $480,830.76 | N/A | $67,733.15 | N/A |
Primary Transmitter TBD | $11,300.00 | $11,300.00 | $0.00 | ||
High VHF - Air Cooled Solid State Transmitter 10 - 100 Watts | $11,300.00 | $11,300.00 | Please see Justification KMNF Transmitter Cost_Like-For-Like for details | N/A | N/A |
Other Electrical Costs: Conduit and Wiring | $0.00 | $0.00 | Filler until a quote is available for this cost | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $53,885.00 | $53,885.00 | N/A | $43,430.00 | N/A |
Total for all systems | $465,717.76 | $480,830.76 | N/A | $67,733.15 | N/A |
Primary Antenna TLS-V4 | $53,885.00 | $53,885.00 | $43,430.00 | ||
High VHF-Low Power, Side Mount, Slotted Coaxial, 3.0kW input, Elliptical | $43,530.00 | $43,530.00 | Please see Dielectric LLC Order Confirmation 1698928 | $43,430.00 | N/A |
Side Mount antenna brackets | $4,625.00 | $4,625.00 | N/A | N/A | N/A |
Sweep test of transmission line and antenna | $5,730.00 | $5,730.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
High VHF-Low Power, Side Mount, Slotted Coaxial, 3.0kW input, Elliptical | |
Side Mount antenna brackets | Information not provided. |
Sweep test of transmission line and antenna | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $26,400.00 | $26,400.00 | N/A | $13,119.34 | N/A |
Total for all systems | $465,717.76 | $480,830.76 | N/A | $67,733.15 | N/A |
Primary Transmission Line | $26,400.00 | $26,400.00 | $13,119.34 | ||
Flexible Foam Transmission Line - dielectric, 1 5/8" | $26,400.00 | $26,400.00 | N/A | $13,119.34 | N/A |
Actual Information Description | File Name |
---|---|
Flexible Foam Transmission Line - dielectric, 1 5/8" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $328,750.00 | $328,750.00 | N/A | $0.00 | N/A |
Total for all systems | $465,717.76 | $480,830.76 | N/A | $67,733.15 | N/A |
Primary Tower GTOWER | $328,750.00 | $328,750.00 | $0.00 | ||
Tower Rigging Tall Tower (greater than 500') | $157,750.00 | $157,750.00 | N/A | N/A | N/A |
Tower mapping and report for structural engineer | $21,000.00 | $21,000.00 | N/A | N/A | N/A |
Minor tower reinforcement/modifications | $150,000.00 | $150,000.00 | Per catalog of costs | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $38,819.50 | $53,932.50 | N/A | $11,025.55 | N/A |
Total for all systems | $465,717.76 | $480,830.76 | N/A | $67,733.15 | N/A |
Outside Professional Services | $38,819.50 | $53,932.50 | $11,025.55 | ||
Project management of the transition | $26,797.00 | $41,910.00 | Please see KMNF-LD LPTV strategic support quote | $11,025.55 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | N/A | N/A |
Perform engineering study for displacement application | $1,800.00 | $1,800.00 | N/A | N/A | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $1,710.00 | N/A | N/A | N/A |
Prepare Form 601 | $755.00 | $755.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Project management of the transition | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for displacement application | Information not provided. |
Prepare/ Review 399 reimbursement form | Information not provided. |
Prepare Form 601 | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $6,563.26 | $6,563.26 | N/A | $158.26 | N/A |
Total for all systems | $465,717.76 | $480,830.76 | N/A | $67,733.15 | N/A |
Other Expenses | $6,563.26 | $6,563.26 | $158.26 | ||
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | N/A | N/A |
Equipment Delivery and Handling Charges | $158.26 | $158.26 | Please see Dielectric order confirmation 1698928 | $158.26 | N/A |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $1,110.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 Major change CP application | $4,960.00 | $4,960.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
FCC Filing Fees - Form 2100 license to cover application | Information not provided. |
Equipment Delivery and Handling Charges | |
FCC Filing Fees - Form 2100 minor change CP application | Information not provided. |
FCC Filing Fees - Form 2100 Major change CP application | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $465,717.76 | $480,830.76 | $67,733.15 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Robert Folliard , III . Assistant Secretary 01/22/2021 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Robert Folliard , III . Assistant Secretary 01/22/2021 |