FCC Form 399: Reimbursement Request

Approved by OMB 3060-1178
Go to the Federal Communications Commission homepage at www.fcc.gov

(REFERENCE COPY - Not for submission) FCC Form 399: Reimbursement Request

Facility ID:
13602
Service:
DTV
Call Sign:
WEDH
Channel:
45 (UHF)
File Number:
0000028127
FRN:
0003574662
Date Submitted:
02/19/2019

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

CONNECTICUT PUBLIC BROADCASTING, INC.

Doing Business As: CONNECTICUT PUBLIC TELEVISION

Meg Sakellarides

1049 ASYLUM AVENUE

HARTFORD, CT 06105

United States

+1 (860) 278-5310 MSAKELLARIDES@CPTV.ORG Not-for-Profit

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

The Preparer is same as the reimbursement contact.

 

 

 

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. Yes
Briefly describe transition plan Purchase of a new transmitter, new transmission line, and new antenna. Retuning of the existing transmitter to the new channel is cost-prohibitive. Interim antenna and transmission line are planned during transition to main antenna.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model DCX Paragon MSDC-IOT
Year 2008
Type Inductive Output Tube
IOT Power Type Two
Power Capacity 36 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model ULXTE-50
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 31.7 kW
Justification for New Transmitter 1) Comark has indicated that retuning the existing transmitter, coupled with the rental of a temporary transmitter, would be higher than the Widelity cost; 2) the temporary rental transmitter would reduce WEDH's public service to its community.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) Yes
Power 150 kVA
Rigid Conduit and Wiring Yes
Size 4 inches
Length 100.0 feet
Other Electrical Service Yes
Description Labor and materials to accomplish either modification of existing electrical service or new electrical service and new wiring for new transmitter and wiring for 480 3-phase.
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Mask Filter

8-Pole Mask Filter

Project Expenses

Other services

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? No
Existing Antenna Manufacturer and Type Class Full Power
Mounting Side Mount
Antenna position in stack Bottom
Polarization Horizontal
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels N/A
Design power capacity in use N/A
Lower Limit N/A
Upper Limit N/A
Other Antenna Type N/A
ERP: 490.0 kW
Manufacturer
Model TFU-16DSC-R C170
Year 2009

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? No
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? No
New Antenna Manufacturer and Types Class Full Power
Mounting Side Mount
Antenna position in stack Bottom
Polarization Horizontal
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 365.0 kW
Manufacturer
Model TFU-16DSC-R C170
Year 2019
Justification for New Antenna Existing antenna is single channel and is channel-specific. Justification for side mount brackets: antenna is top-mounted on candelabra tower but is side mounted in the bottom of the stack and side mounted brackets are required (see attached quote).

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? No
Type
Number of channels supported N/A
Frequencies of channels supported N/A
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? N/A
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? Single Channel
Feed Line Size 7 3/16 inches inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna? Yes
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Name Description

Reducer

6-75 x 7-75

Project Expenses

Other services

Interim Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Interim
Description of Use N/A
Change Type Purchase New
Ownership Owned
Owner N/A
Is antenna shared? Yes
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? No
New Antenna Manufacturer and Type Class Full Power
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Slot
Number of Stations Supported 3
Number of Panels/Bays 16
Lower Limit 470.00 MHz
Upper Limit 665.00 MHz
Design power capacity in use 95.0 %
Other Antenna Type N/A
ERP: 1500.0 kW
Manufacturer
Model TFU-WB16
Year 2020
Justification for New Antenna Interim antenna is necessary for broadcast operation during tower work for 3 stations.

Interim Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? Yes
Type New
Number of channels supported 3
Frequencies of channels supported RF channel
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? No
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? B
Feed Line Size 6 1/8 inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for an antenna? No
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Enter a list of RF channel numbers.

RF Channel Number
31
20
45

Interim Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing transmission line shared with another station or stations? No
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer
Type Rigid
Diameter 7 3/16 inches
Other Diameter N/A
Segment Length 19 1/2 inches
Other Segment Length N/A
Number of parallel runs 1
Length 1480 feet per run

Primary Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? No
Type Rigid
Diameter 7 3/16 inches
Other Diameter N/A
Segment Length 20 inches
Other Segment Length N/A
Number of parallel runs 1
Length 1480 feet per run
Justification for New Transmission Line Current shared transmission line is no longer supported by manufacturer and will not work on new channel.

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Project Expenses

Other services

Interim Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Interim
Description of Use N/A
Change Type Purchase New
Type Rigid
Diameter 6 1/8 inches
Segment Length Broadband
Other Segment Length
Number of parallel runs 1
Length 1450 feet per run
Justification for New Transmission Line Transmission line for temporary operation of 3 stations during antenna changes.

Interim Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Name Description

Interim Internal Transmission Line

Andrews Flexible Air Line, 4in at 80 feet with Reducer & Estimated Freight

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Description of Use N/A
Ownership Leased
Is this tower consider Complex? Candelabra
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users No
Is tower documented for structural analysis? Yes
Is tower compliant with Rev G? Yes
Existing Tower Structure Registration Do you have a tower registration number? No
ASR Number
Coordinates (NAD83) Latitude (NAD83) 41° 42' 13.0" N-
Longitude (NAD83) 072° 49' 55.0" W-
Overall Structure Height 1338.89 feet
Support Structure Height 1291.98 feet
Ground Elevation Above Mean Sea Level (AMSL) 709.97 feet
Structure Type TOWER - Free Standing or Guyed Structure
Tower Owner COMMUNICATIONS SITE MANAGEMENT, LLC
Date Constructed 09/01/1984

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
14050 WCCT-TV DTV
147 WTIC-TV DTV
1910 WRCH FM
66465 WTIC-FM FM
1900 WZMX FM

Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for documented tower
Tower Reinforcements Please select whether tower reinforcements are needed: Minor Reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Candelabra
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Name Description

Tower Lease

Additional tower rent expense for interim antenna and transmission line necessary during transition.

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 695
Explanation Project management services by the transmitter manufacturer and tower landlord.
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 2
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility No
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
NEPA Section 106 environmental review No
Environmental Assessment No
ASR Modification No
FAA Consultation (including preparation of FAA Form 7460) No
Negotiation of Lease and other Matter for Shared Locations Yes
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study Yes
RF exposure measurements Yes
Additional Field Engineering Service Yes
Number of Days 2
Justification Field Engineering required for RF study for a nearby AM directional system.

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Information not provided.

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? Yes
Is Remediation needed? Yes
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning Yes
Non-zoning permits Yes
BLM or NFS Coordination No
FCC Construction Permit Minor Change No
FCC License to Cover Application No
FCC Special Temporary Authority Application No
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? Yes
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? Yes
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? Yes
Does this relocation require MVPD Notification of a Channel Change? Yes

Other Expenses

Back to Top

Other Expenses Not Listed

Name Description

Site Security

Hire of outside security to secure the site during construction

Engineering and Administrative

Internal Project Management

Insurance

Builder's Risk during construction

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $926,487.17 $907,933.97 N/A $295,777.97 N/A
Total for all systems $3,178,065.98 $2,413,537.98 N/A $610,141.67 N/A
Primary Transmitter ULXTE-50 $926,487.17 $907,933.97 $295,777.97
Mask Filter $43,753.12 $43,753.12 N/A $19,514.58 N/A
Project Expenses $0.00 $0.00 N/A N/A N/A
Other Electrical Service: Labor and materials to accomplish either modification of existing electrical service or new electrical service and new wiring for new transmitter and wiring for 480 3-phase. $86,716.18 $86,716.18 N/A $0.00 N/A
4" Rigid Conduit and Wiring (Cost per foot) $10,100.00 $9,600.00 N/A N/A N/A
Transformer 3 phase/480v - 150 KVA $25,550.00 $7,496.80 N/A N/A N/A
UHF - Liquid Cooled Solid State Transmitter 31.7 kW $760,367.87 $760,367.87 N/A $276,263.39 N/A

Components

Actual Information Description File Name
Mask Filter

Component Description:
WEDH-110-1st Primary Transmitter - Mask Filter
Amount:
$16,214.58

Component Description:
WEDH-110-1st Primary Transmitter - Mask Filter
Amount:
$3,300.00
Project Expenses Information not provided.
Other Electrical Service: Labor and materials to accomplish either modification of existing electrical service or new electrical service and new wiring for new transmitter and wiring for 480 3-phase. Information not provided.
4" Rigid Conduit and Wiring (Cost per foot) Information not provided.
Transformer 3 phase/480v - 150 KVA Information not provided.
UHF - Liquid Cooled Solid State Transmitter 31.7 kW

Component Description:
ULXTE-50
Amount:
$229,563.39

Component Description:
ULXTE-50 Transmitter
Amount:
$46,700.00

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $374,150.00 $353,790.00 N/A $82,429.65 N/A
Total for all systems $3,178,065.98 $2,413,537.98 N/A $610,141.67 N/A
Interim Antenna TFU-WB16 $138,630.00 $132,400.00 $0.00
Elbow complex, broadband, at antenna input, per 6 1/8. feedline (if needed) $13,700.00 $12,000.00 N/A N/A N/A
New combiner, cost per channel (without antenna) $84,200.00 $80,000.00 N/A N/A N/A
Sweep test of existing antenna $6,730.00 $6,400.00 N/A $0.00 N/A
UHF - High Power, Side Mount, basic slot antenna, 16 bay,, 1500 kW input, directional,, horizontally polarized $34,000.00 $34,000.00 In resubmission on 8/22/17, item has been reduced to 1/3 the initially submitted amount for sharing of cost with WTIC and WCCT. N/A N/A
Primary Antenna TFU-16DSC-R C170 $235,520.00 $221,390.00 $82,429.65
Project Expenses $0.00 $0.00 N/A N/A N/A
Reducer $2,240.00 $2,240.00 See attached quote from Dielectric supporting cost. N/A N/A
Side mount brackets for high power antennas (if not included in antenna base cost) $23,150.00 $17,752.00 Antenna is top-mounted on candelabra tower but is side mounted in the bottom of the stack of the candelabra and therefore side-mounted brackets are required (see attached quote from Dielectric). $7,988.40 N/A
Elbow complex, single channel, at antenna input, per 7 3/16. feedline (if needed) $13,900.00 $14,998.00 Dielectric Quote 800211CMZ-3A $6,749.10 N/A
Sweep test of existing antenna $6,730.00 $6,400.00 N/A $2,880.00 N/A
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized $189,500.00 $180,000.00 N/A $64,812.15 N/A

Components

Actual Information Description File Name
Elbow complex, broadband, at antenna input, per 6 1/8. feedline (if needed) Information not provided.
New combiner, cost per channel (without antenna) Information not provided.
Sweep test of existing antenna

Component Description:
CT-Hartford-WEDH-Work on interim antenna option; memo - Professional Services
Amount:
$125.00
UHF - High Power, Side Mount, basic slot antenna, 16 bay,, 1500 kW input, directional,, horizontally polarized Information not provided.
Project Expenses Information not provided.
Reducer Information not provided.
Side mount brackets for high power antennas (if not included in antenna base cost)

Component Description:
WEDH Primary Antenna Side Mount Brackets
Amount:
$7,988.40
Elbow complex, single channel, at antenna input, per 7 3/16. feedline (if needed)

Component Description:
WEDH Primary Antenna Elbow Complex
Amount:
$6,749.10
Sweep test of existing antenna

Component Description:
WEDH Primary Antenna Sweep Test
Amount:
$2,880.00
UHF - Lower Power Side Mount, One station - 200-500 kW, horizontally polarized

Component Description:
Antenna - UHF Side/Pole Mount, Rigid Transmission Line - Copper, etc.
Amount:
$64,812.15

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $777,292.41 $375,029.61 N/A $139,115.85 N/A
Total for all systems $3,178,065.98 $2,413,537.98 N/A $610,141.67 N/A
Interim Transmission Line $348,092.41 $91,692.41 $11,692.41
Interim Internal Transmission Line $11,692.41 $11,692.41 Please see attached Dielectric quote 800141CMZ-1 at $10,672.41 and attached Dielectric invoice 203001 for freight costs at $1,020. $11,692.41 N/A
Rigid Transmission Line - copper, 6 1/8" broadband $336,400.00 $80,000.00 In resubmission on 8/22/17, item has been reduced to 1/3 the initially submitted amount for sharing of cost with WTIC and WCCT. $0.00 N/A
Primary Transmission Line $429,200.00 $283,337.20 $127,423.44
Project Expenses $0.00 $0.00 N/A N/A N/A
Rigid Transmission Line - copper, 7 3/16" $429,200.00 $283,337.20 Dielectric Quote 800211CMZ-3A $127,423.44 N/A

Components

Actual Information Description File Name
Interim Internal Transmission Line

Component Description:
Reducer 6-50 X 3-50 W/CONN "QS
Amount:
$1,615.00

Component Description:
Flexible Transmission Line
Amount:
$10,077.41
Rigid Transmission Line - copper, 6 1/8" broadband

Component Description:
WEDH FCC Repack Ch 30 Interim transmission line installation
Amount:
$2,398.00
Project Expenses Information not provided.
Rigid Transmission Line - copper, 7 3/16"

Component Description:
WEDH Primary Transmission Line
Amount:
$127,423.44

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $656,600.00 $357,000.00 N/A $65,000.00 N/A
Total for all systems $3,178,065.98 $2,413,537.98 N/A $610,141.67 N/A
Primary Tower TOWER $656,600.00 $357,000.00 $65,000.00
Structural engineering tower load study for well documented tower $12,600.00 $12,000.00 N/A $0.00 N/A
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $200,000.00 N/A N/A N/A
Minor tower reinforcement/modifications $158,000.00 $80,000.00 N/A N/A N/A
Tower Lease $65,000.00 $65,000.00 See attached quote and invoice from Communications Site Management LLC - estimated cost reduced from $167,020.00 to $65,000.00 $65,000.00 N/A

Components

Actual Information Description File Name
Structural engineering tower load study for well documented tower

Component Description:
Tower structural analysis and report.
Amount:
$3,840.00
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) Information not provided.
Minor tower reinforcement/modifications Information not provided.
Tower Lease

Component Description:
Interim Antenna - Tower Rent per Amendment
Amount:
$65,000.00

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $256,030.00 $254,268.00 N/A $23,976.75 N/A
Total for all systems $3,178,065.98 $2,413,537.98 N/A $610,141.67 N/A
Outside Professional Services $256,030.00 $254,268.00 $23,976.75
Additional Field Engineering Service, 2 Days $4,000.00 $4,000.00 N/A $93.00 N/A
RF Exposure Measurements $21,050.00 $20,000.00 N/A N/A N/A
Comprehensive coverage verification via field study, if needed $84,200.00 $80,000.00 N/A N/A N/A
Attorney Fees - Prepare and File request for Special Temporary Authorization $3,680.00 $3,500.00 N/A N/A N/A
Attorney Fees - Negotiation of lease and other matters for shared locations $4,210.00 $4,000.00 N/A $128.00 N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $2,250.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $5,000.00 N/A $1,581.00 N/A
Prepare request for Special Temporary Authorization $4,100.00 $3,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $1,500.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $3,000.00 N/A $0.00 N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $7,375.00 Du Treil Invoices $2,500.00 N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A $0.00 N/A
Prepare and or review reimbursement form $2,630.00 $3,468.00 Professional Services invoices $2,394.00 N/A
Project management of the transition $109,810.00 $114,675.00 Please see quotes. $17,280.75 N/A

Components

Actual Information Description File Name
Additional Field Engineering Service, 2 Days

Component Description:
Legal services rendered through November 30, 2018.
Amount:
$93.00
RF Exposure Measurements Information not provided.
Comprehensive coverage verification via field study, if needed Information not provided.
Attorney Fees - Prepare and File request for Special Temporary Authorization Information not provided.
Attorney Fees - Negotiation of lease and other matters for shared locations

Component Description:
Attorney - Negotiate Lease and Other Matters
Amount:
$128.00
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application

Component Description:
Legal Services
Amount:
$1,209.00

Component Description:
Attorney - Construction Permit Application (Main)
Amount:
$372.00

Component Description:
Prepare and file Construction Permit Application (Form 2100).
Amount:
$600.00
Prepare request for Special Temporary Authorization Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application Information not provided.
Perform engineering study for new channel assignment and antenna development

Component Description:
CT Hartford-WEDH-Early transition analysis/Phase 4
Amount:
$1,625.00

Component Description:
Engineering study work for new channel assignment and antenna development
Amount:
$500.00

Component Description:
Engineering study work for new channel assignment and antenna development
Amount:
$125.00

Component Description:
CT New Haven-Assist w/channel share-WEDH-App/Map
Amount:
$875.00

Component Description:
Engineering study work for new channel assignment and antenna development
Amount:
$2,000.00
Address transition timing and coordination issues w/ other stations and wireless

Component Description:
Transition timing and coordination.
Amount:
$39.00

Component Description:
Address transition timing and coordination
Amount:
$39.00

Component Description:
Address transition timing and coordination.
Amount:
$172.50
Prepare and or review reimbursement form

Component Description:
Legal services for preparing, reviewing and submitting FCC Reimbursement Form 399
Amount:
$534.00

Component Description:
Prepare and Review Reimbursement Form
Amount:
$325.50

Component Description:
Legal Services
Amount:
$325.50

Component Description:
Legal services for preparing, reviewing and submitting FCC Reimbursement Form 399
Amount:
$540.00

Component Description:
Television Repacking Services - WEDH
Amount:
$627.00

Component Description:
Legal Services
Amount:
$325.50

Component Description:
Legal Services
Amount:
$790.50
Project management of the transition

Component Description:
Project Management
Amount:
$1,577.50

Component Description:
Project Management
Amount:
$4,531.80

Component Description:
Project Management
Amount:
$2,675.40

Component Description:
Project Management
Amount:
$4,373.70

Component Description:
Project Management
Amount:
$1,382.45

Component Description:
Project Management
Amount:
$257.70

Component Description:
Project Management
Amount:
$2,482.20

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $187,506.40 $165,516.40 N/A $3,841.45 N/A
Total for all systems $3,178,065.98 $2,413,537.98 N/A $610,141.67 N/A
Other Expenses $187,506.40 $165,516.40 $3,841.45
Insurance $5,000.00 $5,000.00 N/A N/A N/A
Engineering and Administrative $20,000.00 $20,000.00 N/A N/A N/A
Site Security $10,000.00 $10,000.00 N/A N/A N/A
MVPD Notification of Channel Change $11,000.00 $11,000.00 N/A N/A N/A
Develop and air announcement of upcoming channel change $6,000.00 $6,000.00 N/A N/A N/A
Equipment Storage $15,000.00 $15,000.00 N/A $3,841.45 N/A
Equipment Delivery and Handling Charges $25,000.00 $25,000.00 N/A N/A N/A
Disposal Costs (for equipment and other waste, net of any salvage value) $30,016.40 $30,016.40 See attached quotes from D'Amato and Tri-S for justification. N/A N/A
Non-zoning permits $10,000.00 $10,000.00 N/A N/A N/A
Local Zoning $15,000.00 $15,000.00 N/A N/A N/A
DTV Medical Facility Notification $11,550.00 $11,000.00 N/A N/A N/A
AM Pattern Disturbance -- Remedy $21,050.00 $0.00 Disallowed by FCC as it is duplicated by a request from WTIC. N/A N/A
AM Pattern Disturbance -- Impact study $7,890.00 $7,500.00 N/A N/A N/A

Components

Actual Information Description File Name
Insurance Information not provided.
Engineering and Administrative Information not provided.
Site Security Information not provided.
MVPD Notification of Channel Change Information not provided.
Develop and air announcement of upcoming channel change Information not provided.
Equipment Storage

Component Description:
WEDH FCC Repack Ch 30 Site prep for 2 storage containers
Amount:
$2,556.95

Component Description:
WEDH FCC Repack Ch 30 Rental for 2 storage containers
Amount:
$1,284.50
Equipment Delivery and Handling Charges Information not provided.
Disposal Costs (for equipment and other waste, net of any salvage value) Information not provided.
Non-zoning permits Information not provided.
Local Zoning Information not provided.
DTV Medical Facility Notification Information not provided.
AM Pattern Disturbance -- Remedy Information not provided.
AM Pattern Disturbance -- Impact study Information not provided.

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $3,178,065.98 $2,413,537.98 $610,141.67

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. No
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Meg Sakellarides

Chief Financial Officer


02/19/2019

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Meg Sakellarides

Chief Financial Officer


02/19/2019