(REFERENCE COPY - Not for submission)FCC Form 399: Incentive Auction Relocation Reimbursement Fund System

File Number:
0000054226
FRN:
0004346060
Facility ID:
168834
Repack Channel:
23 (UHF)
Entity:
Broadcaster
Filing Status:
Submitted
Date Submitted:
02/19/2019

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

TRINITY CHRISTIAN CENTER OF SANTA ANA, INC.

Doing Business As: Trinity Broadcasting Network

Colby M. May, Esq.

PO Box 11949

SANTA ANA, CA 92711

United States

+1 (714) 832-2950 CMMAY@MAYLAWOFFICES.COM Not-for-Profit

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

The Preparer is same as the reimbursement contact.

 

 

 

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan WDVB is not sharing facilities in the traditional sense; however, we have a CSA with WTBY (Facility ID 67993). Plan is to replace old transmitter (not retunable) and use modified antenna system

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use  
Ownership Owned
Owner  
Site  
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model SBP 6000W Analog Transmitter / AT7001 Exciter
Year 2003
Type Solid state
IOT Power Type  
Description  
Power capacity  
Solid State Cooling Air
Solid State Power Capacity 2 kw
Other Transmitter Type  

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Description of Use  
Change Type Purchase New
Is this a request for upgraded equipment? No
Manufacturer
Model TMU9-1200
Transmitter Type Solid state
IOT Power Type  
Other  
Power capacity  
Solid State Cooling Air
Solid State Power Capacity 1.2 kw
Other Transmitter Type  
Justification for New Transmitter Existing transmitter could not be retuned

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power
Rigid Conduit and Wiring No
Size
Length
Other Electrical Service No
Description  
HVAC Service Does the replacement transmitter require HVAC Service? No
Type
Size
Other Size  
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size
Channel 14 Costs Is an RF Consulting Engineer needed?
Is a channel 14 Mask Filer needed?
Is additional field engineering time needed?
Number of Days  

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Retune Existing
Antenna Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? No
Existing Antenna Manufacturer and Type Class Class A
Mounting Side-mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Panel
Number of Stations Supported 1
Number of Panels 4
Design power capacity in use 40.0 %
Lower Limit 470.00 MHz
Upper Limit 860.00 MHz
Other Antenna Type N/A
ERP: 7.00 kW
Manufacturer PSI
Model PSIUP-23
Year 2011

Primary Antenna

Back to Top

Adjustment to Existing Antenna

Section Question Response
Sweep Test of Existing Antenna Do you need a sweep test of existing antenna? Yes

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? No
Type
Number of channels supported N/A
Frequencies of channels supported N/A
Frequency

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? No

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? No

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 40
Explanation Management of any work at Empire State Building requires extensive coordination
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development No
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority No
Quantity N/A
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority No
Quantity N/A
NEPA Section 106 environmental review No
Environmental Assessment No
ASR Modification No
FAA Consultation (including preparation of FAA Form 7460) No
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement No
Address transition timing and coordination issues w/ other stations and wireless providers No
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements No
Additional Field Engineering Service No
Number of Days N/A
Justification N/A

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Information not provided.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? No
Permit and Filing Costs Local Zoning No
Non-zoning permits No
BLM or NFS Coordination No
FCC Construction Permit Minor Change Yes
FCC License to Cover Application Yes
FCC Special Temporary Authority Application No
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? No
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? No
Does this relocation require Equipment Storage? No
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? No
Does this relocation require MVPD Notification of a Channel Change? No

Other Expenses

Back to Top

Other Expenses Not Listed

Information not provided.

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $123,000.00 $94,000.00 N/A $79,965.26 N/A
Total for all systems $265,658.00 $185,395.00 N/A $79,965.26 N/A
Primary Transmitter TMU9-1200 $123,000.00 $94,000.00 $79,965.26
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW $123,000.00 $94,000.00 N/A $79,965.26 This is the quoted amount by the vendors

Components

Actual Information Description File Name
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW

Component Description:
Transmitter deposit
Amount:
$13,401.61

Component Description:
Transmitter Installation
Amount:
$21,230.63

Component Description:
Transmitter balance
Amount:
$40,328.21

Component Description:
Commissioning and Testing of transmitter
Amount:
$5,004.81

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $37,070.00 $12,500.00 N/A $0.00 N/A
Total for all systems $265,658.00 $185,395.00 N/A $79,965.26 N/A
Primary Antenna PSIUP-23 $37,070.00 $12,500.00 $0.00
Sweep test of existing antenna $6,550.00 $5,000.00 N/A $0.00 N/A
UHF - Lower Power Side Mount, Class A broadband panel (cost per panel) $4,920.00 $0.00 N/A N/A N/A
UHF - Lower Power Side Mount, Class A One Station antenna -- basic $25,600.00 $7,500.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Transmission Line

Information not provided.

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Information not provided.

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $104,185.00 $77,500.00 N/A $0.00 N/A
Total for all systems $265,658.00 $185,395.00 N/A $79,965.26 N/A
Outside Professional Services $104,185.00 $77,500.00 $0.00
Comprehensive coverage verification via field study, if needed $81,900.00 $60,000.00 N/A N/A N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $4,095.00 $4,000.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,305.00 $0.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,120.00 $4,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,535.00 $1,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,070.00 $2,500.00 N/A $0.00 N/A
Project management of the transition $6,160.00 $6,000.00 N/A N/A N/A

Components

Actual Information Description File Name
Comprehensive coverage verification via field study, if needed Information not provided.
Attorney Fees - Negotiation of lease and other matters for shared locations Information not provided.
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application

Component Description:
Engineering invoice for repack CP (note invoice includes 2 stations - only claiming the amount here for WDVB)
Amount:
$1,250.00
Project management of the transition Information not provided.

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $1,403.00 $1,395.00 N/A $0.00 N/A
Total for all systems $265,658.00 $185,395.00 N/A $79,965.26 N/A
Other Expenses $1,403.00 $1,395.00 $0.00
FCC Filing Fees - Form 2100 license to cover application $333.00 $325.00 N/A N/A N/A
FCC Filing Fees - Form 2100 minor change CP application $1,070.00 $1,070.00 N/A N/A N/A

Components

Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $265,658.00 $185,395.00 $79,965.26

Construction Status

Back to Top
Question Response
Is construction complete? No