Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
Pikes Peak Television, Inc. Doing Business As: Pikes Peak Television, Inc. |
825 Edmond Street Saint Joseph, MO 64501 United States |
+1 (816) 271-8505 | tim.hannan@npgco.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
The Preparer is same as the reimbursement contact. |
|
|
|
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Please see Transition Plan Description Exhibit; please also see Revised Transition Plan Exhibit. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | AT725P | |
Year | 2012 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 25 W |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | UAXTE-4R37 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 2400 W | |
Justification for New Transmitter | Please see Revised Transition Plan Description Exhibit |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
RF Accessories |
RF Accessories |
Miscellaneous Items for Preparation of Transmitter Building |
Miscellaneous Items for Preparation of Transmitter Building |
Electrical and Mechanical Parts and Installation for Transmitter Building |
Electrical and Mechanical Parts and Installation for Transmitter Building |
Mask Filter System |
Mask Filter System |
Commissioning and Sweep |
Commissioning and Sweep |
Transmitter Building |
Transmitter Building |
Documentation and RF Proof |
Documentation and RF Proof |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Purchase New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Other | |
Other Antenna Type | Panel | |
ERP: | 0.14 kW | |
Manufacturer | ||
Model | B8UA | |
Year | 2012 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Purchase New | |
Ownership | Owned | |
Is antenna shared? | No | |
Is antenna directional? | Yes | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Types | ||
Mounting | Top Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | 4DR-16-2HW | |
Year | 2012 | |
Justification for New Antenna | Please See Revised Transition Plan Exhibit |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | No |
Name | Description |
---|---|
Tower rigging, removal of existing panel antenna, and installation of new panel antenna |
Tower rigging, removal of existing panel antenna, and installation of new panel antenna |
Coax Andrew, hangers, standoffs, EIA connectors |
Coax Andrew, hangers, standoffs, EIA connectors |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1012530 | |
Coordinates (NAD83) | Latitude (NAD83) | 38° 49' 43.0" N- |
Longitude (NAD83) | 104° 50' 22.0" W- | |
Overall Structure Height | 464.89 feet | |
Support Structure Height | 459.97 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 5961.87 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | PIKES PEAK TELEVISION INC | |
Date Constructed | 07/01/1953 |
Facility ID | Call Sign | Service |
---|---|---|
66250 | KRDO | AM |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Kintronics 150 Complete Isocoupler to avoid impairment of AM signal |
Kintronics 150 Complete Isocoupler to avoid impairment of AM signal |
Ice Bridge |
Ice Bridge |
Rigging Services including freight, travel, per diem, labor on site and at plant |
Rigging Services including freight, travel, per diem, labor on site and at plant |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | No |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Name | Description |
---|---|
Additional Displacement Legal Services Not Otherwise Specified in Form 399 |
Additional Displacement Legal Services Not Otherwise Specified in Form 399 |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | Yes | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | No |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $167,783.65 | $129,413.46 | N/A | $0.00 | N/A |
Total for all systems | $385,592.23 | $292,214.54 | N/A | $17,003.08 | N/A |
Primary Transmitter UAXTE-4R37 | $167,783.65 | $129,413.46 | $0.00 | ||
Commissioning and Sweep | $3,500.00 | $3,500.00 | N/A | N/A | N/A |
Mask Filter System | $3,380.00 | $3,380.00 | N/A | N/A | N/A |
Documentation and RF Proof | $1,000.00 | $1,000.00 | N/A | N/A | N/A |
Transmitter Building | $48,985.00 | $48,985.00 | N/A | N/A | N/A |
Miscellaneous Items for Preparation of Transmitter Building | $6,100.00 | $6,100.00 | N/A | N/A | N/A |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | $84,000.00 | $45,629.81 | N/A | N/A | N/A |
Electrical and Mechanical Parts and Installation for Transmitter Building | $20,000.00 | $20,000.00 | N/A | N/A | N/A |
RF Accessories | $818.65 | $818.65 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $18,157.48 | $18,157.48 | N/A | $2,351.48 | N/A |
Total for all systems | $385,592.23 | $292,214.54 | N/A | $17,003.08 | N/A |
Primary Antenna 4DR-16-2HW | $18,157.48 | $18,157.48 | $2,351.48 | ||
Coax Andrew, hangers, standoffs, EIA connectors | $4,598.00 | $4,598.00 | N/A | N/A | N/A |
Tower rigging, removal of existing panel antenna, and installation of new panel antenna | $2,351.48 | $2,351.48 | N/A | $2,351.48 | N/A |
UHF-Low Power, Top Mount, Slotted Coaxial, 15.0kW input, Horizontal | $11,208.00 | $11,208.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Coax Andrew, hangers, standoffs, EIA connectors | Information not provided. |
Tower rigging, removal of existing panel antenna, and installation of new panel antenna | |
UHF-Low Power, Top Mount, Slotted Coaxial, 15.0kW input, Horizontal | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $179,609.00 | $123,419.00 | N/A | $0.00 | N/A |
Total for all systems | $385,592.23 | $292,214.54 | N/A | $17,003.08 | N/A |
Primary Tower TOWER | $179,609.00 | $123,419.00 | $0.00 | ||
Ice Bridge | $4,840.00 | $4,840.00 | N/A | N/A | N/A |
Kintronics 150 Complete Isocoupler to avoid impairment of AM signal | $9,250.00 | $9,250.00 | N/A | N/A | N/A |
Rigging Services including freight, travel, per diem, labor on site and at plant | $109,329.00 | $109,329.00 | N/A | N/A | N/A |
Tower Rigging Short Tower (less than 500') | $56,190.00 | $0.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $19,402.10 | $20,584.60 | N/A | $14,651.60 | N/A |
Total for all systems | $385,592.23 | $292,214.54 | N/A | $17,003.08 | N/A |
Outside Professional Services | $19,402.10 | $20,584.60 | $14,651.60 | ||
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | $1,100.00 | N/A |
Prepare request for Special Temporary Authorization | $1,280.00 | $510.70 | N/A | $510.70 | N/A |
Perform engineering study for displacement application | $1,800.00 | $2,475.00 | Additional expenses were incurred as indicated in the attached invoices. | $2,475.00 | Additional expenses were incurred as indicated in the attached invoices. |
Prepare/ Review 399 reimbursement form | $1,710.00 | $3,379.30 | Additional expenses were incurred as indicated in the attached invoices. | $3,379.30 | Additional expenses were incurred as indicated in the attached invoices. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $2,235.00 | $1,842.50 | Additional expenses were incurred as indicated in the attached invoices. | $1,842.50 | Additional expenses were incurred as indicated in the attached invoices. |
Additional Displacement Legal Services Not Otherwise Specified in Form 399 | $4,619.60 | $4,619.60 | Additional expenses were incurred as indicated in the attached invoices. | $4,619.60 | Additional expenses were incurred as indicated in the attached invoices. |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | $724.50 | N/A |
Actual Information Description | File Name |
---|---|
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Prepare request for Special Temporary Authorization | |
Perform engineering study for displacement application | |
Prepare/ Review 399 reimbursement form | |
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Additional Displacement Legal Services Not Otherwise Specified in Form 399 | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $640.00 | $640.00 | N/A | $0.00 | N/A |
Total for all systems | $385,592.23 | $292,214.54 | N/A | $17,003.08 | N/A |
Other Expenses | $640.00 | $640.00 | $0.00 | ||
FCC Filing Fees - Special Temporary Authorization request | $305.00 | $305.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $335.00 | N/A | N/A | N/A |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $385,592.23 | $292,214.54 | $17,003.08 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | James W. DeChant VP of Technology 12/07/2020 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | James W. DeChant VP of Technology 12/07/2020 |