Applicant | Address | Phone | Applicant Type | |
---|---|---|---|---|
A1A TV, INC. Doing Business As: A1A TV, INC. |
FREDERICK CAMPBELL 126 HERCULES ROAD ST. AUGUSTINE, FL 32086 United States |
+1 (904) 794-6774 | gm@wqxt.com | Corporation |
Applicant | Address | Phone | |
---|---|---|---|
[Confidential] |
|
|
|
Applicant | Address | Phone | |
---|---|---|---|
The Preparer is same as the reimbursement contact. |
|
|
|
Question | Response |
---|---|
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. | No |
Briefly describe transition plan | Channel change from CH 28 to CH 29. Side mount required for antenna to match CP CH 29 broadcast footprint and ERP. New transmission line required. Transmitter will be replaced to satisfy the new repack facilities assignment. |
Section | Question | Response |
---|---|---|
Transmitter Related Expenses | Do you have transmitter related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmitter Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is this transmitter currently shared with another station? | No | |
Is this transmitter currently in operating condition? | Yes | |
Existing Transmitter Manufacturer and Type | Manufacturer | |
Model | SBTXU1000RFD | |
Year | 2015 | |
Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power Capacity | 1.0 kW |
Section | Question | Response |
---|---|---|
New Transmitter | Use | Primary (Main) |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Manufacturer | ||
Model | TMU9-2 | |
Transmitter Type | Solid State | |
Solid State Cooling | Air Cooled | |
Solid State Power capacity | 1.2 kW | |
Justification for New Transmitter | The manufacturer cannot confirm the transmitter can be retuned. Amplifiers are over 10 years old and no longer being made or serviced. |
Section | Question | Response |
---|---|---|
Electrical Service | Service Entrance (3 phases 800A 208V) | No |
Switchgear (industrial 800 amp) | No | |
Transformer (480V) | No | |
Power | N/A | |
Rigid Conduit and Wiring | No | |
Size | N/A | |
Length | N/A | |
Other Electrical Service | Yes | |
Description | New AC power service and wiring | |
HVAC Service | Does the replacement transmitter require HVAC Service? | Yes |
Type | Cooling Only | |
Size | 10 tons | |
Other Size | N/A | |
Transmitter Building Addition/Modification or Leasehold Improvement | Does the Transmitter Building require an addition, modification, other leashold improvement? | No |
Size | N/A | |
Channel 14 Costs | Is an RF Consulting Engineer needed? | N/A |
Is a channel 14 Mask Filer needed? | N/A | |
Is additional field engineering time needed? | N/A | |
Number of Days | N/A |
Name | Description |
---|---|
Installation |
Install, test and proof transmitter |
Section | Question | Response |
---|---|---|
Antenna Related Expenses | Do you have antenna related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Antenna Description | Type of change | Retune Existing |
Antenna Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing antenna shared with another station or stations? | No | |
Is the existing antenna directional? | Yes | |
Is antenna in operating condition? | Yes | |
Is antenna located on or in close proximity to an antenna farm? | No | |
Existing Antenna Manufacturer and Type | Class | Class A |
Mounting | Side Mount | |
Antenna position in stack | Not in Stack | |
Polarization | Horizontal | |
Type | Broadband Panel | |
Number of Stations Supported | 1 | |
Number of Panels | 12 | |
Design power capacity in use | 9.3 % | |
Lower Limit | 470.00 MHz | |
Upper Limit | 698.00 MHz | |
Other Antenna Type | N/A | |
ERP: | 15.0 kW | |
Manufacturer | Dielectric | |
Model | TUAM-6/12-C2SP | |
Year | 2015 |
Section | Question | Response |
---|---|---|
Sweep Test of Existing Antenna | Do you need a sweep test of existing antenna? | Yes |
Section | Question | Response |
---|---|---|
Combiner for Shared Antenna | Do you need a Combiner for a Shared Antenna? | No |
Type | ||
Number of channels supported | N/A | |
Frequencies of channels supported | N/A | |
Frequency |
Section | Question | Response |
---|---|---|
Transmission Line Related Expenses | Do you have transmission line related expenses? | Yes |
Section | Question | Response |
---|---|---|
Existing Transmission Line Description | Type of change | Purchase New |
Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Owner | N/A | |
Site | N/A | |
Is the existing transmission line shared with another station or stations? | No | |
Is Transmission Line in operating condition? | Yes | |
Existing Transmission Line Manufacturer and Type | Manufacturer | |
Type | Flexible Foam | |
Diameter | 1 5/8 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 0 | |
Length | 400 feet per run |
Section | Question | Response |
---|---|---|
New Transmission Line Costs | Use | Primary (Main) |
Description of Use | N/A | |
Change Type | Purchase New | |
Is this a request for upgraded equipment? | No | |
Type | Flexible Foam | |
Diameter | 1 5/8 inches | |
Other Diameter | N/A | |
Segment Length | N/A | |
Other Segment Length | N/A | |
Number of parallel runs | 0 | |
Length | 475 feet per run | |
Justification for New Transmission Line | New side mount required for antenna to match CP CH 29 broadcast footprint and ERP, which will need a new transmission line |
Section | Question | Response |
---|---|---|
Tower Equipment or Rigging Costs Changes | Do you have tower equipment or rigging costs changes? | Yes |
Section | Question | Response |
---|---|---|
Existing Tower Description | Type of change | Move Equipment |
Tower Use | Primary (Main) | |
Description of Use | N/A | |
Ownership | Owned | |
Is this tower consider Complex? | No | |
Is this tower currently shared with any other stations? | No | |
One or more FM, AM or TV radio broadcaster(s) | N/A | |
Others Types of Users | N/A | |
Is tower documented for structural analysis? | Yes | |
Is tower compliant with Rev G? | Yes | |
Existing Tower Structure Registration | Do you have a tower registration number? | Yes |
ASR Number | 1034197 | |
Coordinates (NAD83) | Latitude (NAD83) | 29° 54' 15.0" N- |
Longitude (NAD83) | 081° 22' 54.0" W- | |
Overall Structure Height | 395.01 feet | |
Support Structure Height | 395.01 feet | |
Ground Elevation Above Mean Sea Level (AMSL) | 35.10 feet | |
Structure Type | TOWER - Free Standing or Guyed Structure | |
Tower Owner | SBA Towers II LLC | |
Date Constructed | 01/01/1987 |
Section | Question | Response |
---|---|---|
Tower Rigging Costs | Complex Tower | N/A |
Helicopter Services Required | Are helicopter services required? | No |
Name | Description |
---|---|
Structural engineering study |
Tower owner requires structural engineering study |
Section | Question | Response |
---|---|---|
Outside Project Management Services | Do you require outside project management services? | Yes |
Number of Hours | 25 | |
Explanation | No technical employee on the station staff. Plan and manage the submission of the form 399, obtain quotes for new equipment and manage tower crew, transmitter testing and proof of performance activities. | |
Outside RF consulting Engineering Services | Perform engineering study for new channel assignment and antenna development | Yes |
Prepare engineering section of Form FCC Construction Permit Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare engineering section of Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
Do you have Distributed Transmission System engineering services? | N/A | |
Critical Facility | N/A | |
Terrain-Shielded Facility | N/A | |
Attorney and Other Outside Consulting Services | Prepare and file Form FCC Construction Permit Application | No |
For Auxiliary Facility | N/A | |
For Main Facility | N/A | |
Prepare and file Form FCC License to Cover Application | Yes | |
For Auxiliary Facility | No | |
For Main Facility | Yes | |
Prepare request for Special Temporary Authority | No | |
Quantity | N/A | |
NEPA Section 106 environmental review | No | |
Environmental Assessment | No | |
ASR Modification | No | |
FAA Consultation (including preparation of FAA Form 7460) | No | |
Negotiation of Lease and other Matter for Shared Locations | No | |
Prepare or Review FCC Form 399 for Reimbursement | Yes | |
Address transition timing and coordination issues w/ other stations and wireless providers | No | |
RF Field Engineering Services | Comprehensive coverage verification via field study | No |
RF exposure measurements | No | |
Additional Field Engineering Service | Yes | |
Number of Days | 5 | |
Justification | Two Days travel and 3 days on site. Install the new transmitter, test, calibrate and proof the transmitter. Sweep the new transmission line with the moved existing antenna. |
Name | Description |
---|---|
Progress reports |
Prepare and file 10 quarterly progress reports with FCC. |
Section | Question | Response |
---|---|---|
AM Pattern Disturbance | Is an Impact Study needed? | No |
Is Remediation needed? | No | |
Facility Expenses | Name | N/A |
Other Distributed Transmission System Expenses Not listed | N/A | |
Name | N/A | |
Is Notification of a Medical Facility required as a result of DTV broadcasting? | Yes | |
Permit and Filing Costs | Local Zoning | No |
Non-zoning permits | No | |
BLM or NFS Coordination | No | |
FCC Construction Permit Minor Change | Yes | |
FCC License to Cover Application | Yes | |
FCC Special Temporary Authority Application | No | |
Other Miscellaneous Expenses | Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? | Yes |
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? | Yes | |
Does this relocation require Equipment Storage? | No | |
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? | Yes | |
Does this relocation require MVPD Notification of a Channel Change? | No |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $177,400.00 | $134,500.00 | N/A | $57,403.50 | N/A |
Total for all systems | $443,965.00 | $403,800.00 | N/A | $88,151.90 | N/A |
Primary Transmitter TMU9-2 | $177,400.00 | $134,500.00 | $57,403.50 | ||
10 Ton system | $38,900.00 | $37,000.00 | N/A | N/A | N/A |
Other Electrical Service: New AC power service and wiring | $5,000.00 | $5,000.00 | N/A | N/A | N/A |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | $126,000.00 | $85,000.00 | N/A | $53,088.50 | N/A |
Installation | $7,500.00 | $7,500.00 | N/A | $4,315.00 | N/A |
Actual Information Description | File Name |
---|---|
10 Ton system | Information not provided. |
Other Electrical Service: New AC power service and wiring | Information not provided. |
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW | |
Installation |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $6,730.00 | $6,400.00 | N/A | $0.00 | N/A |
Total for all systems | $443,965.00 | $403,800.00 | N/A | $88,151.90 | N/A |
Primary Antenna TUAM-6/12-C2SP | $6,730.00 | $6,400.00 | $0.00 | ||
Sweep test of existing antenna | $6,730.00 | $6,400.00 | N/A | N/A | N/A |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $0.00 | $14,725.00 | N/A | $3,164.74 | N/A |
Total for all systems | $443,965.00 | $403,800.00 | N/A | $88,151.90 | N/A |
Primary Transmission Line | $0.00 | $14,725.00 | $3,164.74 | ||
Flexible Foam Transmission Line - dielectric, 1 5/8" | $0.00 | $14,725.00 | New side mount required for antenna to match CP CH 29 broadcast footprint and ERP, which will need a new transmission line | $3,164.74 | N/A |
Actual Information Description | File Name |
---|---|
Flexible Foam Transmission Line - dielectric, 1 5/8" |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $86,200.00 | $82,000.00 | N/A | $7,950.00 | N/A |
Total for all systems | $443,965.00 | $403,800.00 | N/A | $88,151.90 | N/A |
Primary Tower TOWER | $86,200.00 | $82,000.00 | $7,950.00 | ||
Structural engineering study | $2,000.00 | $2,000.00 | N/A | N/A | N/A |
Short Tower (less than 500') | $84,200.00 | $80,000.00 | N/A | $7,950.00 | N/A |
Actual Information Description | File Name |
---|---|
Structural engineering study | Information not provided. |
Short Tower (less than 500') |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $39,040.00 | $40,500.00 | N/A | $13,373.85 | N/A |
Total for all systems | $443,965.00 | $403,800.00 | N/A | $88,151.90 | N/A |
Outside Professional Services | $39,040.00 | $40,500.00 | $13,373.85 | ||
Prepare and or review reimbursement form | $2,630.00 | $5,000.00 | Additional expense was incurred due to unforeseen preparation issues, high attorney fees, and required responses to FCC inquiries. The estimated cost was clearly inaccurate for the amount legal representation necessary. | $4,051.25 | Additional expense was incurred due to unforeseen preparation issues, high attorney fees, and required responses to FCC inquiries. The estimated cost was clearly inaccurate for the amount legal representation necessary. |
Progress reports | $10,000.00 | $10,000.00 | N/A | $737.50 | N/A |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | $2,365.00 | $2,250.00 | N/A | $1,788.75 | N/A |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | $1,580.00 | $1,500.00 | N/A | N/A | N/A |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | $3,155.00 | $3,000.00 | N/A | N/A | N/A |
Perform engineering study for new channel assignment and antenna development | $7,360.00 | $7,000.00 | N/A | $500.00 | N/A |
Project management of the transition | $3,950.00 | $3,750.00 | N/A | $350.00 | N/A |
Additional Field Engineering Service, 5 Days | $8,000.00 | $8,000.00 | Additional field work | $5,946.35 | N/A |
Actual Information Description | File Name |
---|---|
Prepare and or review reimbursement form | |
Progress reports | |
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application | |
Prepare engineering section of FCC Form 2100 (main), License to Cover Application | Information not provided. |
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application | Information not provided. |
Perform engineering study for new channel assignment and antenna development | |
Project management of the transition | |
Additional Field Engineering Service, 5 Days |
Description | Predetermined Cost Estimate |
Estimated Cost | Estimated Cost Justification | Actual Cost | Actual Cost Justification |
---|---|---|---|---|---|
Sub-total | $134,595.00 | $125,675.00 | N/A | $6,259.81 | N/A |
Total for all systems | $443,965.00 | $403,800.00 | N/A | $88,151.90 | N/A |
Other Expenses | $134,595.00 | $125,675.00 | $6,259.81 | ||
Develop and air announcement of upcoming channel change | $116,600.00 | $116,600.00 | Cost to produce and air announcement PSAs and crawls across 9 multicast channels. See attached estimates. | $500.00 | N/A |
Equipment Delivery and Handling Charges | $2,500.00 | $2,500.00 | N/A | $1,674.81 | N/A |
Disposal Costs (for equipment and other waste, net of any salvage value) | $2,500.00 | $2,500.00 | N/A | N/A | N/A |
FCC Filing Fees - Form 2100 license to cover application | $335.00 | $325.00 | N/A | $335.00 | The FCC raised the price of Form 2100 license to cover application from $325 to $335. |
FCC Filing Fees - Form 2100 minor change CP application | $1,110.00 | $0.00 | N/A | N/A | N/A |
DTV Medical Facility Notification | $11,550.00 | $3,750.00 | N/A | $3,750.00 | N/A |
Actual Information Description | File Name |
---|---|
Develop and air announcement of upcoming channel change | |
Equipment Delivery and Handling Charges | |
Disposal Costs (for equipment and other waste, net of any salvage value) | Information not provided. |
FCC Filing Fees - Form 2100 license to cover application | |
FCC Filing Fees - Form 2100 minor change CP application | Information not provided. |
DTV Medical Facility Notification |
Predetermined Cost Estimate |
Estimated Cost | Actual Cost | |
---|---|---|---|
Total for all systems | $443,965.00 | $403,800.00 | $88,151.90 |
Question | Response |
---|---|
The facility has ceased operating on its pre-auction channel. | Yes |
Construction of final facilities or all necessary modifications are complete. | No |
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. | No |
Section | Question | Response |
---|---|---|
Submission of Estimated Expenses Statements | WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT. |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Jill Campbell Coordinator 03/10/2020 |
Section | Question | Response |
---|---|---|
Submission of Actual Cost Documentation Statements | WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733). |
|
I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above. | Jill Campbell Coordinator 03/10/2020 |