Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
SANDER OPERATING CO. III LLC D/B/A KGW TELEVISION |
Denise A. Branson, Sr. Paralegal TEGNA, Inc. 8350 Broad Street, Suite 2000 Tysons, VA 22102 United States |
+1 (703) 873-6606 | dbranson@TEGNA.com | Limited Liability Company |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
Gary Davis Regional Head of Technology and Operat TEGNA, Inc. |
Gary Davis 8350 Broad Street, Suite 2000 Tysons, VA 22102 United States |
+1 (404) 873-9199 | gadavis@tegna.com |
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | Yes |
Briefly describe transition plan | Replace transmitter and mask filter, replace antenna by leasing existing broadband with rigging for installation of horizontal cable, plus new 3 channel combiner to share antenna with KPXG-TV and KPXG-LD. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | AT71KZ | |
Year | 2009 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 1 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | UAXTE-3R37 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 1800 W | |
Justification for New Transmitter | Existing transmitter could not be retuned from channel 46 to 23 |
Section | Question | Response |
---|---|---|
Other Transmitter Costs | ||
Does the transmitter installation require a Transmitter Building Site Survey/Installation? | No | |
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | Yes | |
Transformer (480V) | No | |
Rigid Conduit and Wiring | No | |
Other Electrical Service | No | |
HVAC Service | Does the replacement transmitter require HVAC Service? | No |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Name | Description |
---|---|
Mask Filter |
6-Pole filter |
Other |
Other |
Receiver |
ATSC Receiver with ASI output |
RF Kit |
Transmission line kit |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Lease New |
Antenna Use | Primary (Main) | |
Ownership | Owned | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | No | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | Yes | |
Existing Antenna Manufacturer and Type | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Slotted Coaxial | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | TFU-24GBH-R06 | |
Year | 2008 |
Section | Question | Response |
---|---|---|
New Antenna Description | Use | Primary (Main) |
Change Type | Lease New | |
Ownership | Leased | |
Owner | Ion Media | |
Is antenna shared? | Yes | |
Is antenna directional? | No | |
Will antenna be located on or in close proximity to an antenna farm? | Yes | |
New Antenna Manufacturer and Types | ||
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 3 | |
Number of Panels/Bays | 56 | |
Lower Limit | 470.00 MHz | |
Upper Limit | 600.00 MHz | |
Design power capacity in use | 90.0 % | |
ERP: | 15.0 kW | |
Manufacturer | ||
Model | TFU-04-41/56H-1-T | |
Year | 2019 | |
Justification for New Antenna | Existing antenna could not accommodate channel 23 |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | Yes |
Type | New | |
Number of channels supported | 3 | |
Frequencies of channels supported | RF channel | |
Elbow Complex | Do you require the separate purchase of the Elbow Complex? | No |
Side Mount Brackets | Do you require the separate purchase of side mount brackets for a high power antenna? | No |
Pattern Scatter Analysis | Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? | No |
Sweep Test | Do you require the sweep testing of transmission line and antenna? | No |
Power Dividers | Does the panel antenna require power dividers? | No |
Cable Harness | Does the panel antenna require cable harness? | No |
RF Channel Number |
---|
32 |
23 |
30 |
Name | Description |
---|---|
Connection Fee |
Connection Fee |
Channel Combiner |
3 channel Combiner to add KGWZ-D into the existing leased antenna system |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Ownership | Owned | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Air | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 1000 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Flexible Air | |
Diameter | 1 5/8 inches | |
Number of parallel runs | 1 | |
Length | 300 feet per run | |
Justification for New Transmission Line | Line to extend to adjacent building to lease existing shared antenna system. | |
Interior RF Systems | Does the Installation of the Transmission Line require an additional or replacement Inside RF system including switching, patch panels, and dehydrators? | No |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Modify Existing |
Tower Use | Primary (Main) | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | Yes | |
One or more FM, AM or TV radio broadcaster(s) | Yes | |
Others Types of Users | No | |
Is tower documented for structural analysis? | Unknown | |
Is tower compliant with Rev G? | Unknown | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1204059 | |
Coordinates (NAD83) | Latitude (NAD83) | 45° 31' 20.5" N- |
Longitude (NAD83) | 122° 44' 49.5" W- | |
Overall Structure Height | 925.84 feet | |
Support Structure Height | 820.86 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 1123.02 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | Sander Operating Co. III LLC | |
Date Constructed | 02/14/2000 |
Facility ID | Call Sign | Service |
---|---|---|
34874 | KGW | DTV |
71080 | KOXO-CD | DTV |
71079 | KORK-CD | DTV |
71078 | KKEI-CD | DTV |
71074 | KOXI-CD | DTV |
71069 | KORS-CD | DTV |
69792 | KPXG-LD | LPD |
5801 | KPXG-TV | DTV |
50589 | KOPB-TV | DTV |
Section | Question | Response |
---|---|---|
Engineering Study | Please what type of engineering study is required, if any: | No study needed |
Tower Reinforcements | Please select whether tower reinforcements are needed: | No reinforcements needed |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 12 | |
Explanation | Review progress, prepare and submit Form 387 quarterly, as well as three special FCC required reports | |
Outside RF consulting Engineering Services | Perform engineering study for displacement application | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Prepare Form 601 | No | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | Yes |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | Yes | |
Quantity | 1 | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Form 399 assistance or other program management costs | Yes | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | No |
Name | Description |
---|---|
FAA |
FAA 7460-1 Notification of height and/or location as well as frequency and power changes |
ASR |
ASR amendment |
Other Engineering Services |
Engineering services not specifically listed in Form 399 |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Permit and Filing Costs | FCC Construction Permit Major Change | No |
FCC Construction Permit Minor Change | No | |
FCC License to Cover Application | No | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Point to Point Microwave (STL/ICR) | Frequency Coordination for Unidirection System | No |
Frequency Coordination for Bi-Direction System | No | |
New Point to Point Microwave System | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $136,997.88 | $108,835.74 | N/A | $57,453.86 | N/A |
Total for all systems | $605,445.30 | $323,753.22 | N/A | $212,019.75 | N/A |
Primary Transmitter UAXTE-3R37 | $136,997.88 | $108,835.74 | $57,453.86 | ||
Receiver | $4,973.73 | $4,973.73 | See attached / uploaded PDF file titled, "HVS 71064 v200410pmv1" | $0.00 | N/A |
Mask Filter | $5,645.88 | $5,645.88 | N/A | N/A | N/A |
RF Kit | $2,562.27 | $2,562.27 | N/A | N/A | N/A |
Other | $1,616.00 | $1,616.00 | This component is for Polaris Electric invoice 5977 | $1,616.00 | N/A |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | $84,000.00 | $55,837.86 | N/A | $55,837.86 | N/A |
Switchgear - industrial 800 amp | $38,200.00 | $38,200.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Receiver | |
Mask Filter | Information not provided. |
RF Kit | Information not provided. |
Other | |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | |
Switchgear - industrial 800 amp | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $246,554.66 | $148,554.66 | N/A | $148,554.66 | N/A |
Total for all systems | $605,445.30 | $323,753.22 | N/A | $212,019.75 | N/A |
Primary Antenna TFU-04-41/56H-1-T | $246,554.66 | $148,554.66 | $148,554.66 | ||
Channel Combiner | $138,554.66 | $138,554.66 | 3-channel combiner for KGWZ, KPXG-TV and KPXG-LD. Quote from RFS | $138,554.66 | N/A |
Connection Fee | $10,000.00 | $10,000.00 | See attached / uploaded PDF file titled, "ION IN-1060 v200410pmv1" | $10,000.00 | N/A |
UHF Broadband panel antenna (per panel), horizontally-polarized | $98,000.00 | $0.00 | There is no cost for an actual antenna because the plan is to utilize / lease existing broadband antenna. See quote for 3-channel combiner. | N/A | N/A |
Actual Information Description | File Name |
---|---|
Channel Combiner | |
Connection Fee | |
UHF Broadband panel antenna (per panel), horizontally-polarized | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $13,556.00 | $5,206.06 | N/A | $1,550.06 | N/A |
Total for all systems | $605,445.30 | $323,753.22 | N/A | $212,019.75 | N/A |
Primary Transmission Line | $13,556.00 | $5,206.06 | $1,550.06 | ||
TLSCRs | $3,656.00 | $3,656.00 | See attached /uploaded PDF file titled "Die 728033 v200624pmv1". | $0.00 | N/A |
Flexible Air Transmission Line - dielectric, 1 5/8" | $9,900.00 | $1,550.06 | Extend line to adjacent building and add combiner to utilize existing broadband transmission line and antenna. | $1,550.06 | N/A |
Actual Information Description | File Name |
---|---|
TLSCRs | |
Flexible Air Transmission Line - dielectric, 1 5/8" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $157,750.00 | $10,000.00 | N/A | $0.00 | N/A |
Total for all systems | $605,445.30 | $323,753.22 | N/A | $212,019.75 | N/A |
Primary Tower TOWER | $157,750.00 | $10,000.00 | $0.00 | ||
Tower Rigging Tall Tower (greater than 500') | $157,750.00 | $10,000.00 | Install new transmission line on ice bridge to nearby building to access / lease existing broadband antenna system | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $37,148.50 | $37,718.50 | N/A | $2,725.00 | N/A |
Total for all systems | $605,445.30 | $323,753.22 | N/A | $212,019.75 | N/A |
Outside Professional Services | $37,148.50 | $37,718.50 | $2,725.00 | ||
Other Engineering Services | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
ASR | $550.00 | $550.00 | N/A | N/A | N/A |
FAA | $550.00 | $550.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File request for Special Temporary Authorization | $2,235.00 | $2,235.00 | N/A | N/A | N/A |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | $3,025.00 | $3,025.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,052.50 | $1,052.50 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $2,102.50 | $2,102.50 | N/A | N/A | N/A |
Prepare request for Special Temporary Authorization | $1,280.00 | $1,280.00 | N/A | N/A | N/A |
Perform engineering study for displacement application | $1,800.00 | $1,800.00 | N/A | N/A | N/A |
Form 399 assistance or other Program Management costs | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Prepare/ Review 399 reimbursement form | $1,710.00 | $2,280.00 | See attached / uploaded PDF files titled "Osborn 38631 v200716pmv1" and "Osborn 39000 v200716pmv1" | $2,280.00 | N/A |
Project management of the transition | $1,266.00 | $1,266.00 | N/A | $445.00 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $1,577.50 | $1,577.50 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Other Engineering Services | Information not provided. |
ASR | Information not provided. |
FAA | Information not provided. |
Attorney Fees - Prepare and File request for Special Temporary Authorization | Information not provided. |
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Prepare request for Special Temporary Authorization | Information not provided. |
Perform engineering study for displacement application | Information not provided. |
Form 399 assistance or other Program Management costs | Information not provided. |
Prepare/ Review 399 reimbursement form | |
Project management of the transition | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | Information not provided. |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $13,438.26 | $13,438.26 | N/A | $1,736.17 | N/A |
Total for all systems | $605,445.30 | $323,753.22 | N/A | $212,019.75 | N/A |
Other Expenses | $13,438.26 | $13,438.26 | $1,736.17 | ||
Equipment Delivery and Handling Charges | $3,438.26 | $3,438.26 | See the attached invoices and quotes where applicable. | $1,736.17 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $10,000.00 | $10,000.00 | N/A | N/A | N/A |
Actual Information Description | File Name |
---|---|
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $605,445.30 | $323,753.22 | $212,019.75 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | No |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Jeffrey C Gehman Engineering Associate 07/16/2020 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Jeffrey C Gehman Engineering Associate 07/16/2020 |