Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
BOARD OF GOVERNORS OF MISSOURI STATE UNIVERSITY Doing Business As: BOARD OF GOVERNORS OF MISSOURI STATE UNIVERSITY |
Rachel Knight 901 S. NATIONAL AVE. SPRINGFIELD, MO 65897 United States |
+1 (417) 836-5878 | RACHELKNIGHT@MISSOURISTATE.EDU | Government Entity |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Matthew Anderson Sanderford , Jr. . President Marsand, Inc. 211 Pack Saddle Trail Weatherford, TX 76088 |
Matthew Sanderford 211 Pack Saddle Trail Weatherford, TX 76088 United States |
+1 (817) 783-5566 | engineering@marsand.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | See attached narrative transition plan. The transition plan has been modified due to the collapse of KOZK's broadcast tower. It is attached and titled: KOZK Modified Transition Plan-Interim. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | DHD20P1 | |
Year | 2003 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 5.5 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | Yes | |
Manufacturer | ||
Model | ULXTE-12 | |
Transmitter Type | Solid State | |
Solid State Cooling | Liquid Cooled | |
Solid State Power capacity | 8.5 kW | |
Justification for New Transmitter | Please see attached document KOZK RF Budget Changes Summary with explanation. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Interim |
Description of Use | N/A | |
Change Type | Lease New | |
Manufacturer | ||
Model | UAXT | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | .9 kW | |
Justification for New Transmitter | Rental transmitter is the quickest procurement to return KOZK to a medium power operation following the tower collapse. Rental transmitter will only be used until a larger interim transmitter can be purchased and installed. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | No | |
Description | N/A | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Type | N/A | |
Size | N/A | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A | |
Inside RF System | Is an additional interior RF system required to support this interim transmitter? | No |
Name | Description |
---|---|
RF Line and Components |
7/8" line from transmitter to existing 3-1/8" line and 7/8" to 3" adaptor |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Ownership | Owned | |
Owner | N/A | |
Is antenna shared? | No | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | No | |
New Antenna Manufacturer and Type | Class | Full Power |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Slot | |
Number of Stations Supported | 1 | |
Number of Panels/Bays | 16 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 698.00 MHz | |
Design power capacity in use | 25.0 % | |
Other Antenna Type | N/A | |
ERP: | 100.0 kW | |
Manufacturer | ||
Model | TFU-WB-16 | |
Year | 2018 | |
Justification for New Antenna | This antenna is an off-shelf antenna designed for quick installation and very low wind load, critical requirements to return KOZK to medium power operation. Antenna will support pre and post auction channels. |
Section | Question | Response |
---|---|---|
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Broadband or Single Channel? | N/A | |
Feed Line Size | N/A | |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for an antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | Yes |
Name | Description |
---|---|
Antenna Installation |
The tower owner already scheduled a tower crew to be on site. KOZK installed the interim antenna at the same time, reducing rigging cost. |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | Other | |
Other Segment Length | 18.4 feet | |
Number of parallel runs | 1 | |
Length | 1942 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Rigid | |
Diameter | 6 1/8 inches | |
Other Diameter | N/A | |
Segment Length | Broadband | |
Other Segment Length | N/A | |
Number of parallel runs | 1 | |
Length | 2100 feet per run | |
Justification for New Transmission Line | Existing transmission line stick length does not support CH16. Broadband length will accommodate both Ch 23 and Ch 16. |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Interim |
Description of Use | N/A | |
Change Type | Purchase New | |
Type | Flexible Air | |
Diameter | 3 inches | |
Segment Length | N/A | |
Other Segment Length | ||
Number of parallel runs | 1 | |
Length | 1100 feet per run | |
Justification for New Transmission Line | Interim transmission line used as contingence plan only in the event extensive tower modification and main transmission line replacement can not be completed by November 2018. |
Name | Description |
---|---|
Interim Line and Antenna Installation |
Cost to install interim line and antenna |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | No | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1007736 | |
Coordinates (NAD83) | Latitude (NAD83) | 37° 10' 11.0" N- |
Longitude (NAD83) | 092° 56' 31.0" W- | |
Overall Structure Height | 1959.62 feet | |
Support Structure Height | 1893.35 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 1564.94 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Board of Governors of Missouri State University | |
Date Constructed | 08/01/2003 |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | Study needed for documented tower |
Tower Reinforcements | Please select whether tower reinforcements are needed: | Serious Reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 200 | |
Explanation | The station has multiple transmitter sites (2 TV) and operates with minimal staff. It does not have personnel available for any of these tasks, nor is the staff trained to provide any of these services. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 2 | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | Yes | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No | |
Number of Days | N/A | |
Justification | N/A |
Name | Description |
---|---|
Site Survey |
Site visit to determine final equipment needs and installation planning |
Additional Legal Expenses |
Additional legal expenses due to collapsed tower, revised transition plan, need for interim operations at interim site and Phase 1 assignment |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | No | |
Does this relocation require Equipment Storage? | No | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | Yes |
Name | Description |
---|---|
IP STL |
IP STL to provide Transport Stream from Master Control to transmitter. RF STL damaged in tower collapse. |
Required bid advertising |
Advertising costs are incurred as state statutes require projects/equipment with a value of $100,000 or greater be advertised to reach potential bidders. |
site check |
Site check to determine constraints and installation of transmitter requirements |
Rescan Helpline |
Charges incurred from call center for assisting viewers with rescan information |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $532,300.00 | $304,530.18 | N/A | $271,389.14 | N/A |
Total for all systems | $2,753,962.50 | $3,464,429.67 | N/A | $1,029,389.43 | N/A |
Interim Transmitter UAXT | $37,800.00 | $37,800.00 | $4,658.96 | ||
RF Line and Components | $1,800.00 | $1,800.00 | N/A | $1,519.07 | N/A |
UHF - Air Cooled Solid State Transmitter .9 kW | $36,000.00 | $36,000.00 | Rental cost is $3,000 per month. Estimated cost includes 12 months rental. Number of months is unknown, but not expected to exceed 12 months. | $3,139.89 | N/A |
Primary Transmitter ULXTE-12 | $494,500.00 | $266,730.18 | $266,730.18 | ||
UHF - Liquid Cooled Solid State Transmitter 8.2 - 13 kW | $494,500.00 | $266,730.18 | N/A | $266,730.18 | N/A |
Actual Information Description | File Name |
---|---|
RF Line and Components | |
UHF - Air Cooled Solid State Transmitter .9 kW | |
UHF - Liquid Cooled Solid State Transmitter 8.2 - 13 kW |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $117,755.00 | $151,185.49 | N/A | $11,708.00 | N/A |
Total for all systems | $2,753,962.50 | $3,464,429.67 | N/A | $1,029,389.43 | N/A |
Interim Antenna TFU-WB-16 | $117,755.00 | $151,185.49 | $11,708.00 | ||
Antenna Installation | $21,625.00 | $21,625.00 | N/A | $7,208.00 | N/A |
Sweep test of existing antenna | $6,730.00 | $6,550.00 | N/A | $4,500.00 | N/A |
UHF - Lower Power Side Mount, One station antenna - medium power (50-200 kW), horizontally polarized | $89,400.00 | $123,010.49 | Antenna selected due to the emergency nature of returning KOZK to medium power operation. Antenna is off-shelf, low wind loading (required by tower owner), and broadband (support pre and post channels. Cost includes mounting brackets and shipping. | N/A | N/A |
Actual Information Description | File Name |
---|---|
Antenna Installation | |
Sweep test of existing antenna | |
UHF - Lower Power Side Mount, One station antenna - medium power (50-200 kW), horizontally polarized | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $652,100.00 | $625,700.00 | N/A | $309,889.75 | N/A |
Total for all systems | $2,753,962.50 | $3,464,429.67 | N/A | $1,029,389.43 | N/A |
Interim Transmission Line | $164,900.00 | $161,600.00 | $0.00 | ||
Interim Line and Antenna Installation | $100,000.00 | $100,000.00 | N/A | N/A | N/A |
Flexible Air Transmission Line - dielectric, 3" | $64,900.00 | $61,600.00 | N/A | N/A | N/A |
Primary Transmission Line | $487,200.00 | $464,100.00 | $309,889.75 | ||
Rigid Transmission Line - copper, 6 1/8" broadband | $487,200.00 | $464,100.00 | N/A | $309,889.75 | N/A |
Actual Information Description | File Name |
---|---|
Interim Line and Antenna Installation | Information not provided. |
Flexible Air Transmission Line - dielectric, 3" | Information not provided. |
Rigid Transmission Line - copper, 6 1/8" broadband |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $1,275,100.00 | $2,209,000.00 | N/A | $369,770.00 | N/A |
Total for all systems | $2,753,962.50 | $3,464,429.67 | N/A | $1,029,389.43 | N/A |
Primary Tower TOWER | $1,275,100.00 | $2,209,000.00 | $369,770.00 | ||
Tall Tower (greater than 500') | $210,500.00 | $0.00 | Tower Rigging cost is include in tower modification cost. | N/A | N/A |
Serious tower reinforcement/modifications | $1,052,000.00 | $2,200,000.00 | See station transition plan | $361,530.00 | N/A |
Structural engineering tower load study for well documented tower | $12,600.00 | $9,000.00 | N/A | $8,240.00 | N/A |
Actual Information Description | File Name |
---|---|
Tall Tower (greater than 500') | Information not provided. |
Serious tower reinforcement/modifications | |
Structural engineering tower load study for well documented tower |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $110,200.00 | $108,056.50 | N/A | $54,225.81 | N/A |
Total for all systems | $2,753,962.50 | $3,464,429.67 | N/A | $1,029,389.43 | N/A |
Outside Professional Services | $110,200.00 | $108,056.50 | $54,225.81 | ||
Additional Legal Expenses | $30,000.00 | $30,000.00 | State University public TV station serving rural areas requires additional legal services due to collapsed tower, interim operations at interim site, Phase 1 assignment and need to new repack plan to meet timeline. | $21,962.28 | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $7,360.00 | $7,170.00 | N/A | $5,000.50 | N/A |
Attorney Fees - Negotiation of lease and other matters for shared locations | $4,210.00 | $4,095.00 | Negotiate site lease for interim site for post-transition operations. | $702.00 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | $391.00 | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $5,260.00 | $6,481.50 | Estimated cost increased based on actual incurred costs. | $6,481.50 | Additional costs related to preparation, filing, and management of construction permit. |
Prepare request for Special Temporary Authorization | $2,050.00 | $1,500.00 | N/A | $0.00 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | $2,250.00 | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | $6,161.28 | N/A |
Address transition timing and coordination issues w/ other stations and wireless | $2,630.00 | $2,560.00 | N/A | N/A | N/A |
Prepare and or review reimbursement form | $2,630.00 | $2,500.00 | N/A | $1,546.50 | N/A |
Project management of the transition | $31,600.00 | $30,000.00 | N/A | $9,730.75 | N/A |
Site Survey | $10,000.00 | $10,000.00 | N/A | $0.00 | N/A |
Actual Information Description | File Name |
---|---|
Additional Legal Expenses | |
Attorney Fees - Prepare and File request for Special Temporary Authorization | |
Attorney Fees - Negotiation of lease and other matters for shared locations | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | |
Prepare request for Special Temporary Authorization | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | |
Perform engineering study for new channel assignment and antenna development | |
Address transition timing and coordination issues w/ other stations and wireless | Information not provided. |
Prepare and or review reimbursement form | |
Project management of the transition | |
Site Survey | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $66,507.50 | $65,957.50 | N/A | $12,406.73 | N/A |
Total for all systems | $2,753,962.50 | $3,464,429.67 | N/A | $1,029,389.43 | N/A |
Other Expenses | $66,507.50 | $65,957.50 | $12,406.73 | ||
Rescan Helpline | $700.00 | $700.00 | N/A | $611.77 | N/A |
site check | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Required bid advertising | $4,000.00 | $4,000.00 | State of Missouri statutes require advertising for projects/equipment with a value of $100,000 or greater. | $3,222.01 | N/A |
IP STL | $4,257.50 | $4,257.50 | Estimated cost has been adjusted to reflect freight/shipping charges which were not reflected in the original quote. | $4,257.50 | The $95 variance from the original estimated cost reflects required shipping charges. Detailed documentation attached. |
MVPD Notification of Channel Change | $11,000.00 | $11,000.00 | Send notification to cable companies, MVPD locations, follow up on signal reception after repack switch. | $1,549.55 | N/A |
Develop and air announcement of upcoming channel change | $5,000.00 | $5,000.00 | Spot creation, talent, production. | N/A | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $20,000.00 | $20,000.00 | Remove existing Sigma Diamond CD transmitter to make room for new transmitter, including Glycol draining and disposal. | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $11,000.00 | N/A | $2,765.90 | N/A |
Actual Information Description | File Name |
---|---|
Rescan Helpline | |
site check | Information not provided. |
Required bid advertising | |
IP STL | |
MVPD Notification of Channel Change | |
Develop and air announcement of upcoming channel change | Information not provided. |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
DTV Medical Facility Notification |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $2,753,962.50 | $3,464,429.67 | $1,029,389.43 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | Yes |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | James P. Baker Vice President, Missouri State University 08/04/2020 |
Section | Question | Response |
---|---|---|
Submission of Final Allocation or Accounting Information Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | James P. Baker Vice President, Missouri State University 08/04/2020 |