Facility ID:
13456
Service:
DTV
Call Sign:
WPBT
Channel:
18 (UHF)
File Number:
0000026469
FRN:
0001822923
Date Submitted:
11/27/2018

Applicant Information

Back to Top

Applicant Name, Type, and Contact Information

Applicant Address Phone Email Applicant Type

South Florida PBS, Inc.

Doing Business As: South Florida PBS, Inc.

Dolores Sukhdeo

14901 N.E. 20TH AVENUE

MIAMI, FL 33181

United States

+1 (305) 424-4250 dsukhdeo@southfloridapbs.org Not-for-Profit

Reimbursement Contact Information

Reimbursement Contact Name and Information

Applicant Address Phone Email

[Confidential]

 

 

 


Preparer Contact Information

Back to Top

Preparer Contact Name and Information

Applicant Address Phone Email

The Preparer is same as the reimbursement contact.

 

 

 

Broadcaster Information and Transition Plan

Back to Top
Question Response
Will the station be sharing equipment with another broadcast television station or stations (e.g., a shared antenna, co-location on a tower, use of the same transmitter room, multiple transmitters feeding a combiner, etc.)? If yes, enter the facility ID's of the other stations and click 'prefill' to download those stations' licensing information. No
Briefly describe transition plan The plan is for WPBT is to replace the existing channel 18 system with a new channel 29 antenna system, transmission line and transmitters. All of the equipment will be owned and operated by SFPBS. See attached narrative.

Transmitters

Back to Top
Section Question Response
Transmitter Related Expenses Do you have transmitter related expenses? Yes

Auxiliary Transmitter

Back to Top

Add Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Auxiliary (Backup)
Description of Use Backup solid state transmitter for IOT Main
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model DTT10KSU Magnum Series
Year 2006
Type Solid State
Solid State Cooling Air Cooled
Solid State Power Capacity 10 kW

Auxiliary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Auxiliary (Backup)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model THU9-EVO
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 25.5 kW
Justification for New Transmitter Interim Main transmitter while permanent Main transmitter facility is constructed on new post auction repack channel (29). Interim transmitter will be re-tuned to new repack channel after the transition.

Auxiliary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service Yes
Description New MDP(Main Distribution Panel) 3 phase breakers, disconnects for transmitter transformers, rigid conduit and wiring, J-Boxes for equipment connections and ground straps for equipment.
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Auxiliary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Interim Transmitter retuning and commissioning

Costs for retuning and commissioning after transition

Auxilliary Transmitter decommissioning

Costs for decommissioning and disposal

Primary Transmitter

Back to Top

Existing Transmitter Information

Section Question Response
Existing Transmitter Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is this transmitter currently shared with another station? No
Is this transmitter currently in operating condition? Yes
Existing Transmitter Manufacturer and Type Manufacturer
Model Sigma CD2200P2
Year 2000
Type Inductive Output Tube
IOT Power Type Two
Power Capacity 44 kW

Primary Transmitter

Back to Top

New Transmitter Costs

Section Question Response
New Transmitter Use Primary (Main)
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Manufacturer
Model THU9-EVO
Transmitter Type Solid State
Solid State Cooling Liquid Cooled
Solid State Power capacity 46 kW
Justification for New Transmitter Our current transmitter manufacture Harris/GatesAir has taken the position that it cannot fully support various discontinued TV transmitter products through the repack. Attached is a letter from GatesAir in support of this.

Primary Transmitter

Back to Top

Other Transmitter Costs

Section Question Response
Electrical Service Service Entrance (3 phases 800A 208V) No
Switchgear (industrial 800 amp) No
Transformer (480V) No
Power N/A
Rigid Conduit and Wiring No
Size N/A
Length N/A
Other Electrical Service Yes
Description Reuse existing fuse blocks,Install additional fuse block, disconnects for transmitter transformers, rigid conduit, J-Boxes for equipment connections, wiring and grounding for equipment.
HVAC Service Does the replacement transmitter require HVAC Service? No
Type N/A
Size N/A
Other Size N/A
Transmitter Building Addition/Modification or Leasehold Improvement Does the Transmitter Building require an addition, modification, other leashold improvement? No
Size N/A
Channel 14 Costs Is an RF Consulting Engineer needed? N/A
Is a channel 14 Mask Filer needed? N/A
Is additional field engineering time needed? N/A
Number of Days N/A

Primary Transmitter

Back to Top

Other Transmitter Cost Not Listed

Name Description

Installation Proposed Non upgraded Transmitter

Installation of non upgraded transmitter

Harris Sigma CD Transmitter decomissioning and disposal

Decommissioning and disposal of existing Harris Sigma CD transmitter

Antennas

Back to Top
Section Question Response
Antenna Related Expenses Do you have antenna related expenses? Yes

Primary Antenna

Back to Top

Existing Antenna Information

Section Question Response
Existing Antenna Description Type of change Purchase New
Antenna Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing antenna shared with another station or stations? No
Is the existing antenna directional? Yes
Is antenna in operating condition? Yes
Is antenna located on or in close proximity to an antenna farm? Yes
Existing Antenna Manufacturer and Type Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels N/A
Design power capacity in use N/A
Lower Limit N/A
Upper Limit N/A
Other Antenna Type N/A
ERP: 1000.0 kW
Manufacturer
Model TFU-24GTH-R P250BNT
Year 2000

Primary Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? Yes
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Types Class Full Power
Mounting Top Mount
Antenna position in stack Not in Stack
Polarization Elliptical
Type Slotted Coaxial
Number of Stations Supported N/A
Number of Panels/Bays N/A
Lower Limit N/A
Upper Limit N/A
Design power capacity in use N/A
Other Antenna Type N/A
ERP: 1000.0 kW
Manufacturer
Model TFU-18GTH/VP-R P250BNT
Year 2018
Justification for New Antenna Existing Dielectric TFU-24GTH-R P250BNT Channel 18 DTV is a single station antenna, which cannot be retuned or modified to operate on our post auction repacked channel 29.

Primary Antenna

Back to Top

Other Antenna Costs

Section Question Response
Combiner for Shared Antenna Do you need a Combiner for a Shared Antenna? No
Type
Number of channels supported N/A
Frequencies of channels supported N/A
Frequency N/A
Do you need a combiner output splitter/switcher for dual feed lines? N/A
Elbow Complex Do you require the separate purchase of the Elbow Complex? Yes
Broadband or Single Channel? Single Channel
Feed Line Size 6 1/8 inches inches
Side Mount Brackets Do you require the separate purchase of side mount brackets for a high power antenna? No
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Primary Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Interim Antenna

Back to Top

New Antenna Costs

Section Question Response
New Antenna Description Use Interim
Description of Use N/A
Change Type Purchase New
Ownership Owned
Owner N/A
Is antenna shared? No
Is antenna directional? No
Will antenna be located on or in close proximity to an antenna farm? Yes
New Antenna Manufacturer and Type Class Class A
Mounting Side Mount
Antenna position in stack Not in Stack
Polarization Horizontal
Type Broadband Slot
Number of Stations Supported 1
Number of Panels/Bays 8
Lower Limit 470.00 MHz
Upper Limit 698.00 MHz
Design power capacity in use 50.0 %
Other Antenna Type N/A
ERP: 76.0 kW
Manufacturer
Model TFU-8WB
Year 2018
Justification for New Antenna The purchase and installation of a new interim antenna will be a crucial part of WPBT's transition plan. WPBT will temporarily move to the low power interim antenna to continue broadcasting while their Main antenna is uninstalled and substituted

Interim Antenna

Back to Top

Other Antenna Costs

Section Question Response
Elbow Complex Do you require the separate purchase of the Elbow Complex? No
Broadband or Single Channel? N/A
Feed Line Size N/A
Side Mount Brackets Do you require the separate purchase of side mount brackets for an antenna? Yes
Pattern Scatter Analysis Do you require separate purchase of pattern scatter analysis for a side mount high or medium power antenna? No
Sweep Test Do you require the sweep testing of transmission line and antenna? Yes

Interim Antenna

Back to Top

Other Antenna Cost Not Listed

Information not provided.

Transmission Line

Back to Top
Section Question Response
Transmission Line Related Expenses Do you have transmission line related expenses? Yes

Primary Transmission Line

Back to Top

Existing Transmission Line

Section Question Response
Existing Transmission Line Description Type of change Purchase New
Use Primary (Main)
Description of Use N/A
Ownership Owned
Owner N/A
Site N/A
Is the existing transmission line shared with another station or stations? No
Is Transmission Line in operating condition? Yes
Existing Transmission Line Manufacturer and Type Manufacturer
Type Rigid
Diameter 6 1/8 inches
Other Diameter N/A
Segment Length 20 inches
Other Segment Length N/A
Number of parallel runs 0
Length 1100 feet per run

Primary Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Primary (Main)
Description of Use N/A
Change Type Purchase New
Is this a request for upgraded equipment? Yes
Type Rigid
Diameter 6 1/8 inches
Other Diameter N/A
Segment Length 19 1/2 inches
Other Segment Length N/A
Number of parallel runs 1
Length 1160 feet per run
Justification for New Transmission Line Existing dielectric 20' rigid 75 OHM Transmission line system is not recommended and considered prohibited per Dielectric catalog at the newly reassigned post auction channel 29.

Primary Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Information not provided.

Interim Transmission Line

Back to Top

New Transmission Line

Section Question Response
New Transmission Line Costs Use Interim
Description of Use N/A
Change Type Purchase New
Type Flexible Air
Diameter 3 inches
Segment Length N/A
Other Segment Length
Number of parallel runs 0
Length 1010 feet per run
Justification for New Transmission Line New interim transmission line and antenna system is required for WPBT's transition plan. In order to ensure a smooth transition and continue broadcasting while the permanent transmission line and antenna are constructed.

Interim Transmission Line

Back to Top

Other Transmission Line Expenses Not Listed

Information not provided.

Tower Equipment And Rigging Costs

Back to Top
Section Question Response
Tower Equipment or Rigging Costs Changes Do you have tower equipment or rigging costs changes? Yes

Primary Tower

Back to Top

Existing Tower

Section Question Response
Existing Tower Description Type of change Modify Existing
Tower Use Primary (Main)
Description of Use N/A
Ownership Leased
Is this tower consider Complex? Candelabra
Is this tower currently shared with any other stations? Yes
One or more FM, AM or TV radio broadcaster(s) Yes
Others Types of Users Yes
Is tower documented for structural analysis? Yes
Is tower compliant with Rev G? Yes
Existing Tower Structure Registration Do you have a tower registration number? Yes
ASR Number 1029604
Coordinates (NAD83) Latitude (NAD83) 25° 57' 31.0" N-
Longitude (NAD83) 080° 12' 43.0" W-
Overall Structure Height 1042.97 feet
Support Structure Height 981.62 feet
Ground Elevation Above Mean Sea Level (AMSL) 6.23 feet
Structure Type GTOWER - Guyed Structure Used for Communication Purposes
Tower Owner IWG Miami
Date Constructed 11/25/1977

FM, AM or TV radio broadcasters. Facility ID's, Call Signs and Services of other broadcast stations with whom the tower is shared

Facility ID Call Sign Service
72984 WFLC FM
48608 WPXM-TV DTV
72982 WHQT FM
40408 WFEZ FM
71418 WEDR FM

Other Types of Users

Users
Government

Primary Tower

Back to Top

Tower Modification Costs

Section Question Response
Engineering Study Please what type of engineering study is required, if any: Study needed for tower with candelabra
Tower Reinforcements Please select whether tower reinforcements are needed: Minor Reinforcements needed

Primary Tower

Back to Top

Tower Rigging Costs

Section Question Response
Tower Rigging Costs Complex Tower Candelabra
Helicopter Services Required Are helicopter services required? No

Primary Tower

Back to Top

Other Tower Expenses Not Listed

Information not provided.

Outside Professional Services Costs

Back to Top
Section Question Response
Outside Project Management Services Do you require outside project management services? Yes
Number of Hours 80
Explanation Outside project management services are required for tower equipment removal and installations as well as tower modifications and rigging planning. This expertise is not available in house.
Outside RF consulting Engineering Services Perform engineering study for new channel assignment and antenna development Yes
Prepare engineering section of Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare engineering section of Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
Do you have Distributed Transmission System engineering services? N/A
Critical Facility N/A
Terrain-Shielded Facility N/A
Attorney and Other Outside Consulting Services Prepare and file Form FCC Construction Permit Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare and file Form FCC License to Cover Application Yes
For Auxiliary Facility Yes
For Main Facility Yes
Prepare request for Special Temporary Authority Yes
Quantity 1
NEPA Section 106 environmental review No
Environmental Assessment No
ASR Modification No
FAA Consultation (including preparation of FAA Form 7460) No
Negotiation of Lease and other Matter for Shared Locations No
Prepare or Review FCC Form 399 for Reimbursement Yes
Address transition timing and coordination issues w/ other stations and wireless providers Yes
RF Field Engineering Services Comprehensive coverage verification via field study No
RF exposure measurements No
Additional Field Engineering Service No
Number of Days N/A
Justification N/A

Outside Professional Services Costs

Back to Top

Other Professional Services Expenses Not Listed

Name Description

Site Survey

Site survey to develop a phased transition plan, BOM, equipment placement and electrical requirements and modifications

Verify As-built documentation of existing Dielectric antenna

Evaluated and resolved as built documentation discrepancy on site in regards to WPBT existing Dielectric antenna. Labor rate and travel for one day

Other Expenses

Back to Top
Section Question Response
AM Pattern Disturbance Is an Impact Study needed? No
Is Remediation needed? No
Facility Expenses Name N/A
Other Distributed Transmission System Expenses Not listed N/A
Name N/A
Is Notification of a Medical Facility required as a result of DTV broadcasting? Yes
Permit and Filing Costs Local Zoning No
Non-zoning permits No
BLM or NFS Coordination No
FCC Construction Permit Minor Change No
FCC License to Cover Application Yes
FCC Special Temporary Authority Application Yes
Other Miscellaneous Expenses Does this relocation require paying Disposal Costs (for equipment and other waste, net of any salvage value)? No
Does this relocation require Equipment Delivery or Handling Charges not otherwise included in individual item costs? Yes
Does this relocation require Equipment Storage? No
Does this relocation require the Development and Airing of an Announcement regarding an upcoming channel change? Yes
Does this relocation require MVPD Notification of a Channel Change? Yes

Other Expenses

Back to Top

Other Expenses Not Listed

Information not provided.

Cost Information

Back to Top

Transmitters

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $2,638,105.60 $1,762,545.62 N/A $1,475,187.29 N/A
Total for all systems $3,938,550.60 $2,722,219.52 N/A $2,052,276.05 N/A
Primary Transmitter THU9-EVO $1,609,276.04 $972,419.11 $733,000.36
Installation Proposed Non upgraded Transmitter $59,225.00 $59,225.00 N/A N/A N/A
Other Electrical Service: Reuse existing fuse blocks,Install additional fuse block, disconnects for transmitter transformers, rigid conduit, J-Boxes for equipment connections, wiring and grounding for equipment. $26,681.04 $26,681.04 N/A $26,681.04 N/A
Harris Sigma CD Transmitter decomissioning and disposal $50,370.00 $50,370.00 N/A $50,370.00 N/A
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW $1,473,000.00 $836,143.07 Estimated costs for the main Transmitter raised by $16,993.07 to cover costs incurred for additional install components per Quote 802.050407.0 and invoice 9500078700 which are attached in the attachment section. $655,949.32 N/A
Auxiliary Transmitter THU9-EVO $1,028,829.56 $790,126.51 $742,186.93
Auxilliary Transmitter decommissioning $23,575.00 $23,575.00 N/A $23,575.00 N/A
Interim Transmitter retuning and commissioning $38,295.00 $38,295.00 N/A N/A N/A
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW $947,000.00 $708,296.95 N/A $698,652.37 N/A
Other Electrical Service: New MDP(Main Distribution Panel) 3 phase breakers, disconnects for transmitter transformers, rigid conduit and wiring, J-Boxes for equipment connections and ground straps for equipment. $19,959.56 $19,959.56 N/A $19,959.56 N/A

Components

Actual Information Description File Name
Installation Proposed Non upgraded Transmitter Information not provided.
Other Electrical Service: Reuse existing fuse blocks,Install additional fuse block, disconnects for transmitter transformers, rigid conduit, J-Boxes for equipment connections, wiring and grounding for equipment.

Component Description:
Second draw on Electrical Install for Main TX
Amount:
$26,681.04
Harris Sigma CD Transmitter decomissioning and disposal

Component Description:
Phase 3 decommissioning of the Main transmitter and disposal of hazardous materials
Amount:
$50,370.00
UHF - Liquid Cooled Solid State Transmitter 35 - 50 kW

Component Description:
Down payment 25% Quote 802-009994.7 WPBT Main TX 46kw CH 29
Amount:
$256,068.75

Component Description:
Down payment Next Milestone 37.38% of Purchase order value of $1,024,275.00 Rohde & Schwarz Quote 802-009994.7 WPBT- Main TX 46KW Ch. 29
Amount:
$382,887.50

Component Description:
Main Transmitter Additional install components required for the installation of the new unit. Quote 802-050407.0 WPBT_Main_additional components_Quotation 802-050407.0.pdf can be found in the attachments section
Amount:
$16,993.07
Auxilliary Transmitter decommissioning

Component Description:
75% Final Payment Quote 802-041755.0 Phase 1 Decommission Existing Aux TX
Amount:
$17,681.25

Component Description:
25% Down payment Quote 802-041755.0 Phase 1 Decommissioning Existing Aux TX
Amount:
$5,893.75
Interim Transmitter retuning and commissioning Information not provided.
UHF - Liquid Cooled Solid State Transmitter 21 - 31 kW

Component Description:
Final Payment 75% Upon Delivery Rohde & Schwarz Quote 802-046428.0 WPBT Interim/Aux TX 25.5KW CH 18
Amount:
$417,112.50

Component Description:
100% Advanced Downpayment Phase 2 - Install new R&S 2 Cabinet Interim Transmitter Quote #802-041757.1
Amount:
$114,792.87

Component Description:
Interim/Aux transmitter additional install components
Amount:
$27,709.50

Component Description:
Downpayment 25% Quote 802-046428.0 WPBT Aux TX 25.5KW CH 18
Amount:
$139,037.50
Other Electrical Service: New MDP(Main Distribution Panel) 3 phase breakers, disconnects for transmitter transformers, rigid conduit and wiring, J-Boxes for equipment connections and ground straps for equipment.

Component Description:
First Draw for electrical services Electrical installation of interim TX
Amount:
$19,959.56

Cost Information

Back to Top

Antennas

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $360,185.00 $261,453.00 N/A $235,307.70 N/A
Total for all systems $3,938,550.60 $2,722,219.52 N/A $2,052,276.05 N/A
Interim Antenna TFU-8WB $51,655.00 $51,325.00 $46,192.50
Sweep test of existing antenna $6,730.00 $6,400.00 N/A $5,760.00 N/A
UHF - Lower Power, Side Mount, Class A, basic slot antenna, 8 bay,, 76 kW input, horizontally polarized $44,925.00 $44,925.00 N/A $40,432.50 N/A
Primary Antenna TFU-18GTH/VP-R P250BNT $308,530.00 $210,128.00 $189,115.20
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed) $12,300.00 $10,984.00 N/A $9,885.60 N/A
Sweep test of existing antenna $6,730.00 $6,400.00 N/A $5,760.00 N/A
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized $289,500.00 $192,744.00 N/A $173,469.60 N/A

Components

Actual Information Description File Name
Sweep test of existing antenna

Component Description:
45% down payment for antenna sweep
Amount:
$2,880.00

Component Description:
Second 45% payment for Sweep testing Interim/Aux antenna
Amount:
$2,880.00
UHF - Lower Power, Side Mount, Class A, basic slot antenna, 8 bay,, 76 kW input, horizontally polarized

Component Description:
45% down payment for Aux Antenna
Amount:
$20,216.25

Component Description:
Second 45% payment (Prior To Ship) for Interim Aux antenna and transmission system
Amount:
$20,216.25
Elbow complex, single channel, at antenna input, per 6 1/8. feedline (if needed)

Component Description:
Second 45% payment for elbow complex
Amount:
$4,942.80

Component Description:
45% down payment for elbow complex
Amount:
$4,942.80
Sweep test of existing antenna

Component Description:
45% down payment for main antenna sweep
Amount:
$2,880.00

Component Description:
Second 45% payment for main antenna sweep
Amount:
$2,880.00
UHF - High Power Top Mount (200-1000 kW), One station antenna , elliptically or circularly polarized

Component Description:
Second 45% payment (Prior To Ship) for Main antenna
Amount:
$86,734.80

Component Description:
45% down payment for Main antenna
Amount:
$86,734.80

Cost Information

Back to Top

Transmission Line

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $234,320.00 $228,130.40 N/A $180,422.10 N/A
Total for all systems $3,938,550.60 $2,722,219.52 N/A $2,052,276.05 N/A
Interim Transmission Line $0.00 $41,410.40 $12,374.10
Flexible Air Transmission Line - dielectric, 3" $0.00 $41,410.40 This flexible broadband transmission line is required to build out an interim transmission facility while the proposed new transmission facility (Antenna and transmission line) is constructed. $12,374.10 N/A
Primary Transmission Line $234,320.00 $186,720.00 $168,048.00
Rigid Transmission Line - copper, 6 1/8" $234,320.00 $186,720.00 N/A $168,048.00 N/A

Components

Actual Information Description File Name
Flexible Air Transmission Line - dielectric, 3"

Component Description:
Second 45% payment( Prior To Ship) For items 2,3,4 and 6 on the invoice. Jumper, transformer, reducer/ adapter to connect to existing transmission line instead of purchasing new aux transmission line.
Amount:
$6,187.05

Component Description:
For items 2,3,4 and 6 on the invoice. Jumper, transformer, reducer/ adapter to connect to existing transmission line instead of purchasing new aux transmission line.
Amount:
$6,187.05
Rigid Transmission Line - copper, 6 1/8"

Component Description:
45% down payment for main antenna transmission line
Amount:
$84,024.00

Component Description:
Second 45% payment for main antenna transmission line
Amount:
$84,024.00

Cost Information

Back to Top

Tower Equipment and Rigging Costs

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $599,000.00 $384,938.00 N/A $127,728.00 N/A
Total for all systems $3,938,550.60 $2,722,219.52 N/A $2,052,276.05 N/A
Primary Tower GTOWER $599,000.00 $384,938.00 $127,728.00
Complex Tower (includes, for example, those with candelabras and/or stacked antennas) $421,000.00 $354,938.00 New proposal, justification letter from Coast to Coast and new rate schedule attached in the attachments section. $124,228.00 N/A
Structural engineering tower load study for a documented tower with candelabra $20,000.00 $5,000.00 N/A $3,500.00 N/A
Minor tower reinforcement/modifications $158,000.00 $25,000.00 N/A N/A N/A

Components

Actual Information Description File Name
Complex Tower (includes, for example, those with candelabras and/or stacked antennas)

Component Description:
Customer Deposit for Repack - Top Arbor Mount TV Antenna System Replacement Services, as agreed in our proposal #12051701T.
Amount:
$37,695.00

Component Description:
Customer Deposit for additional work due to helicopter lift addition to the previous scope of work.
Amount:
$86,533.00
Structural engineering tower load study for a documented tower with candelabra

Component Description:
Tower Structural Analysis-Guyed Tower required for WPBT Miami TV Repack. Proposal is also uploaded in the attachments section
Amount:
$3,500.00
Minor tower reinforcement/modifications Information not provided.

Cost Information

Back to Top

Outside Professional Services

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $69,860.00 $55,990.00 N/A $28,590.00 N/A
Total for all systems $3,938,550.60 $2,722,219.52 N/A $2,052,276.05 N/A
Outside Professional Services $69,860.00 $55,990.00 $28,590.00
Verify As-built documentation of existing Dielectric antenna $2,400.00 $2,400.00 Evaluated and resolved as built documentation discrepancy on site in regards to WPBT existing Dielectric antenna installation. N/A N/A
Site Survey $16,215.00 $16,215.00 N/A $16,215.00 N/A
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application $2,365.00 $2,000.00 N/A N/A N/A
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application $4,210.00 $1,000.00 N/A N/A N/A
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application $5,260.00 $3,000.00 N/A N/A N/A
Prepare engineering section of FCC Form 2100 (main), License to Cover Application $1,580.00 $500.00 N/A N/A N/A
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application $1,580.00 $500.00 N/A N/A N/A
Project management of the transition $12,640.00 $15,000.00 20 additional Program Management hours (Widelity) for management to develop our phased planning for the 399 submission and working with our vendors to develop the budgets and timing for the 399 and throughout the project. $5,375.00 N/A
Address transition timing and coordination issues w/ other stations and wireless $2,630.00 $2,500.00 N/A N/A N/A
Perform engineering study for new channel assignment and antenna development $7,360.00 $3,000.00 N/A $2,875.00 N/A
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application $3,155.00 $2,500.00 N/A $750.00 N/A
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application $2,105.00 $1,500.00 N/A N/A N/A
Prepare request for Special Temporary Authorization $2,050.00 $875.00 N/A $875.00 During the 399 submission process, this figure was an estimated best guess at the time.
Attorney Fees - Prepare and File request for Special Temporary Authorization $3,680.00 $2,500.00 N/A N/A N/A
Prepare and or review reimbursement form $2,630.00 $2,500.00 N/A $2,500.00 N/A

Components

Actual Information Description File Name
Verify As-built documentation of existing Dielectric antenna Information not provided.
Site Survey

Component Description:
Payment in full for site survey to develop equipment lists, services, and transition timing for 399 form.
Amount:
$16,215.00
Attorney Fees -Prepare and File FCC Form 2100 (main), License to Cover Application Information not provided.
Attorney Fees - Aux Antenna, prepare and File Form 2100 Construction Permit or License Application Information not provided.
Attorney Fees - Prepare and File FCC Form 2100 (main), Construction Permit Application Information not provided.
Prepare engineering section of FCC Form 2100 (main), License to Cover Application Information not provided.
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, License to Cover Application Information not provided.
Project management of the transition

Component Description:
First Installment for Program Management Services
Amount:
$3,000.00

Component Description:
Project Management and Consulting Services in connection with WPBT 13456 TV Repack
Amount:
$2,375.00
Address transition timing and coordination issues w/ other stations and wireless Information not provided.
Perform engineering study for new channel assignment and antenna development

Component Description:
Installment, Engineering study work for new channel assignment and antenna development
Amount:
$1,000.00

Component Description:
installment payment, Engineering study work for new channel assignment and antenna development
Amount:
$1,500.00

Component Description:
First installment Engineering Study work for new channel assignment and antenna development
Amount:
$375.00
Prepare engineering section of FCC Form 2100 (main), Construction Permit Application

Component Description:
Engineering study work for new channel assignment and antenna development (Form 2100)
Amount:
$750.00
RF Consulting Engineer Fees- Aux Antenna: Prepare engineering section of FCC Form 2100, Construction Permit Application Information not provided.
Prepare request for Special Temporary Authorization

Component Description:
Consulting Engineers work on WPBT STA request/CH 18
Amount:
$625.00

Component Description:
WPBT Professional Services Revised STA request to increase ERP to 244KW
Amount:
$250.00
Attorney Fees - Prepare and File request for Special Temporary Authorization Information not provided.
Prepare and or review reimbursement form

Component Description:
first installment 399 assistance (help to prepare form 399 for filing)
Amount:
$1,500.00

Component Description:
Final Payment to prepare and review Form 399
Amount:
$1,000.00

Component Description:
Final Payment to prepare and review Form 399
Amount:
$1,000.00

Cost Information

Back to Top

Other Expenses

Where no predetermined cost estimate is available, any estimate provided will also become the predetermined cost (displayed in italics).
Description Predetermined
Cost Estimate
Estimated Cost Estimated Cost Justification Actual Cost Actual Cost Justification
Sub-total $37,080.00 $29,162.50 N/A $5,040.96 N/A
Total for all systems $3,938,550.60 $2,722,219.52 N/A $2,052,276.05 N/A
Other Expenses $37,080.00 $29,162.50 $5,040.96
Develop and air announcement of upcoming channel change $1,500.00 $1,500.00 N/A N/A N/A
MVPD Notification of Channel Change $1,500.00 $1,500.00 N/A $1,500.00 N/A
Equipment Delivery and Handling Charges $22,000.00 $22,000.00 N/A N/A N/A
FCC Filing Fees - Special Temporary Authorization request $195.00 $190.00 N/A N/A N/A
FCC Filing Fees - Form 2100 license to cover application $335.00 $325.00 N/A N/A N/A
DTV Medical Facility Notification $11,550.00 $3,647.50 N/A $3,540.96 N/A

Components

Actual Information Description File Name
Develop and air announcement of upcoming channel change Information not provided.
MVPD Notification of Channel Change

Component Description:
MVPD Notification per guidlines
Amount:
$1,500.00
Equipment Delivery and Handling Charges Information not provided.
FCC Filing Fees - Special Temporary Authorization request Information not provided.
FCC Filing Fees - Form 2100 license to cover application Information not provided.
DTV Medical Facility Notification

Component Description:
Medical Notification per guidelines
Amount:
$3,540.96

Cost Information

Back to Top

Grand Total

Predetermined
Cost Estimate
Estimated Cost Actual Cost
Total for all systems $3,938,550.60 $2,722,219.52 $2,052,276.05

Reimbursement Status

Back to Top
Question Response
The facility has ceased operating on its pre-auction channel. No
Construction of final facilities or all necessary modifications are complete. No
All receipts for reimbursement have been submitted no further costs are expected to be incurred. Note this will lock the Form 399 from further editing and begin close-out procedures with the Fund Administrator. No

Certification

Back to Top
Section Question Response
Submission of Estimated Expenses Statements

WILLFUL FALSE STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT.

  1. The Authorized Person signing below certifies that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  3. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  4. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (broadcasters) or to continue to carry the signal of a broadcaster that changes channels (MVPD).

  5. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  6. The above-named entity certifies that it will maintain and provide to the Commission detailed records, including receipts, of all costs eligible for reimbursement actually incurred.

  7. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  8. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a pre-requisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Gene H. Talley

VP Engineering/Operations


11/27/2018

Certification

Back to Top
Section Question Response
Submission of Actual Cost Documentation Statements

WILLFUL FALSE, FRAUDULENT, OR FICTITIOUS STATEMENTS ON THIS FORM ARE PUNISHABLE BY FINE AND/OR IMPRISIONMENT (U.S. CODE, TITLE 18, SECTION 1001), AND/OR REVOCATION OF ANY STATION LICENSE OR CONSTRUCTION PERMIT (U.S. CODE, TITLE 47, SECTION 312(a)(1), AND/OR FORFEITURE (U.S. CODE, TITLE 47, SECTION 503), AND ANY FALSE AND/OR FRAUDULENT STATEMENTS COULD SUBJECT THIS ENTITY TO LIABILITY UNDER THE FALSE CLAIMS ACT (U.S. CODE, TITLE 31, SECTIONS 3729-3733).

  1. The Authorized Person signing below certifies and represents that he/she is authorized to submit this TV Broadcaster Relocation Fund Reimbursement Form on behalf of the above-named entity.

  2. The above-named entity certifies that the statements in this form and attached documentation are true, complete, and correct.

  3. The above-named entity acknowledges that all certifications and attached documentation are considered material representations.

  4. The above-named entity acknowledges the submission of the information herein creates no obligation on the part of the government to pay any amount.

  5. The above-named entity certifies that the equipment and services paid for with money from the TV Broadcaster Relocation Fund are necessary to change channels (full power and Class A stations) and/or otherwise modify a television station’s facility as a result of the spectrum repack (LPTV/TV Translator stations); or to minimize service disruption resulting from a repacked television station (FM stations); or to continue to carry the signal of a broadcaster that changes channels (MVPD) .

  6. The above-named entity certifies that all payments from the TV Broadcaster Relocation Fund (Fund) received by the entity listed on this form will be used only for expenses that are eligible for reimbursement from the Fund.

  7. The above-named entity certifies that the cost information/documents submitted reflect costs actually incurred.

  8. The above-named entity acknowledges that overpayments or payments in error must be promptly refunded to the Commission.

  9. The above-named entity certifies that it is in full compliance with all statutes, rules, regulations and governmental requirements for which compliance is a prerequisite for obtaining the payments herein requested.

I declare, under penalty of perjury, that I am an authorized representative of the above-named applicant for the Authorization(s) specified above.

Gene H. Talley

VP Engineering/Operations


11/27/2018

Attachments