Facility ID:
167838
Service:
DCA
Call Sign:
KMMD-CD
Channel:
28 (UHF)
File Number:
0000028153
FRN:
0014625362
Date Submitted:
02/22/2019

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

CABALLERO ACQUISITION LLC

Doing Business As: CABALLERO ACQUISITION LLC

Randy Nonberg

15200 Sunset Blvd

Suite 202

PACIFIC PALISADES, CA 90272

United States

+1 (310) 573-1600 randynonberg@cnzcommunications.com Limited Liability Company

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

Robert Wayne Jordan , Jordan .

Engineer

ACME RF INC

Robert Wayne Jordan

9851 CENTER DRIVE

VILLA PARK, CA 92861

United States

+1 (714) 412-1951 rjordan@acmerf.com

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan The station will remove and replace equipment as required to accomplish the repack. The station will remain off the air while the work is being completed.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model ARK 1
Year 1990
Type Solid State
Solid State Cooling Air Cooled
Solid State Power Capacity 1 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? No
Manufacturer
Model TMU9-3 1.8 kW
Transmitter Type Solid State
Solid State Cooling Air Cooled
Solid State Power capacity 1.8 kW
Justification for New Transmitter Existing TX is not supported by the manufacture

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) Yes
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service No
Description N/A
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Information not provided.

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? No
Existing Antenna Manufacturer and Type Class Class A
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels N/A
Design power capacity in use N/A
Lower Limit N/A
Upper Limit N/A
Other Antenna Type N/A
ERP: 15.0 kW
Manufacturer
Model PSILP8AER
Year 1990

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? No
New Antenna Manufacturer and Types Class Class A
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Elliptical
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 15.0 kW
Manufacturer
Model ALP8L3-ESR-28
Year 2018
Justification for New Antenna Existing antenna will not serve new channel assignment

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? No
Type
Number of channels supported N/A
Frequencies of channels supported N/A
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? N/A
Elbow Complex Do you require the separate purchase of the Elbow Complex? No
Broadband or Single Channel? N/A
Feed Line Size N/A
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna? No
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? No

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Description of Use N/A
Ownership Leased
Is this tower consider Complex? No
Is this tower currently shared with any other stations? No
One or more FM, AM or TV radio broadcaster(s) N/A
Others Types of Users N/A
Is tower documented for structural analysis? Yes
Is tower compliant with Rev G? Unknown
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1051048
Coordinates (NAD83) Latitude (NAD83) 36° 32' 05.0" N-
Longitude (NAD83) 121° 37' 12.7" W-
Overall Structure Height 168.96 feet
Support Structure Height 161.74 feet
Ground Elevation Above Mean Sea Level (AMSL) 3379.88 feet
Structure Type TOWER - Free Standing or Guyed Structure
Tower Owner American Tower, Inc.
Date Constructed 10/09/1997


Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for documented tower
Tower Reinforcements Please select whether tower reinforcements are needed: No reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower N/A
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Information not provided.

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 200
Explanation Station does not have staff or experience able to support this project
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority No
Quantity N/A
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority No
Quantity N/A
NEPA Section 106 environmental review No
Environmental Assessment No
ASR Modification No
FAA Consultation (including preparation of FAA Form 7460) No
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study No
RF exposure measurements No
Additional Field Engineering Service No
Number of Days N/A
Justification N/A

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Information not provided.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? No
Permit and Filing Costs Local Zoning Yes
Non-zoning permits Yes
BLM or NFS Coordination No
FCC Construction Permit Minor Change No
FCC License to Cover Application No
FCC Special Temporary Authority Application No
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? Yes
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? Yes
Does this relocation require MVPD Notification of a Channel Change? No

Other Expenses

Back to Top

Other Expenses Not Listed

Information not provided.

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $140,400.00 $134,050.00 N/A $102,641.37 N/A
Total for all systems $343,520.00 $327,700.00 N/A $167,103.87 N/A
Primary Transmitter TMU9-3 1.8 kW $140,400.00 $134,050.00 $102,641.37
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW $126,000.00 $120,000.00 N/A $102,641.37 N/A
Service entrance 3 phase/800 amp/208 volt $14,400.00 $14,050.00 N/A N/A N/A

Components

Actual Information Description File Name
UHF - Air Cooled Solid State Transmitter 1 - 2.5 kW

Component Description:
SJ Ramer invoice 19010 billing KMMD for transmitter installation services.
Amount:
$20,275.00

Component Description:
Sales tax for the transmitter.
Amount:
$5,816.37

Component Description:
Rohde & Schwarz invoice 9500084961 dated 09Aug2018 including Quote 114987.1 and purchase order.
Amount:
$19,137.50

Component Description:
Final payment for transmitter.
Amount:
$57,412.50
Service entrance 3 phase/800 amp/208 volt Information not provided.

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $33,030.00 $31,400.00 N/A $25,000.00 N/A
Total for all systems $343,520.00 $327,700.00 N/A $167,103.87 N/A
Primary Antenna ALP8L3-ESR-28 $33,030.00 $31,400.00 $25,000.00
UHF - Lower Power Side Mount, Class A One Station antenna -- basic $26,300.00 $25,000.00 N/A $25,000.00 The antenna is an upgrade in equipment. Purchaser will pay for the amount over the estimated cost of the antenna.
Sweep test of existing antenna $6,730.00 $6,400.00 N/A N/A N/A

Components

Actual Information Description File Name
UHF - Lower Power Side Mount, Class A One Station antenna -- basic

Component Description:
ERI Invoice KMMD-001C billing the balance of antenna cost, including letter from engineer, proposal and acceptance of proposal.
Amount:
$16,163.31

Component Description:
ERI Invoice KMMD-001 including a letter from the Engineer. Although total cost of ERI antenna is over the estimated cost, the request for reimbursement will not go over the estimated cost. Purchaser will pay for the difference in cost.
Amount:
$8,836.69
Sweep test of existing antenna Information not provided.

Cost Information

Back to Top

Transmission Line

Information not provided.

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $96,800.00 $92,000.00 N/A $12,975.00 N/A
Total for all systems $343,520.00 $327,700.00 N/A $167,103.87 N/A
Primary Tower TOWER $96,800.00 $92,000.00 $12,975.00
Structural engineering tower load study for well documented tower $12,600.00 $12,000.00 N/A $10,475.00 N/A
Short Tower (less than 500') $84,200.00 $80,000.00 N/A $2,500.00 N/A

Components

Actual Information Description File Name
Structural engineering tower load study for well documented tower

Component Description:
American Tower broadcast structural invoice.
Amount:
$10,475.00
Short Tower (less than 500')

Component Description:
American Tower invoice 460209588 dated 08Feb2019 including proposal and purchase order. Repack capital contribution.
Amount:
$2,500.00

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $60,790.00 $57,750.00 N/A $24,487.50 N/A
Total for all systems $343,520.00 $327,700.00 N/A $167,103.87 N/A
Outside Professional Services $60,790.00 $57,750.00 $24,487.50
Prepare and or review reimbursement form $2,630.00 $2,500.00 N/A $525.00 N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A $0.00 N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $7,000.00 N/A $1,312.50 N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $3,000.00 N/A $1,050.00 N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A $0.00 N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $5,000.00 N/A N/A N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $2,250.00 N/A N/A N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $4,210.00 $4,000.00 N/A N/A N/A
Project management of the transition $31,600.00 $30,000.00 N/A $21,600.00 N/A

Components

Actual Information Description File Name
Prepare and or review reimbursement form

Component Description:
Engineering repack services: Qtr 4 2018 reports and updated form 399 for revised antenna model and description.
Amount:
$525.00
Address transition timing and coordination issues w/ other stations and wireless Information not provided.
Perform engineering study for new channel assignment and antenna development

Component Description:
Engineering services: quote and review for R&S transmitter and ERI antenna.
Amount:
$700.00

Component Description:
Engineering services through August 1, 2018.
Amount:
$262.50

Component Description:
Repack engineering quarterly report.
Amount:
$87.50

Component Description:
Repack engineering services; quarterly progress report.
Amount:
$175.00

Component Description:
Engineering repack services; quarterly progress report submittal.
Amount:
$87.50
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application

Component Description:
Engineering services to prepare construction permit, assist with 399 preparation and review for repacked channel.
Amount:
$525.00

Component Description:
Engineering services to prepare channel repack plan and construction permit exhibits.
Amount:
$525.00
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application Information not provided.
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Negotiation of lease and other matters for shared locations Information not provided.
Project management of the transition

Component Description:
Repack project management services. Research and coordination with engineers, attorney, equipment vendors and site owner.
Amount:
$1,500.00

Component Description:
Repack project management services.
Amount:
$1,500.00

Component Description:
Repack project management services including research and coordination w/rf engineering, attorney and vendors and site owners.
Amount:
$9,600.00

Component Description:
ACME RF invoice 1494 billing for repack project management services, research and coordination with engineer, attorney, vendors and owner.
Amount:
$1,500.00

Component Description:
Repack project management services.
Amount:
$1,500.00

Component Description:
Repack project management services: research and coordination with engineering, attorney, equipment vendors and site owner.
Amount:
$2,250.00

Component Description:
Repack project management services. Research and coordinate with engineers, attorney, equipment vendors and site owner.
Amount:
$2,250.00

Component Description:
Repack project management services: research and coordination with engineering, attorney, equipment vendors and site owner.
Amount:
$1,500.00

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $12,500.00 $12,500.00 N/A $2,000.00 N/A
Total for all systems $343,520.00 $327,700.00 N/A $167,103.87 N/A
Other Expenses $12,500.00 $12,500.00 $2,000.00
Develop and air announcement of upcoming channel change $2,500.00 $2,500.00 N/A $2,000.00 N/A
Equipment Storage $2,000.00 $2,000.00 N/A N/A N/A
Local Zoning $2,000.00 $2,000.00 N/A N/A N/A
Non-zoning permits $2,000.00 $2,000.00 N/A N/A N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $2,000.00 $2,000.00 N/A N/A N/A
Equipment Delivery and Handling Charges $2,000.00 $2,000.00 N/A N/A N/A

Components

Actual Information Description File Name
Develop and air announcement of upcoming channel change

Component Description:
Create a custom database to be used to create documents required to notify establishments that offer medical services of upcoming frequency changes.
Amount:
$2,000.00
Equipment Storage Information not provided.
Local Zoning Information not provided.
Non-zoning permits Information not provided.
Disposal Costs (for equipment and other waste, net of any salvage value) Information not provided.
Equipment Delivery and Handling Charges Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $343,520.00 $327,700.00 $167,103.87

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. No
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Randy E Nonberg

Manager


02/22/2019

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Randy E Nonberg