Facility ID:
24263
Service:
LPD
Call Sign:
KMYA-LD
Channel:
25 (UHF)
File Number:
0000089533
FRN:
0027379551
Eligibility Status:
Eligible
Date Submitted:
07/22/2020

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

LR Telecasting LLC

William H. Pollack

855 Ridge Lake Blvd.

Suite 304

Memphis, TN 38120

United States

+1 (901) 685-3993 whpollack@gmail.com Limited Liability Company

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

William H. Pollack

Manager LLC

LR Telecasting LLC

William H. Pollack

855 Ridge Lake Blvd.

Suite 304

Memphis, TN 38120

United States

+1 (901) 685-3993 whpollack@gmail.com

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan Replace transmitter, antenna, transmission line and related equipment that cannot be re-tuned or is not reusable in the displacement-channel facility.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Ownership Owned
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model 1.2 kW Modular EL Wireless UHF System - Ch 47
Year 2016
Type Solid State
Solid State Cooling Air Cooled
Solid State Power Capacity 1.2 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? No
Manufacturer
Model TRN 5X-U-28-C2
Transmitter Type Solid State
Solid State Cooling Air Cooled
Solid State Power capacity 2 kW
Justification for New Transmitter Existing transmitter is for Channel 47. It cannot be retuned to operate on Channel 25, our new channel as a result of the displacement.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Other Transmitter Costs
Does the transmitter installation require a Transmitter Building Site Survey/Installation? Yes
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Rigid Conduit and Wiring No
Other Electrical Service No
HVAC Service Does the replacement transmitter require HVAC Service? No
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Ownership Owned
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? No
Existing Antenna Manufacturer and Type
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Panel
Number of Stations Supported 1
Number of Panels 4
Design power capacity in use 60.0 %
Lower Limit 470.00 MHz
Upper Limit 704.00 MHz
ERP: 15.0 kW
Manufacturer
Model SWLP 16OI
Year 2009

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Change Type Purchase New
Ownership Owned
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? No
New Antenna Manufacturer and Types
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Panel
Number of Stations Supported 1
Number of Panels/Bays 4
Lower Limit 470.00 MHz
Upper Limit 608.00 MHz
Design power capacity in use 70.0 %
ERP: 15.0 kW
Manufacturer
Model UTV01E
Year 2017
Justification for New Antenna Due to channel change, tower location and mounting constraints.

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Elbow Complex Do you require the separate purchase of the Elbow Complex? No
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna? Yes
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? No
Power Dividers Does the panel antenna require power dividers? Yes
Number of Power Dividers 1
Cable Harness Does the panel antenna require cable harness? Yes
Number of Cable Harnesses 4

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Purchase New
Use Primary (Main)
Ownership Owned
Is the existing transmission line shared with another station or stations? No
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer
Type Flexible Air
Diameter 3 inches
Number of parallel runs 1
Length 550 feet per run

Primary Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? No
Type Flexible Air
Diameter Other
Other Diameter 2 1/4 inches
Number of parallel runs 1
Length 550 feet per run
Justification for New Transmission Line Move of tower site.
Interior RF Systems Does the Installation of the Transmission Line require an additional or replacement Inside RF system including switching, patch panels, and dehydrators? Yes

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

RFS Digital Line Dehydrator

Dehydrator

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Move Equipment
Tower Use Primary (Main)
Ownership Leased
Is this tower consider Complex? No
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users No
Is tower documented for structural analysis? Unknown
Is tower compliant with Rev G? Unknown
Existing Tower Structure Registration Do you have a tower registration number? No
Coordinates (NAD83) Latitude (NAD83) 34° 47' 31.3" N-
Longitude (NAD83) 092° 28' 38.6" W-
Overall Structure Height 187.00 feet
Support Structure Height 187.00 feet
Ground Elevation Above Mean Sea Level (AMSL) 909.00 feet
Structure Type TOWER - Free Standing or Guyed Structure
Tower Owner Arkansas Broadcasting Foundation
Date Constructed 01/01/1984

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
2772 KABF FM

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower N/A
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Information not provided.

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 300
Explanation The station lacks sufficient internal resources to complete the channel relocation without project management assistance.
Outside RF consulting Engineering Services Perform engineering study for displacement application Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Prepare Form 601 No
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement Yes
Form 399 assistance or other program management costs Yes
RF Field Engineering Services Comprehensive coverage verification via field study No
RF exposure measurements Yes
Additional Field Engineering Service No

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Name Description

Project Management

Project planning, transacting with vendors, harmonizing schedules, overseeing installations and testing.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Permit and Filing Costs FCC Construction Permit Major Change No
FCC Construction Permit Minor Change Yes
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? No
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? No
Point to Point Microwave (STL/ICR) Frequency Coordination for Unidirection System No
Frequency Coordination for Bi-Direction System No
New Point to Point Microwave System No

Other Expenses

Back to Top

Other Expenses Not Listed

Information not provided.

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $94,000.00 $39,600.00 N/A $39,600.00 N/A
Total for all systems $287,660.00 $188,560.00 N/A $76,100.00 N/A
Primary Transmitter TRN 5X-U-28-C2 $94,000.00 $39,600.00 $39,600.00
Transmitter Building Site Survey/Installation $10,000.00 $6,000.00 N/A $6,000.00 N/A
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW $84,000.00 $33,600.00 N/A $33,600.00 N/A

Components

Actual Information Description File Name
Transmitter Building Site Survey/Installation

Component Description:
Minor survey, installation, proof
Amount:
$6,000.00
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW

Component Description:
New Transmitter
Amount:
$33,600.00

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $16,925.00 $16,925.00 N/A $7,000.00 N/A
Total for all systems $287,660.00 $188,560.00 N/A $76,100.00 N/A
Primary Antenna UTV01E $16,925.00 $16,925.00 $7,000.00
Cable harness (each, for panel antenna system, if not included in antenna cost) $4,000.00 $4,000.00 N/A N/A N/A
Power Dividers (each, for panel antenna system, if not included in antenna cost) $1,300.00 $1,300.00 N/A N/A N/A
Side Mount antenna brackets $4,625.00 $4,625.00 N/A N/A N/A
UHF Broadband panel antenna (per panel), horizontally-polarized $7,000.00 $7,000.00 N/A $7,000.00 N/A

Components

Actual Information Description File Name
Cable harness (each, for panel antenna system, if not included in antenna cost) Information not provided.
Power Dividers (each, for panel antenna system, if not included in antenna cost) Information not provided.
Side Mount antenna brackets Information not provided.
UHF Broadband panel antenna (per panel), horizontally-polarized

Component Description:
Antenna Panel Array
Amount:
$7,000.00

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $29,500.00 $29,500.00 N/A $29,500.00 N/A
Total for all systems $287,660.00 $188,560.00 N/A $76,100.00 N/A
Primary Transmission Line $29,500.00 $29,500.00 $29,500.00
RFS Digital Line Dehydrator $2,175.00 $2,175.00 N/A $2,175.00 N/A
Interior RF Systems: Inside RF system including switching, patch panels and dehydrators $2,500.00 $2,500.00 N/A $2,500.00 N/A
Flexible Air Transmission Line - 2 1/4" 1 parallel runs 550 feet $24,825.00 $24,825.00 The line diameter is 2-1/4". This size is not one of the sizes shown in the drop-down menu, so we entered it in the 'other' category. For this reason the Form 399 did not generate a value in the 'Predetermined Cost' column. The actual cost is $24,825. $24,825.00 N/A

Components

Actual Information Description File Name
RFS Digital Line Dehydrator

Component Description:
RFS Digital Line Dehydrator
Amount:
$2,175.00
Interior RF Systems: Inside RF system including switching, patch panels and dehydrators

Component Description:
MISC RFS system
Amount:
$2,500.00
Flexible Air Transmission Line - 2 1/4" 1 parallel runs 550 feet

Component Description:
Coax cable
Amount:
$24,825.00

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $56,190.00 $35,000.00 N/A $0.00 N/A
Total for all systems $287,660.00 $188,560.00 N/A $76,100.00 N/A
Primary Tower TOWER $56,190.00 $35,000.00 $0.00
Tower Rigging Short Tower (less than 500') $56,190.00 $35,000.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $86,795.00 $63,285.00 N/A $0.00 N/A
Total for all systems $287,660.00 $188,560.00 N/A $76,100.00 N/A
Outside Professional Services $86,795.00 $63,285.00 $0.00
RF Exposure Measurements $12,100.00 $10,000.00 N/A N/A N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $2,235.00 $2,235.00 N/A N/A N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $3,262.50 $3,200.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $1,577.50 $1,500.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $3,025.00 $3,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,052.50 $1,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $2,102.50 $2,100.00 N/A N/A N/A
Prepare request for Special Temporary Authorization $1,280.00 $1,200.00 N/A N/A N/A
Perform engineering study for displacement application $1,800.00 $1,800.00 N/A N/A N/A
Form 399 assistance or other Program Management costs $10,000.00 $10,000.00 N/A N/A N/A
Prepare/ Review 399 reimbursement form $1,710.00 $1,700.00 N/A N/A N/A
Project management of the transition $31,650.00 $10,550.00 N/A N/A N/A
Project Management $15,000.00 $15,000.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $4,250.00 $4,250.00 N/A $0.00 N/A
Total for all systems $287,660.00 $188,560.00 N/A $76,100.00 N/A
Other Expenses $4,250.00 $4,250.00 $0.00
Equipment Delivery and Handling Charges $2,500.00 $2,500.00 N/A N/A N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $335.00 N/A N/A N/A
FCC Filing Fees - Form 2100 minor change CP application $1,110.00 $1,110.00 N/A N/A N/A
FCC Filing Fees - Special Temporary Authorization request $305.00 $305.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $287,660.00 $188,560.00 $76,100.00

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. Yes
Construction of final facilities or all necessary modifications are complete. Yes
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

William H. Pollack

Manager, LLC


07/22/2020

Certification

Back to Top
Section Question Response
Submission of Final Allocation or Accounting Information Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  2. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  3. The above-named entity certifies that all costs identified as "actual costs" herein accurately represent the costs actually paid by the above-named entity, including any discounts, refunds, or rebates.

  4. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  5. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  6. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

William H. Pollack

Manager, LLC


07/22/2020

Attachments